Reading the Map: Bottlenecks, Excess Inventory, and Improvement Opportunities
This chapter assumes you can draw a current-state map with process boxes, data boxes, inventory triangles, and a timeline. It also assumes you can compute takt time and process cycle efficiency (PCE). Here you use those numbers to decide where to improve.
What "reading" a map means
A finished map is a set of measurements, not yet a diagnosis. Reading it means comparing three kinds of numbers and asking where they disagree:
- Cycle time against takt time shows whether each step can keep up with the customer.
- Queue size against daily demand shows where work waits and for how many days.
- Process time against lead time shows how much of the elapsed time adds value.
The running example is a four-step stream. Customer demand is 450 units per day, with 27,000 available seconds per day, so takt time is 60 seconds.
| Step | Cycle time (s) | Queue in front (units) | Wait (working days) |
|---|---|---|---|
| Stamping | 1 | 4,500 | 10.0 |
| Welding | 39 | 1,350 | 3.0 |
| Assembly | 46 | 900 | 2.0 |
| Shipping | 62 | 450 | 1.0 |
Wait days come from queue divided by daily demand. Lead time is the sum of the waits plus the process time, which is about 16 working days. Process time is 148 seconds, so PCE is about 0.034%.
Step 1: Compare every cycle time to takt time
Takt time is the pace the customer sets. A step whose cycle time is above takt cannot meet demand, however well the other steps run.
In the example, Shipping takes 62 seconds against a takt of 60 seconds. Its capacity is 27,000 / 62, about 435 units per day, which is 15 short of the 450 demanded. Shipping is the bottleneck, the step that limits the output of the whole stream.
A second number, load, is cycle time divided by takt time. Load shows how much slack each step has:
| Step | Load (cycle ÷ takt) | Reading |
|---|---|---|
| Stamping | 1.7% | Far faster than needed |
| Welding | 65% | Slack available |
| Assembly | 77% | Slack available |
| Shipping | 103% | Overloaded |
Loads under 100% are not automatically good. A step at 1.7% load that is run in huge batches can still flood the stream, as the next section shows.
Step 2: Find where inventory piles up
Inventory on a map is a symptom, and each triangle has a cause. Queue size matters most where it is largest, so check three things:
- Where is the biggest queue? Here it is in front of Welding: 4,500 units, ten days of demand, and 62.5% of all waiting time.
- Is the upstream step faster than the one downstream? Stamping runs at 1 second per unit and can produce 27,000 units per day, 60 times the demand. Nothing slows it, so it builds stock.
- Is the work pushed or pulled? If Stamping follows a schedule from a planning system instead of a signal from Welding, it produces what the schedule says, not what Welding needs. That is push flow.
The most common cause of a large queue is a fast step with no limit on how much it may make. Large batches, long changeovers, and a "keep the machine busy" habit all produce the same picture.
A queue in front of the bottleneck is different from the rest. Some buffer before the constraint can be deliberate, so that the bottleneck never starves. The queue in front of Shipping (450 units, one day) is plausible for that reason. The ten-day queue in front of Welding has no such defense, because Welding is not the constraint.
Step 3: Compute where the time goes
Reading by eye works for four steps. For a real map with twenty steps, compute the ranking. This script loads the example data and flags overloaded steps, ranks queues by share of waiting time, and prints the PCE.
