Sub topic 13
Common Pitfalls When Mapping the Current State
This chapter assumes you can draw a current-state map with process boxes, data boxes, inventory triangles, and a timeline. It also assumes you can compute takt time, lead time, and process cycle efficiency (PCE) from that map. Here you learn where those maps go wrong, how to spot each error, and how to correct it before the map goes to future-state design.
Why mapping errors matter
A current-state map is the baseline for every improvement decision after it. If the baseline is wrong, the future state fixes the wrong problem. A map can look professional and still be wrong. The errors below fall into four groups: scope, data, drawing, and arithmetic.
| Group | Typical error | Symptom on the map |
|---|---|---|
| Scope | Mapping every product, or stopping at the plant door | Dozens of branches, or a lead time that ignores the customer |
| Data | Using standard times from a system instead of observed values | Cycle times with no variation and no notes |
| Drawing | Drawing the process as designed, not as run | No rework loops, no expediting, no workarounds |
| Arithmetic | Mixing seconds, minutes, and days | A PCE above 100% or a lead time that disagrees with inventory |
Scope pitfalls
Mapping too much at once
A map that covers all products becomes unreadable. Different products use different routes, so you end up drawing every route and none of the data. Choose one product family: products that pass through the same steps and equipment. If two products share fewer than about three quarters of their steps, treat them as separate families.
Wrong start and end points
Starting the map at the first internal step hides the supplier delay. Ending it at the dock hides the transport and customer receiving time. Draw the map door to door at minimum: from the customer's order back to raw material receipt. Write the start and end points on the map so reviewers can see what the lead time includes.
Mapping one step in great detail
Zooming into one machine's changeover is a different tool. Keep the current-state map at the level of process boxes where material is held, changed, or handed off. If a box has sub-steps you need, draw a separate detailed map for it later.
Data pitfalls
Copying numbers from the system
An ERP or scheduling system holds planned values: routing times, standard batch sizes, planned lead times. The map needs actual values. Walk the process, time it, and count the queues yourself. Where the system and the floor disagree, record the floor value and note the gap. The gap is often a finding in itself.
Using one observation
One stopwatch reading is not a cycle time. Take several readings across operators and shifts, then record a representative value and the range. A step that runs 40 s on a good day and 70 s on a bad day behaves differently from one that runs 55 s every day, even though the averages are similar.
Confusing cycle time, takt time, and lead time
These three are the most common mix-up:
- Cycle time is how long one step takes to process one unit.
- Takt time is the pace the customer demands: available time divided by demand.
- Lead time is the total elapsed time for a unit to cross the whole stream, including waiting.
Takt is computed from demand, never measured on the floor. A step is a bottleneck candidate when its cycle time exceeds takt. A long lead time does not by itself mean any step is slow, because most lead time is usually queue time.
Counting only the best case
Cycle time often excludes changeovers, breakdowns, rework, and scrap. Record these in the data box as changeover time, uptime, and yield. A step that runs 39 s per unit but is down 15% of the time delivers less than the number suggests.
Drawing pitfalls
Drawing the designed process
People describe the process as it should run. The actual process includes rework loops, expedited orders, extra inspections, and informal workarounds. Ask the operators "What happens when this goes wrong?" and add those paths. Mark each rework loop on the map with its rate.
Leaving out information flow
A map with only material flow cannot explain why inventory builds up. Draw the forecasts, orders, schedules, and verbal instructions that tell each step what to make. If a scheduler releases work to every step independently, the flow is push, and the map should show it.
Mapping future-state ideas into the current state
Do not draw the kanban you plan to add. Do not remove an inspection because you think it is waste. The current-state map records what exists, including what you intend to remove. Improvement ideas go on the map as burst symbols (kaizen bursts) or notes, clearly separate from the flow.
Drawing alone
One person at a desk produces a map that nobody owns. Map with at least one person from each major step, and have the operators confirm the finished map. Disagreements found at this review are cheaper to fix than errors found after a future state is built.
Arithmetic pitfalls
Mixing units
Cycle times are in seconds. Queues convert to days. Lead time is reported in days. If you add 62 s to 16 days without converting, the total is meaningless. Convert everything to one unit, usually seconds of available working time, before summing.
A related trap is calendar days versus working days. Wait time computed from daily demand is in working days, so convert with the available seconds per working day, not 86,400.
