Sub topic 9
The test: radical difference, not merely harder or costlier performance
Prerequisites and scope
This chapter assumes you know the basic elements of a contract, the difference between express and implied terms, and what breach and damages mean. It also assumes you can read English case citations. The chapter sits after the introduction to frustration as a doctrine and before the separate chapters on categories and limits. Its job is narrow: to state the legal test and show how courts apply it.
Why a test is needed
Contract law starts from strict performance. A party who promises something must do it, or pay damages, even if performance becomes harder than expected. Frustration is a rare exception. It applies when an event after the contract is made changes the situation so much that holding the parties to their bargain would be unjust.
A court needs a way to separate two kinds of case:
- performance that has become harder, slower or more expensive, which stays binding
- performance that has become something fundamentally different from what was promised, which is discharged
The test for frustration is the tool for drawing that line.
The classic formulations
The best-known statement comes from Lord Radcliffe in Davis Contractors Ltd v Fareham UDC [1956] AC 696:
"Frustration occurs whenever the law recognizes that without default of either party a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract."
He added the often-quoted comment: "Non haec in foedera veni. It was not this that I promised to do."
The Supreme Court restated the approach in Edwinton Commercial Corp v Tsavliris Russ (Worldwide Salvage & Towage) Ltd (The Sea Angel) [2007] EWCA Civ 547. The Court of Appeal there described a multi-factor assessment. It said the court should consider:
- the terms and construction of the contract
- its matrix, meaning the background facts known to the parties
- the parties' reasonable expectations about risk allocation
- the nature of the supervening event
- the parties' knowledge, expectations and assumptions
- the effect of the event on performance
The court also said the question is one of "evaluation", not mechanical rule-following.
The working model: four questions
In practice, the test breaks into four questions. Treat them as a working model, not as a statutory list.
- What was undertaken? Construe the contract to identify the obligation as originally agreed. Include its context and any express allocation of risk.
- What has happened since? Identify the supervening event and how it affects performance. It must arise after the contract was made and without default by either party.
- Is performance now radically different? Compare the obligation as undertaken with the obligation as it would have to be performed. The comparison is about the nature of the obligation, not its burden.
- Would it be just to hold the parties to the bargain? The courts describe frustration as resting on the justice of the case. The threshold is high, and the party relying on it carries the burden.
The word "radical" matters. Lord Radcliffe's formulation does not ask whether the contract has become difficult. It asks whether it has become a different thing.
Harder or costlier is not enough
The most common error in this area is treating hardship as frustration. English courts reject that approach repeatedly.
In Davis Contractors itself, the builders agreed to build 78 houses for a fixed price in eight months. Labour shortages and bad weather stretched the work to 22 months and raised their costs. The House of Lords held the contract was not frustrated. The delay and cost were within what a builder might risk. The contract was still to build the houses, only at a loss.
In Tsakiroglou & Co Ltd v Noblee Thorl GmbH [1962] AC 93, a seller agreed to ship Sudanese groundnuts from Port Sudan to Hamburg. The closure of the Suez Canal in 1956 forced ships to sail around the Cape of Good Hope, a much longer and costlier route. The House of Lords held there was no frustration. The contract did not specify the route, and a longer journey was a more expensive way of doing the same thing.
Compare Taylor v Caldwell (1863) 3 B & S 826, where a music hall burned down before a series of concerts. Hiring the hall was impossible, not merely costly. The contract was discharged.
The following table summarises the contrast.
| Feature | Harder or costlier performance | Radically different performance |
|---|---|---|
| Effect on the obligation | Same obligation, heavier burden | Different obligation in substance |
| Typical example | Higher prices, longer route, labour shortage | Subject matter destroyed, performance made illegal |
| Legal result | Contract stays binding | Contract discharged automatically |
| Remedy for non-performance | Damages for breach | None, subject to the 1943 Act |
Delay as a special case
Delay can frustrate a contract, but only when it is long enough to defeat the commercial purpose. Courts ask whether the delay is so great that performance after it would be a different obligation. They do not ask only whether it is inconvenient.
