Sub topic 5
Walking the Process and Collecting Data
This chapter covers how to gather the numbers for a current-state map. It assumes you can already name the product family and the start and end points of the map, and that you know what a process box and a data box are. You should also be comfortable with simple arithmetic on time and rates.
Why you walk the process
A current-state map describes how work actually flows today. It does not describe how the procedure says it should flow. The gap between the two is where most waste hides, and you only see that gap by going to the place where the work happens. Lean practice calls that place the gemba, a Japanese word for "the real place." In a factory it is the shop floor. In a service or software process it is the point of work: the support queue, the ticket board, the deployment pipeline, the desk where the form is processed.
Data from a system report or from a manager's memory is usually cleaner than reality. Standard times assume no breakdowns. Reports average away the bad days. People describe the process as designed, not as practiced. A walk replaces those assumptions with observations.
Plan the walk before you go
A good walk takes preparation. Cover these points first.
- Confirm the scope. Write the product family, the first step and the last step on a sheet. Anyone on the walk should be able to say where the map starts and ends.
- Choose the direction. Walk from the end of the stream back to the start, beginning at shipping or delivery. The steps nearest the customer set the pace for everything upstream, so you learn what the customer actually receives and how often. You can also walk forward. Pick one direction and keep it for the whole map.
- Tell the people involved. Explain that you are studying the process, not judging individuals. People give honest answers when they do not feel audited.
- Bring a blank data sheet. Use one row per step and fixed columns, so each step is measured the same way.
- Bring a stopwatch or timer, a pencil, and paper. Draw rough maps by hand first. Software comes later.
What to collect at each step
Collect the same fields at every process step. The table lists the usual ones and what each is for.
| Field | What it means | Typical source |
|---|---|---|
| Cycle time (C/T) | Time from one unit leaving the step to the next unit leaving it | Direct observation with a timer |
| Changeover time (C/O) | Time to switch from one product or type to another | Observation or operator report, confirmed by watching one |
| Uptime | Share of scheduled time the equipment or step is available | Maintenance or downtime logs, checked against the walk |
| Number of operators | People working at the step | Direct count |
| Available time | Working seconds per shift, after breaks | Shift schedule |
| Batch or pack size | Units moved or processed together | Observation |
| Scrap or rework rate | Share of units that fail or are redone | Quality records, checked on the floor |
| Inventory in front of the step | Units waiting before the step | Physical count |
Two items on this list need extra care: cycle time and inventory.
Cycle time
Cycle time is measured per unit, at the step, with a timer. Do not copy it from a routing sheet or a standard-work document. Those give the intended value.
- Time several cycles, not one. Record each and take a representative figure. A single reading can be lucky or unlucky.
- Time what happens at normal pace. Do not time the best operator on the best day, and do not time a trainee.
- Include the work the operator does inside the step: loading, inspecting, and unloading. Exclude waiting for material, which belongs to the queue.
- If the step is a batch, record the batch time and the batch size. Divide to get a per-unit figure and note both.
For a service or software process, the same rule holds. Time active work on an item, not the elapsed days between touches. A code review that sits for two days and takes twenty minutes of reading has a twenty-minute cycle time and two days of wait.
Inventory
Count what you see. In a plant, count pallets, bins, or boxes and multiply by the units in each. In a service stream, count items in the queue, such as open tickets, pending applications, or pull requests awaiting review. A queue that looks small on a report may be large on the floor, because items hide in inboxes, carts, and staging areas.
Write the count and the time you counted it. Inventory changes through the day, and a count taken just after a delivery will overstate it. If the level swings, take the count at a few different times and record a typical value, noting the range.
Handling variation
Real processes vary. One measurement is a sample and not a fact. Three habits help.
- Record the range. Note the shortest and longest observed cycle time, not just the typical one. A wide spread points to a stability problem on the map.
- Separate normal variation from rare events. A breakdown that happens once a month does not belong in the cycle time. It belongs in uptime. Keep the two apart.
- Write down the conditions. Note the shift, the product variant, and anything unusual. A reader of the map can then judge how far the numbers apply.
Beyond a single walk, repeat the walk on another shift or day if the process is unstable. Two walks that disagree sharply tell you something about the process, and that is useful to know.
