Sub topic 4
Reading the clause: construction, general wording and catch-all phrases
This chapter assumes you know the basics of contract formation, the difference between express and implied terms, and how English cases and statutes are cited. It also assumes you have met the structure of a force majeure clause (event, effect, causation, notice, consequences). Here the question is narrower: how does a court decide what the words of the event list actually cover?
Why wording decides everything
English law has no general doctrine of force majeure. The expression is French, and it has no fixed meaning in English law. In Lebeaupin v Richard Crispin & Co [1920] 2 KB 714, McCardie J said that the scope of a force majeure clause depends on the contract in which it appears. A court cannot supply protection the parties did not write. If the clause is silent about an event, the party who cannot perform has no clause to rely on. It may still have the common law doctrine of frustration, covered in later chapters, but that is a different and much narrower route.
So the first task in any dispute is interpretation. You read the clause, decide what each phrase means, and then ask whether the facts fit.
The ordinary rules of construction apply
Force majeure clauses get no special rulebook. The court applies the same approach it uses for any commercial contract. The leading authorities are Rainy Sky SA v Kookmin Bank [2011] UKSC 50, Arnold v Britton [2015] UKSC 36 and Wood v Capita Insurance Services Ltd [2017] UKSC 24. The court asks what a reasonable person, with the background knowledge available to both parties at the time of contracting, would understand the words to mean. In practice that means:
- The words themselves are the starting point, read in the context of the whole clause and the whole contract.
- Where two readings are possible, the court may prefer the one that fits commercial common sense. It will not rewrite a clear term because the outcome is harsh for one side.
- Sophisticated parties with lawyers get less sympathy when they signed a clause that turns out to be narrow.
- Textual analysis and commercial context are both used. Neither automatically wins.
Older cases sometimes say force majeure clauses should be read strictly against the party relying on them. The modern approach does not use a presumption in either direction. The clause is read for what it says. Contra proferentem (resolving ambiguity against the party who drafted or relies on a clause) is at most a last resort for real ambiguity.
Listed events
Most clauses list events: fire, flood, war, strikes, acts of government, epidemic. Three drafting choices change how the list works.
- Exhaustive or illustrative. "Force majeure means the following events" is a closed list. "Force majeure means any event beyond reasonable control, including the following" is illustrative, and the list gives examples only.
- Defined terms inside the list. "War" may or may not include civil unrest, and "act of government" may or may not include a regulation, an order, or a decision by a public body. Look for a definition elsewhere in the contract before reading the term in its everyday sense.
- Events named but qualified. "Strikes" may be limited to strikes "other than of the affected party's own employees". The qualifier is part of the clause and must be satisfied.
A named event does not remove the other conditions. If the clause says the event must "prevent" performance, then fire at the factory is not enough unless it actually prevented what was promised.
General wording and catch-all phrases
The harder cases involve general words, for example:
- "any other event beyond the reasonable control of the affected party"
- "any cause beyond our control"
- "and other similar events"
- "circumstances outside the party's reasonable control, whether or not similar to the above"
The key point is that general words are read in context, and the context often includes the list that precedes them. Courts sometimes use the ejusdem generis ("of the same kind") rule, which says that general words following a list of specific items are limited to things of the same kind. The rule is a tool for finding the parties' meaning, not an automatic result. It applies more readily when the general words follow the list and there is a recognisable common theme. It applies less readily when the clause says the general words apply "whether or not of the same kind" or "without limitation". In Lebeaupin, a clause naming specific events and ending with general words was read as covering events that genuinely prevented performance, but the case also shows that the court will not stretch it to cover events the parties did not describe.
The table below summarises how common phrasing tends to affect scope.
| Drafting feature | Likely effect on scope |
|---|---|
| "including" or "including without limitation" before the list | The list is illustrative. The general words are wide. |
| Closed list ("means the following") | Only the named events count. A catch-all may be absent. |
| "Other similar events" at the end | General words may be limited by the type of event in the list. |
| "Whether or not similar" or "of any kind" | Intended to defeat ejusdem generis and widen the clause. |
| "Beyond reasonable control" | Adds a test. The event must be outside what the party could reasonably prevent or control. |
| "Beyond control" without "reasonable" | A stricter test for the claimant. The party may have to show it could not have controlled the event at all. |
"Beyond reasonable control" is a condition, not a label
Even when an event is on the list, many clauses require it to be beyond the party's reasonable control. That wording asks what the party could reasonably have done to avoid the event or its effect. A strike at your own plant may be on the list, yet fail this test if you could have settled the dispute on reasonable terms. A third party's default is a related problem: a failure by your supplier is often treated as within your control unless the clause expressly covers it. If a supplier failure is meant to count, the clause should say so, and ideally say what must be shown about the supplier's own position.
Things clauses often leave out, and courts do not add
Absent clear words, courts will not read these into a clause:
- Increased cost or reduced profit. A clause covering events that "prevent" performance does not cover a performance that is merely more expensive. The same logic appears in frustration. Parties who want hardship relief must say so.
- Lack of funds. Many clauses expressly exclude it. Even without an exclusion, a financial event is hard to fit under general words about events beyond control.
- Foreseeability limits. Nothing in English law says a listed event must have been unforeseeable. The parties may have listed it precisely because they foresaw it.
Worked example
Take this wording from a supply agreement:
"Force Majeure Event" means any event or circumstance beyond the reasonable
control of the affected party, including fire, flood, war, epidemic, act of
government or industrial action (other than by the affected party's own staff),
which prevents that party from performing its obligations.A supplier's port is closed by a government order after a disease outbreak, and it cannot ship. Reading in order:
- The clause is illustrative ("including"), so the list is not the limit.
- "Epidemic" and "act of government" are both named, so the event likely falls within the list. If it did not, the general words would still be available.
- The clause says the event must be beyond reasonable control. Closing a port by order meets that test.
- The clause also requires that the event "prevents" performance. If the supplier could ship from another port at higher cost, a court would ask whether performance was truly prevented or merely made dearer, and that depends on the contract's wording about routes and delivery.
The same supplier whose own workers strike would be outside the clause, because of the bracketed exclusion.
Exercise
A contract's clause says: "Force Majeure means any of the following: fire, flood, earthquake, war, and other similar events beyond the reasonable control of the party." A party cannot perform because a key customer has gone insolvent. (a) Is the list open or closed? (b) What is the strongest argument against the party's claim? (c) What drafting change would have made its claim stronger?
Show answer
(a) It is closed in form ("any of the following"), with a limited catch-all in "other similar events". (b) The insolvency is a financial event, not of the same kind as fire, flood, earthquake or war, so "similar events" probably does not reach it. The party also faces the point that the clause gives no relief for financial difficulty and that the customer's default may be within its commercial control. (c) Wording such as "including without limitation" and "whether or not similar to the foregoing", or an express reference to customer or third-party default, would widen the clause. Whether a court would accept even that depends on the whole clause, including the causation condition.
Exercise
Why does a court not simply read a force majeure clause narrowly against the party relying on it?
Show answer
Because the modern approach to construction (Rainy Sky, Arnold v Britton, Wood v Capita) applies the same principles to all commercial contracts. The court looks for the meaning a reasonable person with the parties' background knowledge would take from the words. A presumption against the party relying on the clause is not part of that approach. Contra proferentem is at most a last resort for real ambiguity.