Sub topic 1
The default rule: promises must be performed
This chapter sets the baseline for the whole tutorial. Force majeure clauses and frustration are both departures from a default rule, so you need that rule clear before studying the exceptions. The chapter follows English law.
Prerequisites
This chapter assumes you already know:
- The basic elements of a contract: offer, acceptance and consideration.
- The difference between express terms (written or stated by the parties) and implied terms (read in by custom, statute or necessity).
- What breach of contract means and that damages are the usual remedy.
- How to read a case citation, such as Paradine v Jane (1647) or Taylor v Caldwell (1863) 3 B & S 826, and a statute citation, such as the Law Reform (Frustrated Contracts) Act 1943.
The rule in one sentence
If you promise to do something, you must do it exactly as promised, or pay damages. This is the default rule of English contract law. It applies whether or not the failure was your fault, and whether or not performance has become harder, costlier or even physically impossible.
The rule matters because every later topic is defined against it. Force majeure clauses are parties' agreed exceptions to it. Frustration is the law's narrow exception, applied when the parties agreed nothing relevant.
Strict liability for breach
Most contractual obligations are strict. Liability does not depend on carelessness. The question is only whether the promised performance was delivered.
Compare this with the tort of negligence. A negligence claimant must show the defendant failed to take reasonable care. A contract claimant need only show that a term was not performed. A seller who promises 100 tonnes of wheat by 1 March is in breach if the wheat arrives on 5 March, even if the delay was caused by a lorry strike the seller could not have prevented.
Some contractual duties are not strict. A promise to "use reasonable endeavours" or to "exercise reasonable skill and care" is defined by effort, not result. Chapter 6 of this tutorial returns to endeavours obligations. For now, note that the standard of the promise is itself something the parties choose.
The origin of the rule: *Paradine v Jane*
The classic statement comes from Paradine v Jane (1647). A tenant was sued for rent. He argued that he should not pay because enemy forces had occupied the land during the Civil War and he had been unable to use it. The court rejected the argument. The tenant had promised to pay rent. If he wanted protection against the occupation of the land, he could have bargained for it in the lease.
The reasoning is the lasting contribution. When a party makes an unconditional promise, the law treats that party as having accepted the risk that circumstances will change. The promisor is better placed than the court to say which risks they are willing to bear, so the court holds them to what they said.
Why the law takes this position
Several practical reasons support strict performance.
- Certainty. Parties price and plan around promises. If courts excused performance whenever events turned out badly, no one could rely on a contract.
- Risk allocation. A contract is a tool for assigning future risk. A fixed-price contract places the risk of cost rises on the supplier. A cost-plus contract places it on the buyer. The price reflects that choice.
- Freedom of contract. Commercial parties can write exceptions into their agreements. If they did not, the law assumes they accepted the risk.
- Limited judicial role. Courts enforce bargains. They do not rewrite them because a bargain became unprofitable.
The table below summarises how the default rule treats common disruptions.
| Event after signing | Default result |
|---|---|
| Supplier's costs rise sharply | Supplier must still perform, or pay damages |
| Delivery becomes late because of a third party's failure | Seller is in breach unless the contract says otherwise |
| Performance becomes physically impossible | Default rule would still impose liability; see the exception below |
| Buyer cannot obtain finance | Buyer is in breach if it cannot pay |
What this looks like in a contract
Consider a plain delivery obligation with no exceptions:
The Seller shall deliver 100 tonnes of milling wheat to the Buyer's
premises on or before 1 March 2027. Time is of the essence.This clause is strict. It says nothing about strikes, floods, weather, port closures or supplier failure. Under the default rule, none of those excuses a late delivery. The Seller carries all of those risks. If the Buyer has to buy replacement wheat at a higher price, the Seller is generally liable for the difference, subject to the usual limits on damages such as remoteness and mitigation.
The words "time is of the essence" make the date a condition. That means a late delivery lets the Buyer terminate as well as claim damages. This makes the strict rule bite harder.
The first crack: *Taylor v Caldwell*
The rule softened in Taylor v Caldwell (1863). The defendants agreed to hire a music hall to the claimants for a series of concerts. Before the first concert the hall burned down, without fault on either side. The court held that both parties were excused. The contract rested on the continued existence of the hall, so the law implied a condition that the contract would end if the hall ceased to exist.
This case is the origin of frustration. The key point for this chapter is how narrow the exception was. It required that something fundamental to the bargain had been destroyed. It did not excuse a party who had merely made a bad deal.
The modern doctrine no longer uses the fiction of an implied term. Chapter 8 covers that change.
Three routes away from strict performance
The rest of the tutorial examines the ways a party can escape the default rule.
The routes are:
- An express term. The parties wrote a force majeure clause, a termination right, a price adjustment or a similar provision. The contract's wording governs.
- The doctrine of frustration. A court holds that a later event has made performance impossible, illegal or radically different. The contract ends automatically.
- No excuse. The default rule applies. The party performs or pays damages.
Notice the order. The express terms come first. Frustration is a fall-back and courts apply it reluctantly, because it overrides the parties' own allocation of risk.
Common errors
Learners often make these mistakes at this stage.
- Treating hardship as an excuse. In Davis Contractors Ltd v Fareham UDC [1956] AC 696, a builder faced labour shortages and bad weather, so the job cost far more than priced. The House of Lords held the contract was not frustrated. The contract was still the same contract, only more expensive for the builder.
- Assuming "not my fault" is a defence. Absence of fault does not excuse a breach of a strict obligation.
- Assuming force majeure is a general legal doctrine. English law has no general doctrine of force majeure. The term is a label for a clause. Without such a clause in the contract, there is nothing to apply. The next chapter develops this.
- Skipping the contract. Before arguing about frustration, read the contract. A clause may already allocate the risk.
Summary of the baseline
- Contractual promises are generally strict, and breach does not require fault.
- The promisor bears the risk of events that make performance harder, unless the contract says otherwise.
- Paradine v Jane states the rule. Taylor v Caldwell opens a narrow exception.
- Express terms are checked first. Frustration comes second. Strict performance applies if neither helps.
Exercise
A fixed-price supplier agrees to deliver 500 steel beams by 1 June. In April, the global price of steel rises by 40%, and the supplier will lose money on the contract. The contract has no force majeure clause. What is the supplier's position under the default rule, and why?
Show answer
The supplier must deliver or pay damages. A rise in cost is a risk the supplier accepted by agreeing a fixed price, and the default rule holds a promisor to the promise whatever happens to the cost of performing. Courts do not treat a more expensive performance as a radically different one (see Davis Contractors v Fareham UDC), so frustration would not apply.
Exercise
What is the practical significance of Paradine v Jane for someone drafting a contract today?
Show answer
It shows that the law assigns unexpected risks to the party who made an unconditional promise. A party who wants protection from a particular event, such as a government closure, a strike or a supply failure, must negotiate and write that protection into the contract. Otherwise, the court is unlikely to supply it.