Sub topic 6
Mitigation and reasonable endeavours obligations
This chapter assumes you know the basics of contract formation, the difference between express and implied terms, and how English cases and statutes are cited. It also assumes you have read the chapters on the anatomy of a force majeure clause and on causation and notice. Here the focus is on the duties that come attached to force majeure relief, and how courts read them.
Why clauses carry a mitigation duty
A force majeure clause moves risk from one party to the other, so the party claiming relief usually has to earn it. Drafters ask for three things:
- The event must have caused the failure to perform. Chapter 5 covered this.
- Notice must be given. Chapter 5 covered this too.
- The affected party must try to limit the damage and, where possible, still perform.
The third requirement is the subject of this chapter. It appears in two forms. Some clauses define the event as one whose effects could not be avoided by reasonable steps. Others set out a stand-alone duty to use "reasonable endeavours" to mitigate or overcome the event. A party that ignores either form risks losing relief altogether.
The contractual duty differs from the general common law rule that a claimant must mitigate its loss after a breach (British Westinghouse v Underground Electric Railways [1912] AC 673). That rule limits the damages a claimant can recover. The duty in a force majeure clause is a condition of the defaulting party's own excuse. If the clause makes mitigation a condition, failure to mitigate means no relief, and ordinary breach liability applies.
Where the duty sits in the clause
The duty can appear in three places, and the place affects what you must prove.
| Location of the duty | Typical wording | Practical effect |
|---|---|---|
| In the definition of the event | "beyond the reasonable control of the party, and the effects of which could not have been avoided by reasonable steps" | The claimant must show that no reasonable steps would have avoided the effects. The failure is part of the claimant's case. |
| As a condition of relief | "provided that the affected party uses reasonable endeavours to mitigate" | Relief depends on compliance. The other side will often raise a breach as a defence. |
| As a separate covenant | "The affected party shall use all reasonable endeavours to overcome the event" | A breach may give the other party its own claim, as well as defeat relief, depending on the drafting. |
Read the clause to see which of these applies. The burden of proof usually follows the party relying on the clause, so a duty written into the definition is normally the claimant's to prove.
What "reasonable endeavours" means
English courts treat endeavours wording as a scale rather than a single standard. The usual ranking, from weakest to strongest, is:
| Wording | General approach |
|---|---|
| "Reasonable endeavours" | Take one reasonable course. You need not try every available option, and you can weigh your own commercial interests (*Rhodia International Holdings v Huntsman International* [2007] EWHC 292 (Comm)). |
| "All reasonable endeavours" | Take all the reasonable courses open to you, not just one. Courts often read this as close to "best endeavours". |
| "Best endeavours" | Go further, though still short of ruining yourself. The party need not necessarily act against its own commercial interests entirely. The boundaries depend on the contract. |
Courts do not apply these labels mechanically. The context of the contract matters, and so do the cost of the step, the benefit it would bring, and what the clause is trying to achieve.
Factors courts and advisers weigh
A step is more likely to be required if:
- it is cheap relative to the contract value,
- it is within the party's own control (the party can do it without anyone's consent),
- it has a real prospect of working, and
- it fits the commercial purpose of the contract.
A step is less likely to be required if it means giving up a significant commercial interest, taking on a major new risk, or going outside the contract.
Does the duty require non-contractual performance?
The key question is whether reasonable endeavours can require a party to accept a different kind of performance from the one the contract specifies. In MUR Shipping BV v RTI Ltd [2024] UKSC 18, the contract required payment in US dollars. US sanctions on the paying party's group made dollar payments difficult, and the paying party gave a force majeure notice. The shipowner argued that payment in euros was available and that the clause required the payer to use reasonable endeavours to overcome the event.
The Supreme Court held that the duty to use reasonable endeavours to overcome the effects of the event did not require the payer to accept performance in a different form from the one the contract provided for. The clause was aimed at overcoming the event's effects on the contractual performance. It did not rewrite the contract or ask a party to accept something it had not agreed to.
The rule from this case is narrow and important. Without clear words to the contrary, mitigation and endeavours clauses ask you to try to perform the contract you made. They do not ask you to accept a substitute. Drafters who want a different result must say so.
The affected party shall use reasonable endeavours to mitigate the effects of a
Force Majeure Event. For the avoidance of doubt, reasonable endeavours include
(a) accepting delivery from an alternative source of the same specification
where the cost to the affected party does not exceed 110% of the contract
price, and (b) accepting payment in euros at the exchange rate published by
the European Central Bank on the due date, where payment in the contract
currency is prevented.This illustrative clause shows how a drafter can specify the steps. Part (a) sets a cost ceiling so that the duty is measurable. Part (b) deals directly with the issue in MUR by saying that payment in another currency counts as a reasonable endeavour. It takes the question out of the courts' hands.
Edge cases
- Cost. Courts generally do not require a party to spend whatever it takes. A step that costs far more than the contract is worth is unlikely to be reasonable, unless the clause says otherwise. A clause may still say that increased cost is not a force majeure event, which stands as a separate point from mitigation.
- Third-party consent. A step that depends on someone else's agreement, such as a licence or a supplier's goodwill, may not be within the party's control. The party usually only has to ask, and does not have to guarantee a result.
- Timing. The duty usually runs for as long as the event lasts. A party that tried once and then stopped may fail to show it kept using endeavours.
- Evidence. The affected party should keep records of the steps considered, the steps taken and the reasons for rejecting others. These records are the proof of compliance if the dispute reaches court.
- Choice between contracts. In some cases a party with limited supply has to decide which customer to serve. Courts have rejected relief where the party's own commercial choices, not the event, explain the failure. Chapter 5 covers this under causation.
A worked example
A manufacturer agrees to supply 1,000 units a month to a retailer. A flood closes the factory. The contract has a force majeure clause with a duty to use "reasonable endeavours to mitigate".
- The flood is a listed event, and it caused the failure. Causation is satisfied.
- The manufacturer gives notice within the required period.
- A sister factory 200 km away can make 400 units a month at a 5% higher cost. A reasonable manufacturer would very likely use it, so the manufacturer should supply 400 units. It cannot claim relief for the full 1,000.
- A competitor could supply the other 600 units, but this would mean the retailer receiving goods from a different maker. Under the logic of MUR, the clause does not require the manufacturer to arrange this unless the contract says so.
The result is partial relief. The manufacturer owes performance to the extent mitigation was possible and is excused for the rest.
Exercise
A supplier's contract says it will "use reasonable endeavours to overcome the effects of any Force Majeure Event". A port strike stops delivery by the agreed route. A rival shipping route exists, but it needs the buyer to accept delivery at a different port, which the contract does not allow. Is the supplier in breach of the endeavours clause if it does not use the rival route? Explain by reference to MUR Shipping v RTI.
Show answer
Probably not. In MUR, the Supreme Court held that a duty to use reasonable endeavours to overcome the effects of a force majeure event does not require a party to accept performance different from what the contract provides. Delivery at a different port is non-contractual performance. Unless the clause says that alternative delivery points count as reasonable endeavours, the supplier need not use the rival route, though it should still take any steps that fit within the contract's terms.
Exercise
Name two differences between the common law duty to mitigate damages and a contractual mitigation duty in a force majeure clause.
Show answer
First, the common law duty limits the damages a claimant can recover after a breach, while the contractual duty is a condition of, or a covenant attached to, the defaulting party's excuse. Second, the contractual duty's scope comes from the clause's wording, which can raise or lower the standard (for example "reasonable endeavours" or "all reasonable endeavours"), while the common law duty is a fixed rule of reasonableness.