Sub topic 6
Mitigating a Threat
What mitigation means
Assume you know basic project management vocabulary, risk events, and qualitative probability-impact assessment.
A threat is an uncertain event that could harm a project objective. Mitigation is a response strategy that reduces the threat's probability, its impact, or both. The team acts before the event occurs instead of waiting for the problem.
For example, a project may depend on payment terminals arriving on time. Ordering an initial batch early reduces the probability that all terminals will be late. Qualifying a second supplier reduces the impact if the primary supplier fails.
Mitigation does not promise that the threat will disappear. It changes the exposure to a more acceptable level.
Design a mitigation response
Start with the risk statement and identify its causes, event, and effect.
- Identify the cause that makes the threat more likely.
- Identify the effect that would damage scope, schedule, cost, or quality.
- Choose an action that reduces the likelihood, the effect, or both.
- Assign an owner who can perform or coordinate the action.
- Define a due date and a measure of completion.
- Reassess the risk after the action.
Consider this example:
ID: R-07
Threat: Key supplier may deliver payment terminals late.
Initial exposure: Probability 3/5, impact 4/5, score 12
Strategy: Mitigate
Actions: Order the first batch early; qualify a second supplier.
Owner: Procurement lead
Measure: First batch ships before the integration test date.
Residual risk: The second supplier's quality is unproven.The response has two controls. Early ordering lowers the chance of a schedule delay. A qualified second supplier limits the delay's consequences if the first supplier fails.
Primary, residual, and secondary risks
A mitigation action can create new uncertainty. The remaining exposure is the residual risk. In the example, the project may still face a delay, and the second supplier may provide lower-quality equipment.
A secondary risk is a new risk caused by the response itself. Switching suppliers could create extra testing, contract fees, or compatibility work. Record these risks rather than assuming that the original response solved everything.
Check whether mitigation works
Track an observable measure, such as confirmed shipping dates, supplier test results, or the number of approved backup units. Recalculate probability and impact at planned review points. If exposure remains above the project's threshold, add actions, select another strategy, or escalate the risk.
Exercise
A data migration may fail because the source records contain inconsistent formats. What is one mitigation action, and what residual risk might remain?
Show answer
Run a profiling and cleanup pass before migration. Some inconsistent records may remain, so testing may still reveal conversion errors.