Sub topic 7
What happens next: suspension, extension of time and termination rights
This chapter covers what a force majeure clause does once the clause applies. The earlier chapters in this tutorial dealt with the clause's anatomy, its construction, and the causation, notice and mitigation conditions. Those conditions only decide whether the clause is triggered. The consequences clause decides what the parties are left with.
It assumes you know the basic elements of a contract, the difference between express and implied terms, and what breach and damages mean. It also assumes you can read a case or statute citation.
Why the consequences matter
Under English law there is no general doctrine of force majeure. The remedy is whatever the clause says it is, and the court will not add to it. A clause can be drafted so the event is well defined and the notice is given on time, and still leave the parties with a dispute. This happens when it says little or nothing about what follows.
Most clauses give one or more of three consequences:
| Consequence | Effect | Typical wording |
|---|---|---|
| Suspension | Obligations are paused while the event continues. | "obligations are suspended" |
| Extension of time | Deadlines move by a period linked to the delay. | "time for performance is extended by the period of delay" |
| Termination | A party may end the contract, often after a long-stop period. | "either party may terminate by written notice" |
These are often combined, as in the illustrative clause from the topic plan. The affected party's obligations are suspended while the event continues. If it lasts more than 90 days, either party may terminate.
While the Force Majeure Event continues, the affected party's obligations (other than payment obligations already due) are suspended and it is not liable for failure or delay in performance. If the event continues for more than 90 days, either party may terminate this Agreement by written notice.Suspension
Suspension means the obligation still exists but is not enforceable for the time being. Two points follow from this.
First, the clause usually excuses liability, not the duty. The affected party is "not liable for failure or delay". Once the event ends, the party must resume performance. Many clauses say so expressly, as in "resume performance as soon as reasonably practicable".
Second, suspension should be read alongside the other terms. Look for these:
- Carve-outs. The sample clause excludes "payment obligations already due". Money owed before the event is still owed. Many clauses go further and exclude all payment obligations. This is a drafting choice, and courts apply it as written. A party that has been paid for work done cannot rely on a clause to avoid paying simply because its bank was disrupted, if the clause excludes payment.
- Scope. The suspension may cover only the obligations the event actually prevents. If the clause covers only the affected obligations, the rest of the contract continues.
- Reciprocal obligations. The clause may or may not suspend the other party's duties. If it does not, the other party may still have to perform, or pay, while receiving nothing. Check whether the clause says "the obligations of both parties" or only those of the affected party.
Extension of time
An extension of time clause is common in construction and supply contracts. It moves the deadline instead of excusing it. The wording typically gives the affected party an extension "equal to the period of delay caused by the event".
The practical issues are these:
- Measuring the delay. The extension should reflect the delay the event actually caused, not the length of the event. If the event lasted 10 days but the project could not restart for 20 because of remobilisation, the clause wording decides which figure counts.
- Concurrent causes. If the delay is partly caused by the event and partly by the party's own default, the clause (or the general rules on causation) decides how it is apportioned. Many clauses give no extension for the part caused by the party itself.
- Knock-on costs. An extension of time protects against liability for delay. It does not by itself entitle the party to extra payment. Unless the clause says so, the party bears its own additional costs, such as idle equipment or extended site costs. Some clauses (and some standard forms) allow time but not money.
- Liquidated damages. If the contract has liquidated damages for delay, an extension of time moves the date from which they run. Without a valid extension, the party faces the full pre-agreed sum for the whole delay.
Termination rights
Termination is the most serious consequence, so it is usually tied to a trigger. The common triggers are:
- the event continuing for a stated period, such as 90 days;
- a stated total of days of suspension, whether continuous or cumulative;
- a requirement that the event "materially affects" the contract.
A long-stop period is a deliberate compromise. The parties accept a pause for a while, and set a point after which neither is made to wait. The right to terminate usually belongs to either party, not only the affected one. This lets the party who is receiving nothing stop waiting.
How termination is exercised
Termination under the clause depends on the clause's own procedure. Check the following:
- Written notice. The sample clause requires "written notice". A phone call or an email sent to the wrong address may be ineffective, especially if the contract has a notices clause setting out how notices must be given.
- Timing. The right arises only once the period has passed. Notice given on day 89 of a 90-day period is premature. A party that purports to terminate early risks being treated as having repudiated the contract itself, which gives the other side a claim for damages.
- Accrued rights. Termination under a clause generally ends future obligations but does not wipe out rights already accrued. A payment due before termination remains due unless the contract says otherwise. Check whether the clause preserves accrued rights. A well-drafted one does.
- No further liability. Clauses often say neither party has any liability to the other as a result of termination. That wording should be read with care, as it may not protect against liabilities that arose earlier.
When the clause is silent on termination
A clause may suspend obligations indefinitely and say nothing about ending the contract. The parties then cannot terminate under the clause, because English law does not imply a right to terminate. The affected party is left suspended, and the other party may be stuck too.
This is where the common law may become relevant. If the delay is long enough, the contract may be frustrated, and frustration discharges the contract automatically. A court will take into account that the parties agreed on a suspension regime when deciding whether the delay really changes the nature of the obligation. A later chapter on the interaction between force majeure and frustration deals with this in detail.
Common errors
- Assuming suspension means the contract is over. It is not. The obligation returns when the event ends.
- Treating the extension as automatic. Many clauses make it conditional on notice, so late notice can lose the extension.
- Ignoring payment carve-outs. The excuse may not cover money.
- Terminating before the long-stop date. Early termination can itself be a breach.
- Assuming a right to terminate exists. If the clause does not give one, the party must look to frustration or other rights.
- Reading the clause as shifting costs. Time relief and cost relief are different things.
Worked example
A supplier agrees to deliver 1,000 units on 1 March. A fire at its factory on 10 February is a listed force majeure event. The supplier gives written notice on 14 February, within the 7-day period. The clause provides suspension, an extension equal to the delay, and termination by either party if the event lasts more than 90 days.
- On 1 March the supplier has not delivered. It is not in breach, because its obligation is suspended.
- The factory is repaired and production restarts on 1 April, 50 days after the fire. Under the clause, the supplier must resume performance, and the delivery date moves by the period of delay. The buyer cannot terminate, because the 90 days has not passed.
- If the factory had still been closed on 12 May, more than 90 days after the fire, either party could terminate by written notice. The buyer, who had been waiting, would then be free to buy elsewhere.
If the supplier had given notice on 25 February instead, the late notice could have cost it the relief, depending on whether the clause makes timely notice a condition.
Exercise
A force majeure clause suspends the affected party's obligations during the event and allows either party to terminate if the event lasts more than 60 days. On day 45, the buyer, tired of waiting, serves written notice terminating the contract. Is the termination effective under the clause? What is the risk to the buyer, and what other route might the buyer consider?
Show answer
The termination is not effective under the clause, because the 60-day period has not passed and the right to terminate has not arisen. The buyer risks being treated as having repudiated the contract, which would give the seller a claim for damages. The buyer could wait until day 60 and then serve notice. Alternatively, it could consider whether the delay is so serious and prolonged that the contract is frustrated, although a court is unlikely to find frustration while the parties' own suspension regime is still running.
Exercise
A clause gives the affected supplier an extension of time equal to the period of delay but says nothing about costs. The supplier incurs extra site costs during the delay and asks the customer to pay them. What is the likely position?
Show answer
The supplier probably cannot recover them. An extension of time protects against liability for late performance, but it does not by itself shift the cost of the delay. Unless the clause or another term gives a right to extra payment, the supplier bears its own costs.