AVAILABLE_SECONDS_PER_DAY = 27000
DAILY_DEMAND = 450
takt_s = AVAILABLE_SECONDS_PER_DAY / DAILY_DEMAND
steps = [
{"name": "Stamping", "cycle_s": 1, "queue_units": 4500},
{"name": "Welding", "cycle_s": 39, "queue_units": 1350},
{"name": "Assembly", "cycle_s": 46, "queue_units": 900},
{"name": "Shipping", "cycle_s": 62, "queue_units": 450},
]
total_queue = sum(s["queue_units"] for s in steps)
for s in steps:
s["wait_days"] = s["queue_units"] / DAILY_DEMAND
s["wait_share"] = s["queue_units"] / total_queue
s["load"] = s["cycle_s"] / takt_s
s["capacity_per_day"] = AVAILABLE_SECONDS_PER_DAY / s["cycle_s"]
print(f"{'Step':<10}{'Load':>8}{'Capacity/day':>14}{'Wait (d)':>10}{'Wait share':>12}")
for s in sorted(steps, key=lambda s: s["wait_share"], reverse=True):
print(f"{s['name']:<10}{s['load']:>8.0%}{s['capacity_per_day']:>14.0f}"
f"{s['wait_days']:>10.1f}{s['wait_share']:>12.1%}")
bottlenecks = [s["name"] for s in steps if s["load"] > 1]
print("Bottleneck(s):", ", ".join(bottlenecks) or "none")
process_s = sum(s["cycle_s"] for s in steps)
lead_s = total_queue / DAILY_DEMAND * AVAILABLE_SECONDS_PER_DAY + process_s
print(f"PCE: {process_s / lead_s:.4%}")The output shows Stamping first, with a 62.5% wait share, and Shipping flagged as the only overloaded step. A Little's Law cross-check agrees with the timeline: 7,200 units in the stream divided by 450 units per day is 16 days.
Step 4: Look at what the numbers hide
Two different problems appear in this map, and they call for different responses.
| Problem | Evidence | Typical cause | Improvement direction |
|---|---|---|---|
| Capacity shortfall | Shipping load of 103% | Slow step, extra motions, waiting for parts | Shorten Shipping's cycle time or add capacity there |
| Excess inventory | 10-day queue after Stamping | Fast step, large batches, push schedule | Limit batch size, connect Stamping to Welding by pull |
Fixing the second problem does not fix the first. If you cut Stamping's queue to one day, lead time drops by nine days, but Shipping still ships only 435 units per day and the backlog will grow. If you speed up Shipping but leave the ten-day queue, you meet demand while still holding ten days of stock.
Step 5: Mark improvement opportunities on the map
The usual convention is to draw a kaizen burst (a starburst shape) at each spot where a specific improvement would help. Write a short action on each one, not a general wish. For this map:
- Shipping: reduce cycle time from 62 s to below 55 s, which gives about 10% headroom against takt. Look at packing motions, label printing, and waiting for carriers.
- Stamping to Welding: replace the schedule-driven push with a pull signal and a cap on the queue. A cap of two days (900 units) would cut about 8 days from lead time.
- Assembly and Welding: check whether the two queues behind them (900 and 1,350 units) are needed as buffers or are leftovers from batch sizes.
- Information flow: find who tells Stamping how much to make, and how often. If it is a weekly forecast, that may be the source of the push.
Each burst should be tied to a number on the map, such as a queue, a cycle time, or a wait. A burst with no number behind it is an opinion.
Common errors when reading the map
- Chasing the fastest step's utilization. A step at 1.7% load is not a problem to fix by running it more. Keeping it busy is exactly what built the 4,500-unit queue.
- Fixing the longest cycle time without checking takt. In the example, Shipping has the longest cycle time and also exceeds takt. If Shipping were 55 s, it would still be the longest, but it would be fine.
- Improving process time when waiting dominates. Cutting 5 seconds from Welding changes PCE from 0.0342% to about 0.0331%, a trivial gain next to a 9-day queue reduction. Waiting accounts for over 99.9% of lead time here.
- Mixing units. Queue days use working days, and process times use seconds. Convert both to the same unit before computing PCE, as the script does through the available seconds per day.
- Trusting a single reading. One day's queue count can be unusually high or low. Check it against another day, or against Little's Law, before you commit to a target.
Exercise
Exercise
A map has takt time of 80 s. Step A has cycle time 70 s and a queue of 800 units. Step B has cycle time 85 s and a queue of 200 units. Daily demand is 300 units. (a) Which step is the bottleneck? (b) What is the wait in days in front of each step? (c) If you could only fix one thing first to meet demand, which would it be?
Show answer
(a) Step B, because its cycle time of 85 s is above takt of 80 s (load 106%). Step A has load 87.5%. (b) Wait equals queue divided by daily demand: Step A 800 / 300 = 2.67 days, Step B 200 / 300 = 0.67 days. (c) Step B, the bottleneck. Step A's larger queue lengthens lead time, but only Step B stops the stream from meeting demand. Reducing Step A's queue is the second priority.