Sub topic 8
Frustration: the doctrine and its rationale
This chapter assumes you know the basic elements of a contract, the difference between express and implied terms, and what breach and damages mean. It also assumes you can read English case and statute citations. The focus is English law.
Where frustration sits
The previous chapters established the default rule: a party who promises something must perform it, even if performance becomes harder, and failure to perform is a breach. The parties can change that by writing a force majeure clause, which allocates the risk of disruption by express wording.
Frustration is the common law's fallback for the case where the contract does not deal with the disruption. It applies when a supervening event, one that happens after the contract is formed, makes performance impossible, illegal, or radically different from what the parties undertook. If the doctrine applies, the contract ends automatically and both parties are released from future obligations.
Frustration is a rule of law, not a term the parties chose. That distinction drives most of what follows.
The origin: from absolute promises to a limited exception
The old rule was stated in Paradine v Jane (1647). A tenant was sued for rent and argued that enemy soldiers had occupied the land. The court held that he was still liable. A party who wanted protection from an event could have bargained for it, and if they did not, the promise stood.
That rule had harsh results, and the courts moved away from it in Taylor v Caldwell (1863). The defendants had agreed to let the claimants use a music hall for a series of concerts. The hall burned down before the first concert, through no fault of either side. The court held that both parties were excused.
The reasoning in Taylor v Caldwell was an implied term. The court said the contract was subject to an implied condition that the hall would continue to exist. This was the first version of the doctrine, and it shows its starting point: the law finds a way to excuse a party only when there is a good reason to think the parties would not have wanted the contract to continue.
The rationale: why the law intervenes
Three ideas are usually offered to explain frustration. Each has been influential, and each has weaknesses.
| Theory | Core idea | Main weakness |
|---|---|---|
| Implied term | The parties would have agreed that the contract ends if the event occurred | It is fictional. The parties often never thought about the event, and might not have agreed if asked |
| Failure of the foundation | The event destroys the basis of the contract | "Foundation" is vague, and it does not say how much must be lost |
| Construction or just solution | The court decides what the contract can fairly be taken to cover, and whether the changed situation lies outside it | It gives the court wide discretion, which sits uneasily with certainty |
The modern English position favours the third approach. In Davis Contractors Ltd v Fareham UDC [1956] AC 696, Lord Radcliffe said frustration occurs whenever the law recognises that, without default of either party, a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract. He added the often-quoted words: "Non haec in foedera veni. It was not this that I promised to do."
The House of Lords confirmed this view in National Carriers Ltd v Panalpina (Northern) Ltd [1981] AC 675, where Lord Simon described frustration as a device by which the court does justice when the contract has become inapplicable to the new situation. The implied term label is now regarded as a convenient shorthand at best. The key point is that the doctrine operates by law, whatever the parties think.
This has a practical consequence. Because frustration does not depend on the parties' agreement, they cannot simply decide that it applies. They also cannot easily contract out of it for events they have chosen to cover: if the contract deals with the event expressly, the court applies the contract. Both points are developed in later chapters.
Why the doctrine is kept narrow
The courts apply frustration sparingly. Lord Radcliffe in Davis Contractors said that it is not to be lightly invoked, as the "dissolvent of a contract", and must be kept within very narrow limits. Several policy reasons support this.
- Certainty. Commercial parties rely on contracts being enforced. If any hardship could end a contract, they could not plan.
- Risk allocation. Contracts exist to allocate risk. Price, insurance and drafting reflect who bears which risks. Releasing a party who has accepted a risk undoes that bargain.
- Fairness to the other side. Frustration ends the contract for both parties. The party who still wants performance loses the benefit of their bargain without any fault on the other side.
- Drafting incentives. If the law readily rescues parties, they have less reason to write careful clauses.
The result is a doctrine with a high threshold. Most disruptions do not frustrate a contract. They only make it more expensive or inconvenient, which the law treats as a risk the performing party took on.
The features of frustration
English law treats the following as the key features of the doctrine.
