Sub topic 16
Putting it together: a step-by-step method for a disrupted contract
This chapter assumes you know the basic elements of a contract, the difference between express and implied terms, what breach and damages mean, and how to read case and statute citations. It also assumes you have met the earlier chapters on force majeure clauses, frustration and the Law Reform (Frustrated Contracts) Act 1943. Here you combine them into one repeatable method. The law is stated as it applies in England and Wales.
Why a fixed order matters
A disrupted contract invites a tempting shortcut: "Covid stopped us, so the contract is frustrated." That reasoning skips most of the analysis. The order of questions matters because each stage can make the next one unnecessary.
- The contract's own terms come first. Parties may allocate the risk of disruption themselves, and the court respects that allocation.
- Frustration is a residual doctrine. It applies only where the contract has not dealt with the event.
- Financial consequences come last. They depend on which route applied: a clause, frustration, or neither.
The method below follows that order.
The checklist
1. Does the contract contain a force majeure or similar clause?
- If yes: does the event fall within the wording? Did it cause the failure as the clause requires? Was notice given in time? Were mitigation duties met?
- What relief does the clause give (suspension, extension, termination)?
2. If the clause does not apply or there is none: was the risk allocated elsewhere in the contract?
3. If not: has a supervening event made performance impossible, illegal, or radically different from what was undertaken?
- Was the event foreseen or provided for? Is it self-induced? Is it only a cost increase?
4. If frustrated: the contract ends automatically; apply the Law Reform (Frustrated Contracts) Act 1943 to money paid and benefits conferred.Step 1: the force majeure clause
Start with the text. English law has no general doctrine of force majeure, so the clause is the only source of relief of this kind. Work through four sub-questions.
- Event. Does the event fall within the listed events or the catch-all? Construe the wording by ordinary principles. General words after a list are often read in light of that list, so a catch-all is not a guarantee.
- Causation. Does the clause require that the event "prevents" performance, or only "hinders" or "delays" it? "Prevents" is stricter. If performance remained possible by another route, the party may fail this test. The party relying on the clause normally bears the burden of proving it applies.
- Notice. Was notice given in the form and within the time the clause requires? Where notice is a condition precedent, late notice can lose the relief entirely. Where it is not, late notice may only found a damages claim.
- Mitigation. Did the party meet any duty to use reasonable endeavours? Check what the clause demands. Reasonable endeavours does not usually require a party to take steps that would be commercially ruinous, but it can require accepting reasonable alternatives.
Then identify the relief. The common forms are suspension of obligations, extension of time, and a right to terminate after a long-stop period. Payment obligations already due are often carved out.
Step 2: other risk allocation
If the clause does not apply, look at the rest of the contract before turning to frustration. Terms that may allocate the risk include:
- price adjustment or indexation clauses
- change-in-law provisions
- termination for convenience rights
- liability caps and exclusions
- an express promise to perform whatever happens
If the contract already deals with the event, frustration is unavailable. The parties made their bargain, and the court will not rewrite it.
Step 3: frustration
Only now ask whether the common law doctrine applies. The test is whether a supervening event, without default of either party, makes performance impossible, illegal, or radically different from what was undertaken. Apply these filters:
- Radical difference, not hardship. Performance that is merely harder, slower or more expensive does not frustrate the contract.
- Foreseeability. An event that was foreseen, or that the contract provided for, weighs strongly against frustration.
- Self-induced events. A party cannot rely on frustration brought about by its own choice or fault.
- Cost increases. A rise in price alone is the classic case that fails.
Frustration is hard to establish. Courts treat it as a narrow doctrine because it overrides the parties' agreement.
Step 4: financial consequences
If the contract is frustrated, it ends automatically at the time of the event. Neither party needs to elect or give notice. Under the 1943 Act, money paid before the frustrating event is recoverable, and money payable before it ceases to be payable. The court may allow the payee to keep or recover a sum for expenses incurred, up to the amount paid or payable. A party who obtained a valuable benefit before the event may also have to pay a just sum for it. Contracts outside the Act's scope, such as certain insurance and sale of goods cases, need separate checking.
