Value-Added, Necessary Non-Value-Added, and Waste
This chapter assumes you know what a value stream map is and have seen the map's basic layout. It also assumes you are comfortable adding up times in seconds and minutes. The goal is a consistent way to classify every activity you meet on the map. You will need that classification later, when you build the timeline and calculate process cycle efficiency (PCE).
The three categories
Lean thinking sorts every activity in a value stream into one of three categories. The sorting depends on a single question: would the customer, looking at this activity, agree that it is worth paying for?
| Category | Definition | Typical examples | What to do |
|---|---|---|---|
| Value-added (VA) | Changes the product or service in a way the customer wants, and is done right the first time | Welding a seam, writing a feature the user asked for, cooking the meal | Protect it and make it more reliable |
| Necessary non-value-added (NNVA) | The customer would not pay for it, but the process cannot run without it today | Regulatory inspection, setting up a machine, invoicing, a security review | Reduce it, simplify it, or remove the need for it |
| Waste (muda) | Consumes time, money, or effort and gives the customer nothing | Waiting in a queue, rework, searching for tools, producing before an order exists | Eliminate it |
A VA activity must pass three tests together:
- The customer cares about the result.
- The activity transforms the product or service, so it is physically or informationally different afterward.
- It is done correctly the first time.
If an activity fails any test, it is not VA. Welding passes all three. Re-welding a rejected joint fails the third test. Moving the part to the next station fails the second.
Necessary versus waste: the judgment call
The hardest decision is between NNVA and waste. Ask this: if we deleted the activity tomorrow, what would break?
- If the product would be illegal, unsafe, or impossible to make with current equipment, the activity is NNVA.
- If nothing would break, the activity is waste.
NNVA is a statement about the current process, not a permanent label. A changeover on a stamping press is necessary today. If you redesign the tooling so the changeover takes seconds, most of that NNVA time disappears. NNVA is a target for redesign. Waste is a target for removal.
Classification also depends on whose eyes you use. An internal audit is NNVA for the end customer, but it may be essential to a regulator. Decide whose requirements count, write that down, and apply it to every step. Mixed viewpoints make the map inconsistent.
The eight wastes
Lean practice names eight common forms of waste. The mnemonic TIMWOODS is a convenient way to remember them. The table shows where each one tends to show up on a current-state map.
| Waste | Meaning | Where it appears on the map |
|---|---|---|
| Transport | Moving material or information that does not need to move | Long arrows between distant process boxes |
| Inventory | Stock beyond what the next step needs right now | Triangles between process boxes |
| Motion | People walking, reaching, or searching | Observed at the gemba and noted in data boxes |
| Waiting | Work or people idle until something arrives | Wait time on the timeline |
| Overproduction | Making more, or earlier, than the customer ordered | Push arrows and large inventory after a step |
| Overprocessing | Doing more work than the customer requires | Tight tolerances, extra approvals, duplicate reports |
| Defects | Scrap, rework, and correction | Low first-pass yield in the data box |
| Skills (unused talent) | Not using people's knowledge and ideas | Rarely drawn, but visible in interviews |
Overproduction is often called the worst of the eight. It causes inventory, which causes waiting and hides defects, and it forces extra transport and motion.
Where the waste is: inside steps and between steps
A step's cycle time (CT) in a data box is the total time to complete one unit at that step. It is not all value-added. It can contain VA work, NNVA work, and waste. The queue in front of the step is a separate source of waste.
The following Python snippet breaks the 39-second Welding cycle from an example current-state map into the three categories. It is complete and runs as shown.
from collections import defaultdict
# (activity, seconds, category) observed at the welding station
# VA = value-added, NNVA = necessary non-value-added, W = waste
activities = [
("Weld seams", 30, "VA"),
("Load part into fixture", 5, "NNVA"),
("Walk to get fasteners", 3, "W"),
("Re-weld rejected joint", 1, "W"),
]
totals = defaultdict(int)
for name, seconds, kind in activities:
totals[kind] += seconds
cycle = sum(totals.values())
for kind in ("VA", "NNVA", "W"):
share = totals[kind] / cycle
print(f"{kind:<5}{totals[kind]:>3} s {share:>6.1%}")
print(f"Cycle time: {cycle} s")Output:
VA 30 s 76.9%
NNVA 5 s 12.8%
W 4 s 10.3%
Cycle time: 39 sInside the step, 77% of the time is value-added, which looks healthy. The picture changes once you add the queues, as the next section shows.
