Sub topic 5
Transferring a Threat
What transfer means
Assume you know how to assess probability and impact, calculate a risk score, and work within a project's scope, schedule, and budget.
Transferring a threat means shifting responsibility for some consequences to a third party. A threat is an uncertain event that could harm project objectives. Transfer usually moves financial responsibility or delivery responsibility through a contract, insurance policy, warranty, service agreement, or specialist supplier.
Transfer does not remove the threat. A supplier can still deliver late. An insurer can still reject a claim. The project team must check that the agreement actually covers the loss.
| Transfer method | What it can shift | Typical limitation |
|---|---|---|
| Fixed-price contract | Some cost-overrun risk | Scope changes may create extra charges |
| Insurance | Defined financial losses | Exclusions, deductibles, and claim limits |
| Warranty | Repair or replacement cost | Conditions and time limits apply |
| Service-level agreement | Service performance consequences | Credits may be smaller than the business impact |
When transfer fits
Transfer is useful when another party has better control, expertise, or financial capacity to handle the threat. For example, a project team may transfer payment-terminal delivery risk to a supplier through delivery terms and contractual penalties.
Before choosing transfer, check:
- Whether the third party can actually control the cause of the threat.
- Whether the contract language is specific and enforceable.
- The cost of the premium, fee, penalty, or supplier margin.
- The limits, exclusions, deductibles, and claim process.
- The third party's financial strength and ability to perform.
- The residual risk that remains with the project.
A risk owner remains necessary. The project risk owner monitors the agreement and confirms that the transfer is working. The third party does not replace project oversight.
Limits, residual risks, and secondary risks
A transferred threat often leaves residual risk. The supplier may pay delay damages, but the project may still lose customer trust or miss a regulatory deadline. A response can also create a secondary risk. For example, selecting a cheaper supplier to obtain stronger contractual protection may introduce quality risk.
Define the transfer precisely:
- State the event and measurable consequence.
- Name the responsible third party.
- Record the contract clause, policy, or warranty.
- Define evidence, notification deadlines, and claim steps.
- Assign a project owner and monitoring dates.
- Record residual and secondary risks.
ID: R-07
Type: Threat
Description: Key supplier may deliver the payment terminals late.
Probability: Medium (3/5) Impact: High (4/5) Score: 12
Strategy: Transfer
Response: Use a contract with delivery milestones, delay damages, and replacement-supplier rights.
Owner: Procurement lead
Trigger: Supplier misses the first confirmed shipping date
Contingency: Invoke the contract and switch to the qualified second supplier
Residual risk: Delay damages may not cover lost launch revenue
Secondary risk: The replacement supplier's quality is unproven
Status: OpenExercise
A project can buy insurance for equipment damage, but the policy excludes damage caused by poor installation. Is the threat fully transferred?
Show answer
No. The policy transfers only covered equipment losses. Installation-related damage remains a residual risk, so the team needs controls, a qualified installer, or additional coverage.