- A supervening event. Something must occur, or become known, after the contract is made. If the problem existed at formation, the matter is dealt with by the law of mistake, not frustration.
- No fault. The event must occur without the fault of the party who relies on it. This is the "self-induced" limit, covered in a later chapter.
- A radical change. The change must make performance impossible, illegal or fundamentally different. Mere difficulty or loss is not enough. The test is the subject of the next chapter.
- No allocation of the risk. The contract must not have provided for the event, whether through a force majeure clause or in some other way.
- Automatic effect. If the requirements are met, the contract ends at the moment of the event, without any act by either party.
The fifth feature distinguishes frustration from a force majeure clause. A clause usually gives a party a right to be excused or to terminate, often after notice. Frustration involves no election, no notice and no choice. The contract is simply at an end.
A worked illustration: *Krell v Henry*
In Krell v Henry [1903] 2 KB 740, the defendant agreed to rent rooms on Pall Mall for two days to watch the coronation procession of Edward VII. The procession was cancelled because the King fell ill. The defendant refused to pay the balance of the rent.
The Court of Appeal held that the contract was frustrated. The rooms still existed and could be used, so performance was not impossible. But the purpose of the contract, which both parties understood, was to view the procession, and without it the arrangement was a different thing from what had been agreed.
Compare Herne Bay Steam Boat Co v Hutton [1903] 2 KB 683. The defendant hired a boat to watch a naval review and also to cruise around the fleet. The review was cancelled, but the boat could still do the cruise. The court held the contract was not frustrated, as the review was not the only purpose.
The two cases show a point that recurs throughout the doctrine: the question is what the contract was for, as shown by its terms and the circumstances both sides knew about, not merely whether it can still be done.
Common errors
- Treating frustration as a way out of a bad bargain. A contract that has become unprofitable is not frustrated. The party must still perform or pay damages.
- Assuming the parties can choose it. The parties cannot agree that frustration applies in a way that binds a court, though they can agree a termination right by contract.
- Confusing impossibility with frustration. Impossibility is one category of frustration. Frustration also covers illegality and the loss of a shared purpose.
- Overlooking the contract. Always read the express terms first. If a clause covers the event, the doctrine of frustration is usually excluded for that event.
- Forgetting the financial consequences. Ending the contract does not end the money questions. The Law Reform (Frustrated Contracts) Act 1943 deals with sums paid and benefits conferred, which a later chapter covers.
Summary of the doctrine
Frustration releases both parties from a contract when a supervening, fault-free event makes the contract radically different from what was promised. Its rationale is a just solution, reached by construing the contract in light of the new circumstances, rather than a fictional implied term. Its threshold is high because the law values certainty and respects the parties' own allocation of risk.
Exercise
A company agrees to buy a cargo of wheat at a fixed price. Before delivery, a poor harvest raises the market price sharply, so the seller will lose money by delivering. The seller argues the contract is frustrated. Is the argument likely to succeed, and why?
Show answer
No. The wheat can still be delivered, and the contract is not radically different in nature. The seller has only suffered an increase in cost, which the law treats as a risk the seller accepted when agreeing a fixed price. Frustration is not available for a bargain that has become unprofitable. The seller must perform or pay damages.
Exercise
Why does frustration end a contract automatically, whereas a force majeure clause typically requires a party to give notice and may only suspend obligations?
Show answer
Frustration operates by law, not by the parties' agreement, so it takes effect when the qualifying event occurs, whatever either party does or wants. A force majeure clause is a contractual term, so its effect depends on its wording. Clauses often require notice, set conditions, and give remedies such as suspension or an option to terminate.
Exercise
In Krell v Henry the rooms could still be rented, yet the contract was frustrated. In Herne Bay Steam Boat Co v Hutton the review was cancelled and the contract was not frustrated. What explains the different outcomes?
Show answer
In Krell v Henry, the sole foundation of the contract was viewing the procession, and both parties understood that. Without it, the contract was radically different. In Herne Bay, the boat could still be used for the cruise, which was a second purpose, so the contract was not radically changed.