Wrong PCE
PCE is value-added time divided by total lead time. Using total process time as the numerator is acceptable only if every step is value-adding, which is rare. State which you used. Either way, a PCE above 100% means a unit error. Typical manufacturing PCE is a few percent or less, so a value near 0.03% is plausible when inventory is measured in days.
Skipping the cross-check
The timeline and the inventory counts describe the same stream from two angles. Little's Law says average lead time equals work in process divided by throughput. If they disagree by more than a few percent, one of the counts, the demand figure, or the throughput figure is wrong. A mismatch often means a hidden queue you did not count, or inventory that you counted twice.
Throughput in this check is what the stream actually ships per day, not planned demand. When shipments fall short of demand, the two differ, and the gap is itself worth investigating.
A script to catch arithmetic errors
This script audits a map's data. It computes the timeline lead time, compares it with the Little's Law figure, and flags steps slower than takt.
AVAILABLE_S = 27000 # 7.5 working hours, in seconds
DEMAND = 450 # units per day required by the customer
def audit(steps, throughput_per_day, tolerance=0.05):
"""Return a list of warnings about a current-state map."""
warnings = []
takt = AVAILABLE_S / DEMAND
wait_days = sum(s["queue_units"] / DEMAND for s in steps)
process_days = sum(s["cycle_s"] for s in steps) / AVAILABLE_S
timeline_days = wait_days + process_days
wip = sum(s["queue_units"] for s in steps)
little_days = wip / throughput_per_day
gap = abs(timeline_days - little_days) / little_days
if gap > tolerance:
warnings.append(
f"Timeline {timeline_days:.2f} d vs Little's Law "
f"{little_days:.2f} d differ by {gap:.0%}; recheck counts"
)
for s in steps:
if s["cycle_s"] <= 0:
warnings.append(f"{s['name']}: cycle time must be positive")
elif s["cycle_s"] > takt:
warnings.append(
f"{s['name']}: cycle time {s['cycle_s']} s exceeds takt {takt:.0f} s"
)
return warnings
steps = [
{"name": "Stamping", "cycle_s": 1, "queue_units": 4500},
{"name": "Welding", "cycle_s": 39, "queue_units": 1350},
{"name": "Assembly", "cycle_s": 46, "queue_units": 900},
{"name": "Shipping", "cycle_s": 62, "queue_units": 450},
]
print("Shipping 450 units/day:")
for w in audit(steps, throughput_per_day=450):
print(" -", w)
print("Shipping 360 units/day:")
for w in audit(steps, throughput_per_day=360):
print(" -", w)The first run reports only that Shipping exceeds takt, because 16.01 days from the timeline agrees with 16.00 days from Little's Law. The second run adds a mismatch warning (about 20%), because 7,200 units at 360 per day is 20 days, not 16. That disagreement tells you to recount the queues or confirm the real shipping rate before trusting the map.
Reviewing a map before handoff
Use this short checklist before sending the map on:
- The product family, start point, and end point are written on the map.
- Every number has a source: observed, counted, or taken from a named record.
- Variation is shown for cycle times and queues that are not stable.
- Rework loops, expediting, and workarounds appear.
- Information flow shows who tells each step what to make.
- All times are converted to one unit before totals.
- The timeline and the Little's Law figure agree within a few percent.
- Operators from each step have reviewed it.
Exercises
Exercise
A map lists queues of 2,000, 1,000, and 500 units, with daily shipments of 500 units. The timeline shows a total lead time of 5 days. Does the map pass the Little's Law cross-check? What is your next step?
Show answer
No. Work in process is 3,500 units, and 3,500 / 500 = 7 days, versus 5 days on the timeline, a gap of about 29%. Go back to the floor. Recount the queues, check whether the shipment rate is really 500 per day, and look for a hidden queue or a wrong wait-time conversion on the timeline.
Exercise
A team's draft current-state map shows a smooth flow with no rework loops, uses routing times from the ERP, and includes a planned kanban between two steps. Name three pitfalls and the fix for each.
Show answer
First, the drawn process is the designed one: ask operators what happens when things go wrong and add the rework loops with their rates. Second, the data are system values: time the steps on the floor over several observations and record ranges. Third, a future-state idea (the kanban) is on the current-state map: remove it from the flow and, if worth keeping, record it as a kaizen burst note.