Sub topic 11
Process Cycle Efficiency and a Little's Law Cross-Check
What this chapter assumes
You have a current-state map with process boxes, data boxes, inventory triangles, and a timeline along the bottom. You can calculate takt time, which is available working time divided by customer demand. This chapter turns the timeline into two numbers you can defend: process cycle efficiency (PCE), and a Little's Law check that confirms the timeline is internally consistent.
Process cycle efficiency
PCE is the share of total lead time in which work is actually being done on the product:
PCE = process time ÷ lead time
Lead time is the sum of all wait time and all process time, from the moment an order enters the mapped stream until it leaves. Process time is the sum of the cycle times of the steps. If a unit spends 148 seconds being worked on and 432,000 seconds waiting, almost all of its life is queue.
Typical PCE values are low. Many discrete manufacturing streams sit in the low single digits of a percent. Office and software delivery streams are often below 10%. A PCE of 25% or more is usually seen only in streams that already have pull flow and small queues. Treat these figures as rough orientation, not targets. The useful comparison is your own current state against your own future state.
Value-added time versus process time
Strictly, the numerator of PCE is value-added time: the part of the work the customer would pay for. Process time also includes necessary non-value-added work, such as inspection or a required approval. Many teams use total process time because it is easy to read from the data boxes. That version is an upper bound on true PCE.
Choose one definition, write it on the map, and use it the same way on the future-state map. If you switch definitions between maps, the improvement you report will be an artifact of the change in definition.
A worked example
The map below covers a product family with demand of 450 units per day and 27,000 available seconds per day. Takt time is 27,000 ÷ 450 = 60 seconds.
| Step | Cycle time (s) | Queue in front (units) | Wait (working days) |
|---|---|---|---|
| Stamping | 1 | 4500 | 10.0 |
| Welding | 39 | 1350 | 3.0 |
| Assembly | 46 | 900 | 2.0 |
| Shipping | 62 | 450 | 1.0 |
Wait time in days is the queue divided by daily demand. This is the idea behind Little's Law, which we return to below. Summing the wait column gives 16 working days, or 16 × 27,000 = 432,000 seconds.
- Total process time = 1 + 39 + 46 + 62 = 148 seconds.
- Lead time = 432,000 + 148 = 432,148 seconds, about 16.01 working days.
- PCE = 148 ÷ 432,148 ≈ 0.034%.
Put another way, 99.97% of the time a unit spends in this stream is waiting. Improving the 62-second Shipping step by 10 seconds would barely move the lead time. Cutting the 4,500-unit queue in front of Stamping would move it a great deal.
Computing it in code
The script below reproduces the arithmetic and flags any step slower than takt. It is useful when a map has more than a handful of steps and you want to re-run it each time you correct a data box.
AVAILABLE_SECONDS_PER_DAY = 27000 # 7.5 working hours
DAILY_DEMAND = 450 # customer demand, units per day
takt_s = AVAILABLE_SECONDS_PER_DAY / DAILY_DEMAND # 60.0 seconds per unit
# queue_units is the inventory waiting in front of each step
steps = [
{"name": "Stamping", "cycle_s": 1, "queue_units": 4500},
{"name": "Welding", "cycle_s": 39, "queue_units": 1350},
{"name": "Assembly", "cycle_s": 46, "queue_units": 900},
{"name": "Shipping", "cycle_s": 62, "queue_units": 450},
]
# Wait time in working days = queue / daily demand
for s in steps:
s["wait_days"] = s["queue_units"] / DAILY_DEMAND
total_wait_s = sum(s["wait_days"] for s in steps) * AVAILABLE_SECONDS_PER_DAY
total_process_s = sum(s["cycle_s"] for s in steps)
lead_time_s = total_wait_s + total_process_s
pce = total_process_s / lead_time_s
print(f"Takt time: {takt_s:.0f} s")
print(f"Lead time: {lead_time_s / AVAILABLE_SECONDS_PER_DAY:.2f} working days")
print(f"Process time: {total_process_s} s")
print(f"Process cycle efficiency: {pce:.4%}")
for s in steps:
if s["cycle_s"] > takt_s:
print(f"{s['name']} cycle time exceeds takt time")It prints a takt time of 60 s, a lead time of 16.01 working days, a process time of 148 s, and a PCE of 0.0342%. It also reports that Shipping exceeds takt time.
Little's Law as a cross-check
Little's Law relates three averages in a stable system:
lead time = work in process ÷ throughput
Here work in process (WIP) is the average number of units inside the mapped boundary, and throughput is the average number of units leaving per unit of time. The law holds regardless of how the work is scheduled or in what order it is processed, so it makes a good independent check.
