Sub topic 8
Material Flow, Inventory, and Push Versus Pull
This chapter assumes you can read a basic process-box layout, know the idea of takt time from the previous chapter, and are comfortable converting between units and days. Here you add the parts of the current-state map that show how material moves between steps and where it waits. You then decide, for each link between steps, whether work is pushed or pulled.
What material flow shows
Material flow is the path a product takes from supplier to customer. On the map it runs left to right along the bottom of the page, through the process boxes. Between two boxes you draw one of three things:
- An inventory triangle, if work waits there.
- A push arrow, if the upstream step sends work forward on its own schedule.
- A pull symbol, if the downstream step signals what it needs.
Draw what actually happens, not what the procedure says. If operators carry parts to a rack and someone fetches them an hour later, that rack is inventory, even if the work instruction does not mention it.
The same idea applies outside factories. In a software or service process, "material" is the work item: a ticket, a pull request, an insurance claim. A queue of ten days of open pull requests is inventory, and you draw it as a triangle.
Recording inventory
Draw an inventory triangle in front of each step where work waits. Write two numbers beside it:
- The quantity you counted, in the unit of the product (pieces, orders, tickets).
- The time that quantity represents, in working days of demand.
Convert quantity to time like this:
wait time (days) = quantity in queue ÷ daily customer demand
Use daily demand, not the step's own output rate. The time a unit waits depends on how fast the customer consumes the stream. Those two rates can differ a lot when a step runs in large batches.
Count inventory at the gemba during the walk. System stock figures often disagree with what is on the floor, because of scrap, parts parked in odd places, and unrecorded rework. If you must use system numbers, say so on the map.
Three kinds of inventory usually appear:
- Raw material, in front of the first step.
- Work in process (WIP), between steps.
- Finished goods, after the last step or in a shipping area.
Converting counts to days
The following script uses the queues from the running example (demand of 450 units per day) and flags the largest wait.
DAILY_DEMAND = 450 # units per working day
queues = [
("Stamping", 4500),
("Welding", 1350),
("Assembly", 900),
("Shipping", 450),
]
total_units = 0
total_days = 0.0
largest = None
for name, units in queues:
days = units / DAILY_DEMAND
total_units += units
total_days += days
if largest is None or days > largest[1]:
largest = (name, days)
print(f"{name:<9} {units:>5} units {days:>5.1f} days")
print(f"Total {total_units:>5} units {total_days:>5.1f} days")
print(f"Largest wait: {largest[0]} ({largest[1]:.1f} days)")Expected output:
Stamping 4500 units 10.0 days
Welding 1350 units 3.0 days
Assembly 900 units 2.0 days
Shipping 450 units 1.0 days
Total 7200 units 16.0 days
Largest wait: Stamping (10.0 days)The 16 days is the total wait that goes on the timeline in the next chapter. Stamping holds about 62% of it, and its cycle time is only 1 second.
Why inventory matters
Inventory is not harmless storage. Each unit of waiting work:
- Adds to lead time, because a unit cannot leave until the units ahead of it do.
- Hides defects. A bad batch is found only when someone downstream uses it, by which time thousands of units may be affected.
- Ties up cash and floor space.
- Can become obsolete if the design changes.
- Hides problems such as unreliable machines, because the buffer absorbs the stoppage.
Inventory also has legitimate uses. A small buffer can protect a customer from a machine failure, or cover a shipping interval. Record all inventory on the current-state map without judging it. Judgement comes when you read the map.
Push versus pull
The difference between push and pull is what triggers a step to start work.
- Push: a step produces according to a schedule or forecast and sends the output downstream whether or not the next step needs it.
- Pull: a step produces only when a downstream step has consumed something and signals the need.
A quick test for each link on the map: ask the operator, "What tells you to start the next batch?" If the answer is a schedule, a work order, or "when I run out of things to do", the link is push. If the answer is an empty bin, a returned card, or a free slot in a lane, it is pull.
How to draw each
| Situation | Map symbol | What it means |
|---|---|---|
| Upstream step sends work on its own schedule | Striped push arrow | Work is pushed. Queues tend to grow. |
| Downstream step takes from a stocked shelf | Supermarket symbol with a withdrawal kanban arrow | Pull. The supermarket holds a fixed, controlled quantity. |
| Work moves in order through a limited lane | FIFO lane symbol with a maximum count | Flow with a cap. Upstream stops when the lane is full. |
| Total WIP across several steps is capped | CONWIP loop, usually noted as text | A new job starts only when one finishes. |
Most real current states are mostly push. That is normal, and it is the finding, not an error in the map. Do not draw pull symbols that you hope to build later. They belong on the future-state map.
Reading the example
In the running example, stamping works from a weekly schedule and feeds welding with large batches. Welding and assembly each receive a work order. Shipping responds to customer orders. The map therefore shows push arrows from stamping to welding, welding to assembly, and assembly to shipping. The 4,500 pieces in front of stamping and the 1,350 in front of welding are what push flow looks like when each step follows its own plan.
Edge cases
Batch transfers
If a step moves work in batches of 500, then 499 pieces wait while the 500th is made. The batch is also inventory, even though it sits on a cart and not on a shelf. Record the batch size in the data box and include the in-process batch in the queue count.
Several products sharing one step
When the map covers one product family, a shared machine may hold work for other families. Count only the inventory that belongs to your family. Note the shared resource, because it explains delays that the family's own numbers cannot.
Inventory that is not a pile
In office and software work, inventory is often a list: a backlog, an inbox, a column on a board. Count items, not hours of estimated effort, and convert using the daily rate at which the customer receives finished items.
Unstable or seasonal queues
If a queue changes by a factor of two across the week, one count is misleading. Count on several days, record the typical value, and write the range next to the triangle. State which value you used on the timeline.
Obsolete or stuck stock
Parts that no one will use should be counted separately, or left out of the lead-time calculation with a note. Including them inflates wait time with units that never move.
Common mistakes
- Drawing the pull symbols you want rather than the control that exists.
- Counting only inventory in official storage areas and missing parts on carts, floors, and machines.
- Recording quantity but not converting it to days, so the map cannot feed the timeline.
- Treating a queue as a "buffer" without checking whether it is bigger than any failure it protects against.
- Mixing units, such as pieces in one queue and pallets in the next, so totals do not add.
Exercise
A map shows customer demand of 600 units per day. The queue in front of the first step is 3,000 units, the queue before the second step is 1,200 units, and the finished-goods area holds 600 units. The scheduling office releases work orders to both steps weekly. (a) How many days of inventory does each queue represent, and what is the total? (b) Is the link between the two steps push or pull, and how do you know?
Show answer
(a) Divide each queue by daily demand of 600: 3,000 / 600 = 5 days, 1,200 / 600 = 2 days, and 600 / 600 = 1 day. The total is 8 days, from 4,800 units. (b) It is push. Both steps start work when the scheduling office releases a weekly work order, not when a downstream step consumes material and signals for more, so the map shows a push arrow.