Capture information flow while you walk
Material is only half the picture. At each step, ask how the operator knows what to work on next. Record the answers in a notebook.
- Who sends the customer order, and how often? Daily, weekly, or by a forecast?
- Who turns that order into a schedule, and what form does the schedule take?
- Does each step receive its own schedule, or does it respond to a signal from the step after it?
- Are there expediters, whiteboards, spreadsheets, or email chains that change the plan during the day?
These answers feed the information-flow section of the map. They also reveal whether work is pushed or pulled, which a later chapter covers.
A worked example
Suppose you are mapping a family of brackets, and you walk from shipping back to stamping. At shipping you time five cycles, in seconds: 60, 64, 61, 63, 62. The average is 62 seconds, so you record a cycle time of 62 s with a range of 60 to 64. You count 450 units waiting in front of shipping. At assembly you record 46 s, and 900 units wait. At welding you record 39 s, and 1,350 units wait. At stamping you record 1 s per unit, and 4,500 units wait.
The script below stores the sheet as data, computes the average of repeated timings, and checks that no field is missing before you leave the floor.
from statistics import mean
REQUIRED = ["name", "cycle_samples_s", "queue_units", "operators", "uptime_pct"]
walk = [
{"name": "Shipping", "cycle_samples_s": [60, 64, 61, 63, 62],
"queue_units": 450, "operators": 2, "uptime_pct": 100},
{"name": "Assembly", "cycle_samples_s": [45, 47, 46, 46, 46],
"queue_units": 900, "operators": 3, "uptime_pct": 95},
{"name": "Welding", "cycle_samples_s": [38, 40, 39, 39, 39],
"queue_units": 1350, "operators": 1, "uptime_pct": 90},
{"name": "Stamping", "cycle_samples_s": [1, 1, 1, 1, 1],
"queue_units": 4500, "operators": 1, "uptime_pct": 85},
]
for step in walk:
missing = [f for f in REQUIRED if step.get(f) is None]
if missing:
print(f"{step['name']}: missing {missing}, go back and collect it")
continue
samples = step["cycle_samples_s"]
print(
f"{step['name']}: cycle {mean(samples):.0f} s "
f"(range {min(samples)}-{max(samples)}), "
f"queue {step['queue_units']} units, "
f"uptime {step['uptime_pct']}%"
)Running it prints one line per step, for example Shipping: cycle 62 s (range 60-64), queue 450 units, uptime 100%. The check for missing fields matters more than it looks. It is far cheaper to notice a blank field on the floor than to discover it at the desk, when the process is no longer in front of you.
Common data-collection errors
- Copying standard times. The map then shows the plan, not the process. Always time at least a few cycles yourself.
- Timing only the best case. This hides instability and makes the stream look faster than the customer experiences.
- Mixing units. A cycle time per batch beside one per unit breaks every later calculation. Write the unit in each field.
- Counting inventory once. A single count may catch an extreme moment. Note when you counted.
- Collecting data from the desk. Reports are useful as a cross-check, but the walk comes first.
- Skipping the people. Operators know about the workarounds, the late deliveries, and the breakdowns. Ask them, and write down what they say.
Check the data before drawing
Before you leave the area, do a quick sanity pass. Do the queue sizes look believable against the daily demand? Does any step have a cycle time far above or below its neighbors, and is there a reason? Is every field filled in for every step? A few minutes of review here prevents a second trip.
Exercise
You are mapping a service process. A ticket takes 20 minutes of agent work, but a report shows an average of 3 days from opening to closing. Which number do you place in the cycle time field, which goes elsewhere, and how should you gather the first number?
Show answer
The 20 minutes of active agent work goes in the cycle time field. The remaining time is waiting, which belongs to the queue or wait time on the timeline. Gather the 20 minutes by observing several tickets being worked, at normal pace, and averaging them, instead of taking it from a report or a standard.
Exercise
At a welding step you time one cycle at 39 seconds and record it. Name two problems with this reading and say what you would do instead.
Show answer
One reading may not be representative, and it hides the spread between faster and slower cycles. Instead, time several cycles at normal pace, record the average and the range, and note the conditions such as shift and product variant. If the step is unstable, repeat the walk on another shift.