In The Sea Angel, the delay in the arrest of a vessel was an important factor. The question there was whether the extent of the delay matched the original expectation of the parties.
A further point arises when a contract has no fixed end date. Courts then look at the likely duration of the disruption at the time the question arises. The classic illustration is Jackson v Union Marine Insurance Co Ltd (1874) LR 10 CP 125, where a ship ran aground on the way to load cargo. The delay in refloating it was so long that it defeated the commercial venture. Contrast a short interruption to a long lease, which rarely frustrates the lease. This is the point made in National Carriers Ltd v Panalpina (Northern) Ltd [1981] AC 675, where a road closure of about 20 months did not frustrate a ten-year lease of a warehouse. Roughly half of the term remained available for use after the closure.
Timing and the objective standard
Two practical points shape how a court applies the test.
- Assessment is objective. The question is not whether the parties thought the contract was at an end. A court considers how a reasonable observer would assess the situation.
- Timing matters. Frustration is judged by the position when the event occurs, on the facts then known or reasonably foreseeable, even though a court later hears the case with hindsight. A party who declares the contract frustrated too soon, and then stops performing, risks being in repudiatory breach if a court later disagrees.
Applying the test: a worked example
Suppose a company agrees to supply 10,000 tonnes of steel to a buyer at a fixed price, delivered in six months. Two months later, a tariff raises the seller's cost of buying raw materials by 40 percent. Supply remains lawful and possible.
Apply the four questions.
- The seller undertook to deliver steel at a fixed price. Fixed price means the seller accepted the risk of cost movements.
- The supervening event is a tariff. It arose after the contract and was not the seller's default.
- The obligation is still to deliver steel. Delivery is more expensive, but it is not a different thing.
- Holding the seller to the price is not unjust in the relevant sense. The price was fixed to allocate this risk.
The contract is not frustrated. The seller must perform or pay damages.
Now change the facts. A statute passes that makes it unlawful to export steel to the buyer's country. The obligation can no longer be performed lawfully. The test is met through illegality, which the next chapters discuss.
Question 1: What was undertaken? -> Deliver 10,000 tonnes of steel at a fixed price.
Question 2: What has happened? -> Tariff raises raw material cost by 40 percent.
Question 3: Radically different? -> No. Same goods, same buyer, higher cost.
Question 4: Unjust to hold to bargain?-> No. Fixed price allocated the cost risk.
Result: Not frustrated. Seller remains bound.Common errors
- Treating a loss-making contract as frustrated. A bad bargain is not a frustrated one.
- Ignoring the contract's own wording. If the contract allocates the risk, the court will usually respect that allocation. A force majeure clause may govern the situation instead, as a later chapter explains.
- Relying on a foreseeable event. If the parties foresaw the event, or could have, courts are slow to find frustration. The limits chapter covers this in detail.
- Quoting the test without applying it. Citing "radical difference" is not analysis. Show why the changed obligation differs in nature, not only in cost.
- Assuming frustration is optional. If it applies, discharge is automatic. The parties cannot choose to keep the contract alive.
Exercise
A haulier agrees to carry goods from London to Rome for a fixed fee. A landslide closes the usual Alpine pass, and the only alternative route adds two days and 30 percent to the cost. The contract does not specify the route. Is the contract frustrated? Give your reasoning using the radical difference test.
Show answer
Probably not. The obligation undertaken was to carry the goods to Rome, and it still can be, by a longer and costlier route. This matches Tsakiroglou v Noblee Thorl, where closure of the Suez Canal did not frustrate a contract that did not specify the route. The change affects the burden of performance, not the nature of the obligation, so the haulier remains bound or pays damages. The answer might differ if the contract required the specific pass or if the goods were perishable and the delay destroyed their value, because the nature of the obligation could then change.
Exercise
In National Carriers v Panalpina, a road closure lasting about 20 months affected access to a warehouse held under a ten-year lease. Why did the House of Lords decline to find frustration?
Show answer
The closure removed the tenant's use of the warehouse for only part of the term. A substantial part of the ten-year term remained after the closure, so the lease was not radically different from what was undertaken. The interruption was a temporary reduction in value, not the end of the commercial purpose of the lease.