Sub topic 5
Causation, Burden of Proof and Notice Conditions
This chapter assumes you know the points below. It builds on the earlier chapters on the anatomy and interpretation of force majeure clauses.
- How breach of contract and damages work.
- The difference between express and implied terms.
- How English case law and statutes are cited.
A force majeure clause does not give relief just because something bad happened. The party relying on it must prove three things. The event must fall within the clause. The event must have caused the failure to perform in the way the clause requires. The party must have met any procedural conditions, usually notice. This chapter covers the second and third points and who must prove each.
Causation: the link between event and failure
Most clauses connect the event to the failure with a causal word. Common choices are "prevents", "hinders or delays", "as a result of", "caused by" and "arising from". The word chosen sets how strong the link must be.
The illustrative clause from the plan says the event "prevents that party from performing its obligations". A clause that uses "prevents" is read strictly. The event must actually stop performance. It is not enough that performance became harder, slower or less profitable.
| Wording | Typical effect on the claimant |
|---|---|
| "prevents" or "makes impossible" | Must show performance could not be carried out |
| "hinders or delays" | Wider. Slower or more difficult performance can qualify |
| "directly or indirectly caused by" | Wider on remoteness. Knock-on effects may qualify |
| "to the extent that" | Relief is limited to the part of the failure the event caused |
These are guides to how a court may read the words. The exact clause always controls.
The but-for test
English courts generally apply a "but for" test to causation under these clauses. The question is whether the party would have performed if the event had not happened. If it would not have performed anyway, the event did not cause the failure.
Classic Maritime Inc v Limbungan Maritima SA [2019] EWCA Civ 1102 is the leading authority. The clause relieved a party where an event "prevented" performance. The Court of Appeal held that the party must show that, but for the event, it would have performed. Other causes of non-performance defeat the claim.
Seadrill Ghana Operations Ltd v Tullow Ghana Ltd [2018] EWHC 1640 (Comm) points the same way. A party cannot rely on a force majeure event where its failure had another cause, or where it chose not to perform for its own reasons.
Concurrent and competing causes
Real disruptions often have several causes. Courts have not settled every combination. The safest working rules are these:
- If the event is one of several causes, but performance would still have failed without it, the claim fails under a "prevents" clause.
- If the clause says "to the extent that", relief may be partial.
- If the clause says "directly or indirectly", a looser causal chain may be enough.
- A clause can change the default, for example by stating that the event need only be "a" cause. Check for such wording first.
A worked example
A seller agrees to ship 10,000 tonnes of grain from Port A in March. A strike closes Port A for the whole month. The clause covers strikes and applies where an event "prevents" delivery.
The seller's own supplier had in fact already failed to deliver the grain in February. Even with the port open, the seller had no grain to ship.
The strike did not prevent performance in the but-for sense, because the seller could not have shipped anyway. The clause fails on causation. The seller is in breach for the supplier's default, not excused by the strike.
If the seller had the grain and only the strike stopped shipment, the claim would succeed on causation.
Burden of proof
The party who relies on a force majeure clause carries the burden of proving that it applies. This follows the general rule that a party asserting an exemption must prove it. See, for example, Channel Island Ferries Ltd v Sealink UK Ltd [1988] 1 Lloyd's Rep 323.
In practice the claimant must prove:
- The event occurred and falls within the definition, including any catch-all words.
- The event caused the failure in the way the clause requires.
- Notice was given as required.
- Any mitigation or endeavours conditions were met.
The standard is the ordinary civil standard, the balance of probabilities. Clauses sometimes shift the burden or add evidence requirements, for example a certificate from a chamber of commerce. Such a requirement is usually enforced as written.
The other party need not disprove anything until the claimant has made out its case. A party resisting the claim can still raise its own points. It might argue that the event was foreseeable and that the clause was meant to exclude it, or that the claimant's own conduct contributed.
Notice conditions
Most clauses require the affected party to tell the other party about the event. The illustrative clause requires written notice within 7 days of becoming aware of it. The notice must describe the event and its expected duration.
Is notice a condition precedent?
The key question is whether giving notice is a condition of relief. If it is, late or missing notice means no relief, even if the event and causation are proved.
Courts look at the wording. Phrases such as "provided that notice is given" or "shall not be entitled to relief unless" point strongly to a condition precedent. A bare statement that a party "shall give notice", with no stated consequence, is more open to argument. The court may then treat late notice as a breach that gives damages for any loss it caused, but does not strip the relief. Do not rely on that reading. Assume strict compliance is required.
Points to check
- Trigger. Notice may run from the event, from awareness of it, or from the point it affects performance. These dates can differ by weeks.
- Deadline. A fixed period ("within 7 days") is applied as written. "Promptly" or "as soon as reasonably practicable" is judged on the facts.
- Content. The clause may require the event, its effects and its expected duration. A vague notice may fail.
- Form and delivery. Follow the contract's notices clause on writing, addressee and method. Email may not be valid service unless the contract allows it.
- Updates. Some clauses require further notice as the situation changes or when it ends.
Waiver and estoppel
If the other party receives a late notice and acts as though it were valid, for example by negotiating a revised schedule, it may be held to have waived the defect. Do not plan around this. Waiver and estoppel depend on clear conduct and reliance, and a party that stays silent will not always be treated as having waived anything.
Common errors
- Treating a cost increase or a difficulty as "prevention".
- Relying on a general event while ignoring that the party was already unable to perform.
- Missing the notice deadline because the clock started on awareness, not on the event.
- Sending notice to the wrong address or by a method the contract does not allow.
- Assuming the other side must prove the claim is wrong.
Exercise
A buyer's contract says it is excused where a force majeure event "prevents" it from taking delivery, and that relief is available "only if written notice is given within 5 days of the event". A flood closes the buyer's warehouse on 1 June. The buyer would in any case have been unable to pay for the goods because its financing had collapsed in May. The buyer emails notice on 10 June. Identify two separate reasons the buyer's claim is likely to fail, and say who bears the burden of proof.
Show answer
First, causation. Under a "prevents" clause the but-for test applies, and the buyer would not have performed anyway because of the collapsed financing, so the flood did not cause the failure. Second, notice. The clause makes notice a condition ("only if"), and notice was sent on 10 June, outside the 5-day period (which ended on 6 June). The burden is on the buyer, as the party relying on the clause, to prove the event, causation and compliance with the notice condition.
Exercise
Compare the likely effect of the words "prevents" and "hinders or delays" on a party whose delivery was only slowed, not stopped, by a port closure.
Show answer
"Prevents" requires that performance was stopped, so a party that could still deliver, only later or at higher cost, is unlikely to qualify. "Hinders or delays" is wider and can cover slower or more difficult performance, so the party has a stronger claim. The result still depends on the full wording and on proof that the closure caused the delay.