Anatomy of a force majeure clause: events, effect, causation, notice and consequences
Prerequisites and scope
This chapter assumes you know the basic elements of a contract, the difference between express and implied terms, and what breach and damages mean. It also assumes you can read a case citation.
English law has no general doctrine of force majeure. The relief a party gets depends on what the contract says. So the useful skill is reading a clause part by part. This chapter takes the clause apart into five components. Later chapters cover interpretation, causation and notice, mitigation, and consequences in more depth. Here the aim is to know what each part does and how the parts fit together.
Why the parts matter
Parties usually agree to the clause in advance, with no particular disruption in mind. When a disruption happens, the affected party wants relief, and the other party wants to hold it to its promise. Each part of the clause is a gate. The affected party must get through all of them. If it fails at any one, the clause gives no relief and the ordinary rule applies: failure to perform is a breach.
A model clause
Here is an illustrative clause. Real clauses vary in wording, but most contain these elements.
"Force Majeure Event" means any event or circumstance beyond the reasonable control of the affected party, including fire, flood, earthquake, war, act of terrorism, epidemic, or act of government, which prevents that party from performing its obligations under this Agreement.
A party affected by a Force Majeure Event shall (a) give written notice to the other party within 7 days of becoming aware of it, describing the event and its expected duration; (b) use reasonable endeavours to mitigate its effect; and (c) resume performance as soon as reasonably practicable.
While the Force Majeure Event continues, the affected party's obligations (other than payment obligations already due) are suspended and it is not liable for failure or delay in performance. If the event continues for more than 90 days, either party may terminate this Agreement by written notice.The following sections map the clause onto the five gates.
1. The events: the definition
The definition says what counts. Drafters combine two techniques:
- A general test. The words "beyond the reasonable control of the affected party" describe a quality that any event must have. Some clauses say only "beyond the party's control". The word "reasonable" matters. It asks whether the party could sensibly have prevented or avoided the event, not whether it was literally powerless.
- A list of examples. "Fire, flood, earthquake, war..." gives certainty for the common cases. It also sets the tone for how a court may read the rest.
Lists come in two forms. A closed list covers only the named events. An open list uses words such as "including" or "any other event beyond reasonable control". The clause above is open because it says "including". A catch-all at the end of a list may be read narrowly if the words are limited by what comes before, and the later chapter on reading the clause covers this.
Lists of events are only part of the picture. Many clauses also have exclusions, for example "lack of funds", "changes in market conditions" or "failure of a subcontractor". These stop a party from relying on events that the parties thought should stay at that party's risk.
2. The effect: what the event must do
An event on the list does not by itself trigger relief. The clause also says what the event must do to performance. The model clause uses "prevents". Other clauses use weaker verbs:
| Wording | Effect required | Practical consequence |
|---|---|---|
| "prevents" | Performance cannot be carried out | Hardest to satisfy. Making performance harder or costlier does not meet it. |
| "hinders" or "delays" | Performance is impeded or late | Easier to satisfy. Partial disruption can qualify. |
| "makes performance impracticable" | Performance is much harder | Brings in judgment about degree, and invites argument. |
The verb sets the threshold. A party that can still perform, but at a loss, will usually fail under "prevents". The same facts might succeed under "hinders". This is why two clauses that list the same events can give very different outcomes.
3. Causation: the link between event and failure
The clause must connect the event to the failure. Words such as "which prevents", "as a result of" and "caused by" create a causal requirement. The party must show that the event, and not some other reason, led to the failure to perform.
The standard of causation is a question of construction. English courts have applied "but for" causation to some clauses. In Classic Maritime Inc v Limbungan Makina Ltd [2019] EWCA Civ 1102, the Court of Appeal held that a party relying on force majeure had to show that it would have performed but for the event. The party failed because it would not have performed anyway. Other wording may require the event to be the sole or dominant cause. Check the wording before assuming the standard.
Burden of proof usually falls on the party who invokes the clause. The next chapter develops this.
4. Conditions: notice and mitigation
Most clauses make relief conditional on what the affected party does after the event. Two conditions are common.
Notice. The model clause requires written notice within 7 days of becoming aware of the event, stating the event and its expected duration. Courts take notice terms seriously. Where the clause makes notice a condition precedent, failure to give timely notice can cost the party its relief entirely. Where it is only an obligation, failure may lead to a claim for damages but may leave relief intact. The drafting decides which.
Notice clauses also commonly specify:
- how notice must be given (in writing, to a named address);
- from when the time runs ("becoming aware" or the date of the event);
- what the notice must contain.
Mitigation. The party must use "reasonable endeavours" to reduce the effect of the event. This is an obligation to take reasonable steps. It does not usually mean doing anything at all, regardless of cost. The scope of that duty is the subject of a later chapter.
5. Consequences: what relief is available
The last part says what the affected party gains. Typical consequences, often combined, are:
- Suspension. Obligations are paused while the event continues. The model clause suspends them and excludes liability for the delay.
- Extension of time. The date for performance moves back by the period of disruption.
- Termination. If the event lasts beyond a set period, one or both parties can end the contract. The model clause allows either party to terminate after 90 days.
- Excluded obligations. The clause protects payment obligations "already due". Without that carve-out, a party could stop paying for goods it had already received.
Note what the clause does not say. It does not say who bears the cost of the disruption. A suspended contract leaves each party with its own losses unless the clause provides otherwise. If the contract is silent, check the other terms for risk allocation before assuming either party must pay.
Reading the five parts together
The parts interact. A narrow event definition, a strong verb such as "prevents", a strict causation test and a tight notice deadline combine to give a clause that is hard to use. A broad definition, "hinders", loose causation and no notice condition give a generous one. When reviewing a clause, do not judge it on its list of events alone. Ask what a party must do at each of the five gates.
The five-gate check also tells you when to go beyond the clause. If the clause fails at any gate, relief under it is lost, and the question becomes whether the common law doctrine of frustration applies. That doctrine is a separate subject with its own test, and a later chapter covers it.
Exercise
A supplier's contract has a force majeure clause covering "any event beyond the reasonable control of either party which prevents performance". A strike at the supplier's own factory makes production more expensive, but it can still deliver late and at a loss. It gives notice 20 days after the strike began, and the clause requires notice within 7 days. Identify two gates at which the supplier is likely to fail, and explain why.
Show answer
First, the effect gate. The clause requires that the event "prevents" performance, and the supplier can still perform, only at higher cost and later, so a court is unlikely to find that performance is prevented. Second, the notice gate. Notice was given 20 days after the event, outside the 7-day period, so if notice is a condition precedent the supplier loses relief even if the other gates were met. A further issue is whether the strike was beyond the supplier's reasonable control, since a strike at its own factory may be treated as within its control, depending on the clause and the facts.
Exercise
Name the five parts of a force majeure clause covered in this chapter, in the order a party must satisfy them.
Show answer
Events (the definition), effect (what the event must do to performance), causation (the link between event and failure), conditions (notice and mitigation), and consequences (suspension, extension of time or termination).