Sub topic 2
What Force Majeure Is, and Why English Law Has No General Doctrine of It
Prerequisites and scope
This chapter assumes you know the basic elements of a contract (offer, acceptance, consideration). It also assumes you can tell express terms from implied terms, know what breach and damages mean, and can read case and statute citations. It follows the chapter on the default rule that promises must be performed.
The aim is to explain what "force majeure" means in a contract, why English law treats it as a matter of contract wording instead of a free-standing legal doctrine, and what follows for anyone drafting or relying on a clause.
What "force majeure" means
"Force majeure" is a French phrase, usually translated as "superior force". In its original civil law sense it describes an event that a party could not foresee or prevent, and that excuses non-performance.
In English law the phrase has no fixed meaning of its own. Courts treat it as a label that parties attach to a clause. The label tells you what the clause is for, which is to deal with events outside the parties' control. It does not tell you what the clause covers. As Mackinnon LJ put it in Lebeaupin v Richard Crispin & Co [1920] 2 KB 714, there is no precise English law definition. The scope depends on the words the parties chose.
A force majeure clause is therefore a contractual term. It does one or more of the following when a listed event occurs:
- excuses a party from liability for failing or delaying to perform;
- suspends the affected obligations for a period;
- extends the time for performance;
- gives one or both parties a right to terminate.
Why English law has no general doctrine
The starting point is strict performance
English law holds a party to the promise it made. If circumstances change and performance becomes harder, more expensive or impossible, the promisor is still liable in damages for non-performance. The leading authority is Paradine v Jane (1647) Aleyn 26. The tenant was held to his rent even though enemy troops had occupied the land. The rule rests on the idea that a party can protect itself by negotiating for an exception. If it did not, the law will not add one.
Risk allocation is a matter for the parties
Courts take the view that the contract is the parties' own allocation of risk. A court that excused performance whenever events turned out badly would rewrite the bargain, and it would make commercial dealings less certain. Commercial parties often price risk into their deals, so a general excuse would also distort that pricing.
For this reason English law offers two separate routes out of a bargain that has been disrupted:
- An express clause. The parties agree in advance what happens. This is force majeure in the contractual sense.
- The doctrine of frustration. The common law steps in only in narrow cases, where an event makes performance impossible, illegal or radically different. Later chapters cover it.
There is no third route in which a court asks whether an event was "force majeure" in a general sense and grants relief on that basis. This is the key difference from many civil law systems.
The consequence: no clause, no force majeure relief
If the contract has no force majeure clause, a party cannot rely on "force majeure" at all. The only question is whether frustration applies. If it does not, the party is in breach. This is a common mistake in practice. People describe a flood, a strike or a government order as "force majeure" and assume that this ends the matter. Whether it does depends only on the contract's words.
Force majeure compared with frustration
The two concepts are related but differ in source, trigger and effect.
| Feature | Force majeure clause | Frustration |
|---|---|---|
| Source | The contract's express wording | Common law doctrine |
| Trigger | Whatever events the clause lists or describes | A supervening event that makes performance impossible, illegal or radically different |
| Effect | Whatever the clause says: suspension, extension, termination | Automatic discharge of the contract |
| Financial adjustment | As the clause provides | Law Reform (Frustrated Contracts) Act 1943 |
| Parties' control | Parties can draft the scope and consequences | Parties cannot vary the doctrine, though they can allocate risk by contract |
A clause can be wider than frustration. A party may be excused by a clause for an event that merely makes performance more costly or slower, which frustration would never excuse. A clause can also be narrower. It might list only a few events, so that a party has to fall back on frustration for anything else.
Where the label can mislead
Some points commonly cause errors.
- The heading does not control the content. A clause headed "Force Majeure" gives relief only for what its words cover. Equally, a clause with a different heading, such as "Excused Events" or "Events Beyond Control", can do the same job. Courts read the operative wording and not the title.
- Listed events matter. If the clause names fire, flood and war but not epidemic or sanctions, a party must ask whether general words in the clause reach the event. Later chapters cover that construction exercise.
- The clause is not implied. Courts will not imply a force majeure clause into a commercial contract. It would not meet the strict test for implied terms, because it is not needed to make the contract work and the parties could have written one.
- Trade custom does not fill the gap. Parties sometimes assume that a standard form, such as one used in a particular commodity trade, contains the clause. Check whether the form is incorporated and what its text says.
- Foreign law may differ. If a contract is governed by a civil law system, or a US state's law, there may be a statutory or doctrinal excuse that has no English equivalent. The governing law clause decides which approach applies.
Seeing the structure
The diagram shows how an English law analysis separates the contract route from the doctrine route.
A short worked example
A UK bakery contracts to buy flour monthly from a mill for two years. The contract contains no force majeure clause. In month ten, a flood closes the mill for six weeks and it cannot deliver.
- The bakery cannot argue "force majeure", because the contract has no such clause and English law has no general doctrine.
- The mill asks whether the contract is frustrated. A six-week closure in a two-year contract is unlikely to make performance radically different, so frustration probably fails.
- The mill is therefore in breach for the missed deliveries and is liable in damages, subject to the usual rules on remoteness and mitigation.
Now change the facts. The contract includes a clause that excuses a party for "flood or other event beyond its reasonable control which prevents performance", on written notice. The mill's flood falls within the wording, so the mill is excused for the period of the closure if it follows the notice requirements. The same event gives opposite results because of the contract wording alone.
Practical consequences for drafting and advice
- Draft a clause for each contract. Do not assume one will be implied or that a precedent from another deal fits.
- Name the events that matter commercially, and add general wording to catch what you cannot predict.
- State the consequences clearly: whether obligations are suspended, whether time extends, and when termination becomes available.
- Consider how the clause interacts with frustration and with other risk-allocation terms, such as price adjustment, hardship or termination for convenience.
- When advising a party after an event, read the clause before discussing the doctrine, because the clause often decides the matter.
Exercise
A English law supply contract has no force majeure clause. A government order bans the export of the goods, and the supplier says it is excused "by force majeure". Is the supplier right? Which question should be asked instead?
Show answer
No. English law has no general doctrine of force majeure, and with no clause the label gives no relief. The right question is whether the contract is frustrated, for example because the export ban makes performance illegal or radically different. If it is not, the supplier is in breach.
Exercise
A contract has a clause headed "Excused Events" that suspends obligations during any "event beyond a party's reasonable control which prevents performance". Is it a force majeure clause even though it is not labelled that way?
Show answer
Yes in substance. Courts look at the operative wording and not the heading, so the clause works as a force majeure clause. Whether a particular event is covered depends on the words of the clause and how a court would construe them.