Sub topic 7
Customer Demand and Takt Time
This chapter assumes you can read a basic process flow, know what a cycle time is, and are comfortable with arithmetic on time and rates. You should also know how a current-state map is laid out, with process boxes, data boxes and a customer box. Here you will learn to turn customer demand into takt time, put it on the map, and compare it with the cycle time of each step.
Why takt time belongs on the map
Takt time is the pace of production that matches customer demand. The word comes from the German Takt, meaning a beat or rhythm. If the customer wants one unit every 60 seconds on average, the stream needs to complete one unit every 60 seconds on average. A faster pace builds inventory. A slower pace misses orders.
Takt time is a calculation from demand. It is not a measurement of the process. That is why it is useful: it gives you a fixed reference to hold every measured cycle time against.
On the current-state map, takt time appears in two places:
- In the customer box, next to the demand figure.
- In the comparison you make for each process box: is the cycle time at or below takt?
The formula
takt time = available working time per period / customer demand per periodBoth numbers must cover the same period and the same product family you scoped earlier.
Available working time
Available time is the time the process can actually produce. Start with the scheduled shift and subtract the planned stops that are the same every day.
| Item | Typical treatment |
|---|---|
| Shift length | Include |
| Scheduled breaks and lunch | Subtract |
| Planned team meetings, daily start-up routines | Subtract |
| Planned maintenance windows | Subtract |
| Unplanned downtime, breakdowns, changeovers, scrap | Do not subtract here |
Unplanned losses stay out of the takt calculation. They are problems of the process. If you subtract them, you hide them by lowering the pace you claim the customer needs.
A worked example: an 8-hour shift with 30 minutes of breaks leaves 7.5 hours. Work in seconds, because cycle times on the map are usually in seconds.
7.5 hours x 60 minutes x 60 seconds = 27,000 seconds per dayCustomer demand
Demand is what the customer actually requires of this product family, in units per period. Use the customer's rate, not your production plan. Sources include:
- Firm orders and the delivery schedule in the contract.
- Recent shipments averaged over a period long enough to smooth out noise.
- A forecast, when orders have not arrived yet. Mark it as a forecast on the map.
Use the unit the customer buys. If the customer orders pallets of 10 parts, either calculate takt per pallet or convert consistently. Mixing parts and pallets is a common source of wrong takt values.
Suppose the customer requires 450 units per day.
takt time = 27,000 s / 450 units = 60 seconds per unitCalculating it in code
The first script from this chapter's spine computes takt and then uses it to check each step. It also computes lead time and process cycle efficiency, which later chapters explain. For now, look at the takt line and the final loop that flags slow steps.
AVAILABLE_SECONDS_PER_DAY = 27000 # 7.5 working hours
DAILY_DEMAND = 450 # customer demand, units per day
takt_s = AVAILABLE_SECONDS_PER_DAY / DAILY_DEMAND # 60.0 seconds per unit
# queue_units is the inventory waiting in front of each step
steps = [
{"name": "Stamping", "cycle_s": 1, "queue_units": 4500},
{"name": "Welding", "cycle_s": 39, "queue_units": 1350},
{"name": "Assembly", "cycle_s": 46, "queue_units": 900},
{"name": "Shipping", "cycle_s": 62, "queue_units": 450},
]
# Wait time in working days = queue / daily demand
for s in steps:
s["wait_days"] = s["queue_units"] / DAILY_DEMAND
total_wait_s = sum(s["wait_days"] for s in steps) * AVAILABLE_SECONDS_PER_DAY
total_process_s = sum(s["cycle_s"] for s in steps)
lead_time_s = total_wait_s + total_process_s
pce = total_process_s / lead_time_s
print(f"Takt time: {takt_s:.0f} s")
print(f"Lead time: {lead_time_s / AVAILABLE_SECONDS_PER_DAY:.2f} working days")
print(f"Process time: {total_process_s} s")
print(f"Process cycle efficiency: {pce:.4%}")
for s in steps:
if s["cycle_s"] > takt_s:
print(f"{s['name']} cycle time exceeds takt time")The output reports a takt time of 60 s, and it flags Shipping, whose 62 s cycle time exceeds takt. The other three steps are under 60 s.
