Sub topic 9
Information Flow and How Work Is Scheduled
This chapter covers the top half of the current-state map: the information flow. It assumes you can already draw process boxes, data boxes, and inventory triangles, and that you know how takt time is calculated. By the end you should be able to draw how a customer order becomes a production schedule, and explain why that schedule decides how much inventory the material flow carries.
Why information flow gets its own band
Material flow shows where the product physically goes. Information flow shows what tells each step to start working, what to make, and how much. On a current-state map the two are drawn separately. Material flow runs left to right along the bottom. Information flow sits above it, usually running right to left from the customer toward the earlier steps.
The reason to map information is that most inventory is created by a scheduling decision, not by the work itself. If a planner releases 4,500 stamped parts because a forecast said so, those parts sit in front of welding whether or not anyone ordered them. You will not see why the queue exists by looking at the material flow alone. You see it when you trace the signal that told stamping to run.
The elements of the information band
Information flow uses a small set of symbols. Draw each item you actually observe, and no others.
| Element | What it represents | Typical label |
|---|---|---|
| Customer box | The external party that places orders | Monthly demand, daily demand, pack size |
| Supplier box | The external party that supplies material | Delivery frequency, lot size |
| Production control box | The person, team, or system that issues schedules | "MRP", "Planner", "ERP" |
| Straight arrow | Information passed on paper, by phone, or in conversation | "Weekly fax", "Daily call" |
| Zigzag (lightning) arrow | Information passed electronically | "EDI 90-day forecast" |
| Schedule arrow | A schedule sent to a process | "Weekly schedule" |
| Production kanban or withdrawal kanban | A card signal that triggers production or movement | "Kanban post" |
| Go-see scheduling | An adjustment made by someone walking the floor | "Supervisor adjusts" |
Label every arrow with three things: what is sent, how it is sent, and how often. "Forecast, EDI, every 90 days" is useful. "Forecast" alone is not.
Tracing the signal from the customer
Start at the customer box and follow the order backward. Ask the people who do the scheduling, not the people who run the machines.
- What does the customer send, and how often? Record firm orders and forecasts separately.
- Who receives it? Name the role, not only the system.
- What does that role do with it? Common answers are to enter it into a planning system, to batch it into a weekly plan, or to adjust it by hand.
- What does each process receive? A daily schedule for each step is very different from a single schedule for the whole stream.
- Does anything go back? Expediting calls, shortage reports, and rework requests are all information flow and belong on the map.
Write down what you find, even if it looks untidy. The mess is often the finding.
In this picture, production control sends a separate schedule to every step. No step is told what the next step actually needs. That structure is the signature of push scheduling.
Push and pull as information patterns
Chapter material flow introduced push and pull as ways material moves. The same distinction applies to information, and the information view is the more reliable way to classify a process.
- Push. A central scheduler releases work to each step based on a forecast or plan. A step runs because it was told to, whether or not the next step is ready. Inventory builds between steps.
- Pull. A step produces only when the step after it signals a need, for example by removing a kanban card or emptying a supermarket slot. The signal travels backward from the point of consumption.
Two tests help you classify a step on the map:
- Which arrow arrives at this step? A schedule arrow from a central planner means push. A card or empty-slot signal from the next step means pull.
- If the next step stopped, would this step keep running? If yes, it is being pushed.
Many real streams are mixed. A shipping step may pull from a finished-goods supermarket while everything upstream is pushed from an ERP schedule. Draw it as you find it.
Why many schedules produce big queues
When each step receives its own schedule, each step is planned against a forecast, a batch size, and an assumed yield. Errors compound:
- The forecast is wrong, so the plan overproduces some items and underproduces others.
- Each step rounds up to a convenient batch, so it makes more than the plan needs.
- A downstream breakdown does not stop the upstream steps, because they were told to run.
- Expediting moves urgent orders to the front, which delays other orders and raises their queues.
The result is the pattern you can compute from the data boxes. In the example stream, stamping has a cycle time of 1 second but 4,500 units waiting in front of the next stage, which is 10 days of demand at 450 units per day. The queue is not caused by the stamping press being slow. It is caused by a schedule that lets the press run in large batches far ahead of need.
You can check this relationship quickly. The days of inventory at a step is the queue divided by daily demand.
DAILY_DEMAND = 450
queues = {
"Stamping": 4500,
"Welding": 1350,
"Assembly": 900,
"Shipping": 450,
}
for name, units in queues.items():
days = units / DAILY_DEMAND
print(f"{name}: {units} units = {days:.1f} days of demand")Running this prints 10.0, 3.0, 2.0, and 1.0 days. Add them and you get 16 days, which matches the lead time you will build on the timeline.
Scheduling signals worth recording
For each step, record the following in or near its data box, because they describe how the schedule behaves:
- Schedule frequency. Daily, weekly, or monthly. Longer intervals mean larger planned batches.
- Lot size or batch size. The quantity released at once.
- Changeover trigger. Who decides when to change the product, and on what basis.
- Schedule stability. How often the schedule is changed after release. Ask for a recent example.
- Expedite frequency. How often work is moved ahead of the plan.
Stability and expedite frequency are rarely in any system. You usually learn them by asking the supervisor, "How many times last week did the schedule change after it was printed?"
The pacemaker preview
In a pull or flow design, one step receives the customer's schedule and sets the pace for everything upstream. This step is called the pacemaker process. You do not choose it in the current-state map. You do notice which steps receive their own independent schedules, because in the future state most of those schedules disappear and are replaced by one schedule plus pull signals. Mark each independent schedule arrow now, so the future-state team can count how many there are.
Common errors when drawing information flow
- Drawing the system, not the practice. The ERP may produce a daily schedule, but the supervisor may ignore it and run a spreadsheet. Map what is followed.
- Leaving out informal signals. Phone calls, hallway requests, and "hot lists" are information flow. They are often the real scheduling mechanism.
- Unlabeled arrows. An arrow without content, medium, and frequency cannot be analyzed.
- Mixing up direction. Information arrows run from the sender to the receiver. A forecast arrow points toward production control, and a schedule arrow points away from it.
- Treating one schedule as one signal. If production control sends a weekly schedule and a daily revision, draw two arrows.
Reading information flow before you leave the gemba
Before you close the information band, check three things:
- Every process box has at least one incoming information arrow, or an explicit note that it works without one.
- The customer's demand figure on the map matches the demand used for takt time.
- You can name who would change the schedule if the customer order changed tomorrow, and how long that change would take to reach the first step.
The third question gives you a rough measure of how responsive the stream is. If a change takes a week to reach stamping, then up to a week of work is already committed to the old plan.
Exercise
A stream has three steps. Production control sends each step a weekly schedule built from a 90-day forecast. Step B has a 2-second cycle time and 1,800 units queued in front of it. Daily demand is 600 units. (a) How many days of demand is that queue? (b) Is Step B push or pull, and what evidence on the map supports your answer?
Show answer
(a) 1,800 / 600 = 3 days of demand. (b) Push. Step B receives a weekly schedule arrow from production control rather than a card or empty-slot signal from the next step, so it runs on the plan whether or not the downstream step needs parts. The large queue relative to its fast cycle time is consistent with batch release by schedule.
Exercise
Name two pieces of scheduling information that are usually missing from planning systems but should still appear on an information-flow band, and say how you would collect them.
Show answer
Examples are schedule stability (how often the schedule changes after release) and expedite frequency (how often work is moved ahead of plan). Collect them by asking supervisors and schedulers for recent concrete cases, such as how many changes were made to last week's schedule, and by checking hot lists or expedite requests at the point of work.