Waste between steps dominates
Suppose the whole stream has the four steps from the running example: Stamping (1 s), Welding (39 s), Assembly (46 s), and Shipping (62 s). Total process time is 148 seconds. The inventory queued in front of those steps adds up to 7,200 units, and customers take 450 units per day. The lead time is therefore 7,200 / 450 = 16 working days.
A working day of 7.5 hours is 27,000 seconds, so 16 days is 432,000 seconds. Even if every one of the 148 process seconds were value-added, the best possible PCE is 148 / 432,148, which is about 0.034%. In practice it is lower, because some of those seconds are NNVA or waste.
The usual finding on a first map is that most waste is not on the shop floor in the form of visible motion or rework. It is in the queues, where nobody is doing anything to the product.
Classifying activities on your own map
Use a short routine for every activity you observe at the gemba (the place where the work actually happens).
- Write down what you saw, with a time if you can measure one. Do not classify while you observe, because you may bias what you record.
- Apply the three VA tests. If all three pass, mark it VA.
- If it fails, ask what would break if you removed it. If something would, mark it NNVA and note the reason, such as "regulation" or "current equipment".
- Otherwise mark it waste and assign one of the eight types.
- Record the classification next to the activity, so the team can challenge it later.
Doing step 5 matters more than it seems. A classification that nobody can see is a classification that nobody can correct.
Common errors
- Treating all cycle time as value-added. The data box shows the step's total time. Splitting it by category needs separate observation, as in the code above.
- Calling every inspection waste. Inspection to catch defects you caused is waste. Inspection required by a regulator or a customer contract is NNVA. The first goes away when you fix the cause. The second stays until the rules change.
- Labeling people's work as waste. The categories describe activities, not workers. Saying "this step is waste" is accurate. Saying "this person is waste" is wrong and damages the data collection that follows.
- Ignoring waiting because nobody looks busy-looking at it. Wait time is invisible on the floor because no one is doing anything. It appears only when you convert inventory into days.
- Deciding NNVA is permanent. If a necessary activity is expensive, ask what design change would make it unnecessary.
- Mixing viewpoints. Pick one definition of "customer" for the map and keep it.
What carries forward
The classification feeds two later steps. On the timeline, wait time and non-VA process time become the gap between lead time and VA time. In the reading-the-map chapter, you will use the categories and the eight wastes to decide where to place improvement bursts. For now, the aim is to be able to look at any activity and say which category it falls into, and why.
Exercise
At an invoicing step, a clerk spends 20 seconds entering the order into the billing system, 10 seconds fixing a customer name that was misspelled upstream, and 5 seconds looking for a purchase order number. Entering the order is required by the tax authority. Classify each activity and give the cycle time split.
Show answer
Entering the order is NNVA, because the customer does not care about it but the regulation requires it (20 s). Fixing the misspelled name is waste of the defects type (10 s). Looking for the purchase order number is waste of the motion type (5 s). The cycle time is 35 s. The split is 20 s NNVA (57.1%) and 15 s waste (42.9%), with no value-added time at this step.
Exercise
A stream has 5,400 units of inventory queued across all steps, ships 300 units per day, and the total process time of all steps is 120 seconds. A working day is 27,000 seconds. What is the lead time in working days, and what is the maximum possible process cycle efficiency?
Show answer
Lead time = 5,400 / 300 = 18 working days, which is 18 x 27,000 = 486,000 seconds. Maximum PCE = 120 / (486,000 + 120) = 120 / 486,120, about 0.0247%. It is a maximum because it assumes all 120 process seconds are value-added.