Recording Responses in the Risk Register
Prerequisites and purpose
Assume you know basic project management terms, can describe a risk as an uncertain event, and have used probability and impact assessments. This chapter shows how to turn a chosen response into a useful risk register entry.
A risk register is a shared record of identified risks and the information needed to manage them. Recording only “mitigate” or “accept” is not enough. The entry must tell the team what will happen, who will act, and how the team will know whether action is needed.
Fields that make a response actionable
Record the risk type, description, probability, impact, and score first. Then record the response strategy and the actions that implement it.
| Field | What to record | Example |
|---|---|---|
| Strategy | The selected response | Mitigate |
| Response | Specific planned actions | Order early and qualify a second supplier |
| Owner | Person accountable for monitoring and action | Procurement lead |
| Trigger | Observable condition that starts the response | First confirmed shipping date is missed |
| Contingency | Action taken if the risk occurs | Switch to the second supplier |
| Residual risk | Risk remaining after the response | Second supplier quality is unproven |
| Status | Current state of the response | Open |
The risk owner is accountable for keeping the entry current. The owner may delegate an action, but delegation does not remove accountability.
For an opportunity, record the equivalent details. A response such as “enhance” should state how the team will increase the opportunity's probability or impact. For example, an owner might offer an early-adopter incentive and schedule a decision-maker demonstration.
Example risk register entry
ID: R-07
Type: Threat
Description: Key supplier may deliver the payment terminals late.
Probability: Medium (3/5) Impact: High (4/5) Score: 12
Strategy: Mitigate
Response: Order a first batch early and qualify a second supplier.
Owner: Procurement lead
Trigger: Supplier misses the first confirmed shipping date
Contingency: Switch to the second supplier for the remaining batches
Residual risk: Second supplier's quality is unproven (secondary risk R-15)
Status: OpenThe response reduces exposure before the event. The contingency limits damage if the event occurs. The residual risk records what remains. The secondary risk records a new risk caused by the response itself.
Linking responses to monitoring
A register should support regular review. The owner checks whether response actions are complete, whether probability or impact has changed, and whether the trigger is approaching. Update the score, status, dates, and next actions when conditions change.
A response may also require a contingency reserve, such as extra time or money for a known risk. Record the reserve and its approval authority where your project controls require it. A management reserve is broader funding held for unforeseen work and is not the same as a risk-specific contingency reserve.
Exercise
A register says “Accept” but has no owner, trigger, or contingency. What should you add for active acceptance?
Show answer
Add an owner, an observable trigger, a contingency action, and any reserve needed to carry out that action.