A worked example
A supplier agrees to deliver 500 tonnes of steel to a buyer in March at a fixed price. In February a government order bans exports of that steel type. The contract contains this clause:
"Force Majeure Event" means any event or circumstance beyond the reasonable control of the affected party, including fire, flood, earthquake, war, act of terrorism, epidemic, or act of government, which prevents that party from performing its obligations under this Agreement.
A party affected by a Force Majeure Event shall (a) give written notice to the other party within 7 days of becoming aware of it, describing the event and its expected duration; (b) use reasonable endeavours to mitigate its effect; and (c) resume performance as soon as reasonably practicable.
While the Force Majeure Event continues, the affected party's obligations (other than payment obligations already due) are suspended and it is not liable for failure or delay in performance. If the event continues for more than 90 days, either party may terminate this Agreement by written notice.Apply the method.
- Event. "Act of government" is listed, and an export ban fits it.
- Causation. The clause says "prevents". The ban prevents export of that steel type. If the supplier could source the same steel from a domestic mill and deliver, a court may find the event did not prevent performance. The supplier must show that it could not perform.
- Notice. The supplier learns of the ban on 10 February. Notice is due by 17 February. If it sends notice on 25 February, it must check whether the clause makes timely notice a condition of relief. The wording here ("shall give") does not say so expressly, which leaves the point arguable.
- Mitigation. The supplier must show it looked for alternatives, such as another source or another delivery route.
- Relief. Obligations are suspended while the ban lasts. After 90 days, either party can terminate.
Because the clause applies, the analysis stops at step 1. Frustration is not needed. If the clause had not covered government acts, the next question would be step 2, then step 3, where a permanent ban on the only available supply might support frustration. A temporary ban probably would not, since performance would remain possible after a delay.
Common errors
| Error | Why it fails |
|---|---|
| Starting with frustration | Clauses and express allocation come first, and they can exclude frustration. |
| Treating "force majeure" as a free-standing legal concept | The label has no fixed meaning in English law. The clause wording controls. |
| Assuming the event list is decisive | Causation, notice and mitigation can still defeat the claim. |
| Relying on cost increases | A rise in cost alone does not frustrate a contract. |
| Ignoring the 1943 Act | Money paid and benefits conferred still need a legal answer after discharge. |
| Assuming a temporary delay frustrates | The question is whether the delay makes performance radically different, which depends on its length compared with the contract's remaining term. |
Writing the conclusion
State your result in the order of the method. Name the route that applies, give the reason, and then state the financial outcome. For example: "The clause applies. The export ban is an act of government that prevented delivery. Notice was given within seven days. Obligations are suspended, and either party may terminate after 90 days. The 1943 Act does not apply." A reasoned conclusion that addresses the weak points in your own case is more useful than a confident one that ignores them.
Exercise
A contract for the hire of a venue contains no force majeure clause. A new law, passed after signing, makes the planned event illegal on the hire date. The hirer has paid a 20% deposit and the venue owner spent money on preparations. Using the four-step method, state which step decides the case and what happens to the deposit.
Show answer
Step 1 finds no clause, and step 2 finds no other term allocating the risk, so frustration is considered at step 3. A supervening law making the event illegal is a recognised category, and it arose without default of either party, so the contract is frustrated and ends automatically. At step 4 the 1943 Act applies. The deposit is recoverable by the hirer. The court may allow the venue owner to retain or recover a just sum for its preparation expenses, up to the amount of the deposit.
Exercise
A supplier invokes a force majeure clause that covers "events beyond reasonable control which prevent performance" after the price of raw materials doubles. Delivery remains physically possible. Does the clause help, and could frustration help instead?
Show answer
The clause probably does not help. A price rise may be beyond the supplier's control, but it does not prevent performance, so causation fails. Frustration also fails, because an increase in cost alone does not make performance radically different. The supplier remains bound and is in breach if it does not deliver.