In the example, the map shows 4,500 + 1,350 + 900 + 450 = 7,200 units of inventory. Shipping 450 units per day gives 7,200 ÷ 450 = 16 days. The timeline says 16.01 days. The two figures agree, which tells you the inventory counts and the wait calculations are consistent.
def littles_law_lead_time(wip_units: float, throughput_per_day: float) -> float:
"""Average lead time in days = work in process / throughput."""
return wip_units / throughput_per_day
# 7200 units in the whole stream, 450 units shipped per day
print(littles_law_lead_time(7200, 450)) # 16.0 daysWhy the check is nearly circular here
In this example the timeline's wait times were themselves derived from queue ÷ demand, so the agreement is close to guaranteed. The check earns its keep when the inputs come from different places. For example, take wait times from tracked units ("this order sat for 3 days") and WIP from a physical count or a system report. If those independent sources agree with Little's Law, you can trust the map. If they disagree, one of them is wrong.
When the two numbers disagree
A gap of more than about 10% is a signal to investigate. Common causes:
- Mismatched units. WIP in units, throughput in orders, or days mixed with calendar days. Convert everything to one unit and one clock, and write the clock on the map.
- Inventory outside the boundary. Stock that sits before the first step or after the last one is counted in WIP but not in the timeline, or the reverse. Use the start and end points you chose when scoping.
- A snapshot that is not typical. A queue counted the day after a large shipment, or at month-end, is not the average. Count on several days, or ask operators what the normal range is.
- Throughput that is not demand. The example uses 450 units per day as throughput, but Shipping takes 62 seconds per unit. That caps its output at 27,000 ÷ 62 ≈ 435 units per day. If the stream really ships 435, the Little's Law lead time is 7,200 ÷ 435 ≈ 16.6 days, and the queues are growing or demand is being missed. Use measured departures for throughput, and compare them with demand separately.
- A system that is not stable. Little's Law assumes that, on average, inflow equals outflow. During a ramp-up, a backlog build-up, or a seasonal swing, the averages will not match.
Reading PCE honestly
- PCE is a ratio of averages. It hides variation. A unit that happened to skip the queue will have a far higher PCE than the average, and the worst units will be far lower.
- Lead time includes waiting you may not control. A 10-day queue in front of Stamping may be due to batch purchasing policy, not to anything inside the stamping department. Mark where each queue originates.
- Raising PCE is mostly about cutting queues. Shortening process time by 20% in this example raises PCE from 0.0342% to about 0.0274% only if lead time stays fixed, which is a decrease. In fact, cutting process time by 20% lowers both numerator and denominator, and the change in PCE is negligible. Cutting total inventory by half roughly doubles PCE. Compare the levers before choosing a target.
- Do not chase PCE of 100%. Some waiting, such as a curing step or a required review, is physically or legally necessary. Record it as necessary non-value-added time.
A short checklist
- Confirm every data box uses the same time basis, such as working seconds per day.
- Compute wait time per step from queue ÷ demand, or from tracked units if you have them.
- Sum waits and process times into lead time.
- Compute PCE and note whether the numerator is value-added time or total process time.
- Sum all inventory and compute Little's Law lead time with measured throughput.
- If the two lead times differ by more than about 10%, resolve the gap before drawing conclusions.
Exercise
A current-state map shows 3,000 units of inventory in total, a measured output of 250 units per day, and a total process time of 120 seconds. One working day has 25,000 seconds. (a) What is the Little's Law lead time in days? (b) What is the PCE, taking lead time as the Little's Law lead time? (c) The timeline on the same map adds up to 9 days. What should you do?
Show answer
(a) 3,000 ÷ 250 = 12 working days. (b) Lead time in seconds is 12 × 25,000 = 300,000, so PCE = 120 ÷ 300,000 = 0.04%. (c) The 9-day timeline and 12-day Little's Law result differ by 25%, well above the 10% tolerance. Check for mismatched units, inventory outside the map boundary, an atypical inventory count, or throughput that differs from demand, then correct the data box that is wrong before reporting PCE.
Exercise
Why can reducing the cycle time of the slowest step leave PCE almost unchanged in a stream whose PCE is below 1%?
Show answer
Process time is a tiny fraction of lead time, so a few seconds saved in one step changes the numerator and the denominator by almost nothing. PCE rises meaningfully only when waiting time falls, which means reducing the inventory queues between steps.