Sub topic 11
Limits: foreseeability, express allocation of risk, self-induced frustration and cost increases
Frustration is deliberately hard to establish. The courts treat it as a narrow doctrine, because it overrides the parties' bargain and ends the contract automatically. This chapter covers the four main limits on it. Each is a reason a court may refuse to find frustration even though performance has become difficult, expensive or disappointing.
It assumes you know the test from the previous chapter: a supervening event must make performance impossible, illegal or radically different from what the parties undertook. It also assumes you know the basic idea of breach and damages. Cases are cited by name only. Check the reports before relying on any detail.
Why the limits exist
Contract law starts from strict performance. A party who promises something takes the risk that it becomes harder to do. Frustration is an exception, and the limits below stop it from becoming a general escape route. Each limit asks a version of the same question: whose risk was this?
The four limits are:
- The event was foreseen or foreseeable.
- The contract already allocates the risk, expressly or by implication.
- The party relying on frustration caused the event.
- The event only made performance more expensive.
They often overlap. A court may rely on several of them in one judgment.
Foreseeability
An event that the parties foresaw, or should have foreseen, is less likely to frustrate a contract. The reasoning is that a party who saw a risk coming could have written a term to deal with it. If they did not, the court may conclude that they accepted it.
Foreseeability does not decide the question by itself, for these reasons:
- Foreseeing that something might happen is different from foreseeing that it will happen, or foreseeing its scale. A party may know a war is possible without expecting the particular closure of a trade route that follows.
- The degree of foresight matters. A remote possibility mentioned in passing counts for less than a risk both sides discussed.
- The authorities treat foresight as a factor to weigh. They do not treat it as an absolute bar. Courts have found frustration even where some risk was foreseen, particularly where the actual event was far more severe than anything contemplated.
In practice, the more specifically the parties discussed the risk, the harder it is to argue frustration. If the contract mentions the event at all, the next limit usually applies.
Express allocation of risk
If the contract provides for the event, there is no gap for frustration to fill. The parties have decided who bears the risk, and the court will respect that decision.
This happens in several ways:
- A force majeure clause covers the event. The clause then governs, and frustration generally has no role where the clause deals fully with the event.
- Another term allocates the risk. Examples are a price adjustment clause, a termination right, or a term making one party responsible for supply or delivery.
- The risk is allocated by implication. The nature of the contract, such as a sale of goods that the seller undertakes to obtain from any source, may show that one party took the risk.
A subtle point arises when a clause exists but does not cover the event. The omission may mean the parties chose not to cover it, which points away from frustration. It may instead mean the event was simply not thought of. Courts look at the whole contract and the circumstances to decide which is more likely. A detailed, carefully drafted clause listing many events makes the first reading more persuasive.
A clause that covers the event but whose conditions are not met causes a different problem. If a party fails to give the notice the clause requires, it usually cannot fall back on frustration to avoid the consequences. The clause has already dealt with the situation.
Self-induced frustration
A party cannot rely on frustration if it brought about the event through its own choice or default. The doctrine protects parties from outside events, not from the results of their own conduct.
Several points apply:
- The party relying on frustration carries the burden of showing that the event was not self-induced.
- The conduct must be a real cause of the event. Being merely connected with it is not enough.
- A deliberate act clearly counts. So does a decision that left the party unable to perform, such as selling the only item it had promised to supply to someone else.
- A breach by the party relying on frustration can also count, if it led to the event.
- Negligence is less clear. The authorities suggest that fault short of a deliberate choice can still bar frustration, but the position is less settled, and the outcome depends on the facts.
A classic situation is a party who has several contracts and a limited resource. If a supervening event reduces the resource, the party cannot choose which contract to perform and then claim frustration of the others. Having made the choice, the party has caused its own inability to perform the rest.
Increases in cost
A rise in the cost of performing, even a steep one, does not frustrate a contract. The party who agreed to perform for a fixed price bears the risk that costs go up. The performance is still the same performance. It is just less profitable.
The courts have been consistent on this. The question is whether performance has become radically different in nature, not whether it has become more burdensome. Examples that did not amount to frustration include:
- A route for shipping goods becoming longer and more costly after a closure, where the voyage was still possible and the goods could still be delivered.
- A shortage that raised the market price of materials.
- A change in exchange rates or taxes that reduced the profit on the deal.
There is no fixed percentage at which a cost increase becomes frustrating. In practice, a rise that is large but still leaves performance possible will almost never succeed. A cost increase might be relevant if it is so extreme that performance becomes commercially meaningless, but courts have been reluctant to accept this, and the claim is difficult to win.
The same logic applies to force majeure clauses, which often state expressly that increased cost or economic hardship is not a force majeure event. Such wording confirms the default position.
Putting the limits together
A court will usually work through the limits in a rough order. The table shows the question each one asks and the sort of facts that defeat a claim.
| Limit | Question | Facts that defeat frustration |
|---|---|---|
| Foreseeability | Did the parties foresee the event? | A specific, discussed risk of the actual event |
| Express allocation | Does the contract deal with the risk? | A clause or term placing the risk on one party |
| Self-induced | Did the claimant cause the event? | A deliberate choice or default by the claimant |
| Cost increase | Is performance only more expensive? | Possible performance at higher cost |
Common errors
- Treating foresight as decisive. Foreseeability is a factor. A party can still succeed if the event was far worse than anything foreseen.
- Ignoring the contract's own terms. Check for a clause or other allocation of risk before analysing frustration at all.
- Arguing frustration after missing a clause condition. Failing to give notice under a force majeure clause does not revive the doctrine.
- Confusing hardship with radical difference. A bad bargain, a lost profit or a higher price is the ordinary risk of contracting.
- Overlooking your own part. If your decisions contributed to the event, expect the other side to raise self-induced frustration.
Exercise
A supplier agrees to deliver 500 tonnes of steel at a fixed price. Before delivery, a trade dispute raises the market price of steel by 60 percent. Steel is still available. The supplier says the contract is frustrated. What is the likely outcome, and which limit applies?
Show answer
The claim is likely to fail. The price rise only makes performance more expensive, and the supplier took that risk by agreeing a fixed price. Performance is still possible and is not radically different in nature, so the cost increase limit applies. If the contract mentions price risk, express allocation would also point the same way.
Exercise
A haulier has two contracts to deliver goods using its only available lorry. A supervening event destroys its other vehicles, leaving one lorry. It uses the lorry for Contract A and claims Contract B is frustrated. Why might this fail?
Show answer
The haulier chose which contract to perform. That choice caused its inability to perform Contract B, so the frustration is self-induced. The doctrine does not protect a party from the results of its own election.