Sub topic 13
Force majeure versus frustration: which applies and when
This chapter assumes you know the basic elements of a contract, the difference between express and implied terms, and what breach and damages mean. You should also be able to read case and statute citations. It also assumes you have met force majeure clauses and the test for frustration in the earlier chapters. Here the question is how the two fit together when a real disruption happens.
Two different sources of relief
A force majeure clause is a term the parties wrote. Its meaning, its triggers and its consequences all come from the contract, so a court construes it like any other term. Frustration is a rule of law. It applies without either party agreeing to it, and it applies only when the strict conditions in the test are met.
| Feature | Force majeure clause | Frustration |
|---|---|---|
| Source | The contract | Common law, plus the Law Reform (Frustrated Contracts) Act 1943 |
| Triggering events | Whatever the clause lists, including any catch-all | Any supervening event that meets the test |
| Threshold | Set by the wording (for example "prevents", "hinders" or "delays") | Radical difference from what was undertaken |
| Notice and mitigation | Often required as conditions | None required by the doctrine |
| Typical result | Suspension, extension of time, or a right to terminate | Automatic discharge of future obligations |
| Money consequences | Whatever the clause says, or accrued rights | The 1943 Act |
| Can the parties exclude it? | Yes, by omitting or narrowing the clause | Yes, by allocating the risk expressly |
The most important practical difference is who decides. Under a clause, the parties decide in advance. Under frustration, a court decides afterwards, and the contract ends whether or not either party wants that.
The order of analysis
The usual order is clause first, doctrine second. The clause comes first because the parties' own allocation of risk takes priority over a rule that fills gaps. If the clause covers the event, there is usually nothing left for frustration to do.
Why a clause usually displaces frustration
Frustration depends on the contract not having provided for the event. In Bank Line v Arthur Capel [1919] AC 435, Lord Sumner explained that the doctrine is a device for deciding which party bears a risk the contract left unallocated. If the parties dealt with the risk, the court has no gap to fill. Later cases apply the same reasoning. In Channel Island Ferries v Sealink UK [1988] 1 Lloyd's Rep 323, an express clause covering the event meant the contract was not frustrated.
Two points limit this rule.
- Displacement is only to the extent of the clause. A clause displaces frustration only for the events and consequences it addresses. If it covers a short interruption and the real event is permanent, the clause may not have been written for that event. In Metropolitan Water Board v Dick Kerr [1918] AC 119, a clause allowing an extension of time for delays did not stop the House of Lords finding frustration. The wartime ministerial order stopped the work for an indefinite period. The clause was held to contemplate ordinary delays, not an interruption of that kind.
- Having a clause does not by itself exclude the doctrine. Courts ask what the clause was meant to cover. A clause that lists the event but gives no sensible remedy for it is weaker evidence of allocation than one that sets out a full scheme.
Section 2(3) of the 1943 Act supports the same approach. If a contractual provision was meant to operate when circumstances arise that would frustrate the contract, the court must give effect to it. The Act does not override the parties' own scheme.
When the clause applies but the party loses
A clause failing is not the same as frustration succeeding. Several outcomes are possible when a party relies on force majeure and the clause does not help.
- The event is outside the wording. The party is not excused, and the court then asks whether frustration applies. Frustration will usually fail if the event is the kind the parties plainly considered and chose not to list.
- The event is covered but causation fails. Courts read "by reason of", "as a result of" and "prevents" strictly. In Classic Maritime v Limbungan Makmur [2019] EWCA Civ 1102, the Court of Appeal required "but for" causation. The party had to show it would have performed if the event had not occurred. A party that would have been unable to perform anyway cannot rely on the clause.
- A condition was missed. Late or defective notice may remove the protection, depending on whether notice is a condition precedent. Check the wording ("provided that", "only if", "as a condition of relief").
- A mitigation obligation was not met. In MUR Shipping v RTI [2024] UKSC 18, the Supreme Court held that a "reasonable endeavours" proviso did not oblige a party to accept a non-contractual form of performance (payment in euros rather than the contractual dollars) to avoid the event. The clause's wording decided how far mitigation went.
In each case the loss of the clause does not automatically open the door to frustration. Frustration has its own limits. Foreseeability, self-induced events and mere increases in cost all weigh against it, and an express attempt to allocate the risk weighs against it even more.
Different consequences, different strategies
Because the outcomes differ, a party's choice matters.
- Clause relief is flexible but conditional. It can suspend obligations while the contract lives on. That is often what both parties want when a disruption is temporary.
- Frustration is blunt. The contract ends at the moment of the frustrating event, without notice and without either party choosing it. A party that would prefer to keep the contract cannot opt out.
- Termination under a clause is not frustration. If a party terminates under the clause, the contract ends by agreement, and the 1943 Act does not apply. Money paid and work done are governed by the clause and by accrued rights. A clause that says nothing about these leaves the parties with a gap that is harder to fill than under the Act. Draft termination rights with payment consequences stated.
The following drafting sentence shows how parties can address the interaction directly.
This clause sets out the parties' agreed allocation of risk for the events it covers. Where a Force Majeure Event occurs, the parties' rights and obligations are as stated in this clause, and neither party may treat this Agreement as frustrated by reason of that event unless it has continued for more than 180 days.A sentence like this makes the intention clear and gives a court less room to find the clause was not meant to be exclusive. It does not bind the court on a different event, or on one that falls outside the definition.
Applying the interaction to a scenario
A supplier agrees to deliver goods by sea over 12 months. A government bans exports of the goods in month four. The contract has a clause covering "act of government which prevents performance", with suspension for up to 60 days and termination after that.
- The event is an act of government, so it falls within the wording. Causation holds, because the ban prevents export.
- The supplier gives notice within the stated period and tries to find alternatives.
- The clause gives suspension, then termination at 60 days. The scheme is complete for this event, so frustration is displaced.
- If the supplier terminates, the clause governs payments. If the supplier had missed the notice period, it might lose protection. Frustration would then probably not rescue it, because the parties dealt with exactly this risk.
Change one fact. Suppose the clause covered only "weather" and "strikes". The ban is not listed, no catch-all applies, and no other term allocates the risk. The court would then ask whether the contract is radically different, which would also consider whether the ban is permanent and whether the supplier could perform another way.
Exercise
A charterparty contains a clause excusing delay caused by "floods, strikes and any other cause beyond the owner's control". War closes a canal on the route, and the owner claims the contract is frustrated. Explain why the court asks first about the clause, and what could still allow frustration.
Show answer
The parties' own allocation of risk takes priority, and frustration fills only gaps the contract left. The court first asks whether the closure falls within the clause, including the catch-all, and what remedy the clause gives. If it is covered and the clause gives a full scheme, the clause governs and frustration is displaced. Frustration could still apply if the clause was only meant for ordinary delay, and the closure creates a permanent or indefinite change in the obligation that the clause did not contemplate, as in Metropolitan Water Board v Dick Kerr. The court would also check that the event was not foreseen and not self-induced.
Exercise
A buyer terminates under a force majeure clause that gives a right to terminate after 60 days but says nothing about prepaid money. Does the Law Reform (Frustrated Contracts) Act 1943 govern the prepayment?
Show answer
No. Termination under the clause is a contractual termination, not frustration, so the 1943 Act does not apply. The prepayment is dealt with by the clause (which is silent here) and by the ordinary law on accrued rights and restitution, such as recovery for total failure of consideration. The lesson is to state payment consequences in the termination provision.