Comparing cycle time with takt time
The comparison is simple, and the interpretation is where the judgment lies.
| Relationship | What it means |
|---|---|
| Cycle time well below takt | The step can keep up with demand. It may be idle part of the time, or it may overproduce and feed inventory downstream. |
| Cycle time just below takt | The step meets demand with little margin. Any disruption makes it fall behind. |
| Cycle time above takt | The step cannot meet demand at the available time. It is a constraint, and work queues up in front of it. |
In the example, Shipping at 62 s is 2 s over takt. Over a day, that is a shortfall:
27,000 s / 62 s = 435.5 units per day, against demand of 450That is about 14 units short each day. A gap that looks tiny per unit is a visible shortage over a week.
Notice also that Stamping, at 1 s, is far below takt. Stamping is fast, and it sits behind a 4,500-unit queue in the data. A step that is much faster than takt, with no link to what the customer is pulling, tends to run ahead and pile up inventory. A fast step is not a problem in itself, but it needs a signal to stop.
Cycle time is not the only way a step can fail to meet takt. Changeovers, downtime and scrap reduce the output a step really delivers. The data box on the map should carry changeover time, uptime and yield so that you can judge an effective cycle time, not just a stopwatch value.
Edge cases
Several products in one family
When a family has variants with different demand, add the demand of all variants for the takt calculation. Then check each step against the combined takt using the weighted average cycle time, or the actual mix that arrives. If one variant takes much longer than the others, a step can meet takt on average and still miss it on a bad mix day.
Demand that varies
Demand is rarely flat. Choose a period that reflects the real pattern and say which one you used.
- If demand is steady, use the average daily rate.
- If demand has seasons, calculate takt for a typical period, and note the peak takt separately.
- If demand is lumpy from week to week, a weekly takt, divided over the working days, is steadier than a daily one.
Whatever you choose, write the demand, the period and the source on the map so others can reproduce the number.
Different shift patterns
If steps run different numbers of shifts, a single takt in seconds per unit still applies to the whole stream, but the available time in the formula must be that of the step you are checking. A step running two shifts has twice the available time. Compare consistently, for example by computing the output each step can deliver per day.
Parallel machines and operators
Cycle time on the data box is the time between completed units leaving the step. If three identical machines each take 150 s per unit, the step produces a unit every 50 s. Use the effective rate for the comparison, and record the number of machines or operators in the data box.
Takt time versus cycle time of the whole stream
Do not confuse takt time with lead time or with total process time. Takt is a rate, in seconds per unit. Lead time is how long one unit takes to pass through the stream. A stream can have a takt of 60 s and a lead time of 16 days.
Common errors
- Using total shift length and ignoring breaks, which gives a takt that is too slow.
- Subtracting breakdowns and changeovers from available time, which hides real problems.
- Using the production plan or the machine capacity as demand.
- Mixing units, such as parts for demand and pallets for cycle time.
- Calculating takt from one day's order spike.
- Writing takt on the map without the demand and available time behind it.
Recording takt on the map
Add the following to the current-state map:
- Customer demand per period in the customer box.
- Available working time per period, with the breaks you subtracted.
- The takt time result, in the same unit as your cycle times.
- A marker, such as a burst, on any process box whose effective cycle time exceeds takt.
These marks feed the later chapter on reading the map for bottlenecks.
Exercise
A cell works one 8-hour shift with two 15-minute breaks and a 30-minute lunch. Demand is 360 units per day. (a) What is the takt time in seconds per unit? (b) A step has a cycle time of 80 s. Can it meet demand alone, and how many units can it make in the available time?
Show answer
(a) Available time is 8 h - 30 min - 30 min = 7 h = 25,200 s. Takt = 25,200 / 360 = 70 s per unit. (b) No. 80 s is above the takt of 70 s. In 25,200 s the step makes 25,200 / 80 = 315 units, which is 45 short of demand. It needs a faster method, or a second machine or operator.
Exercise
Why should unplanned downtime not be subtracted from available time when you calculate takt time? Where should it appear on the map?
Show answer
Takt time expresses what the customer needs. Subtracting downtime would shorten the available time and make takt look faster or slower than the real demand rhythm, and it would hide a process problem. Downtime belongs in the data box of the affected step, usually as uptime, where it reduces that step's effective capacity when you compare it with takt.