Monitoring Whether Risk Responses Work
You should already know basic project terms, how a risk is scored by probability and impact, and how a team records risks in a risk register. This chapter focuses on what happens after a response is planned. A response is useful only if the team checks whether it changes the risk as expected.
Monitor the response, not only the risk
Monitoring means collecting evidence about three things:
- Implementation: Has the planned response happened?
- Effectiveness: Did it reduce a threat or improve an opportunity?
- New exposure: Did the response leave a residual risk or create a secondary risk?
For example, a team may plan to order payment terminals early and qualify a second supplier. The risk owner should check purchase dates, supplier confirmations, delivery progress, and the quality of the second supplier. “The response is in progress” is not enough evidence.
A useful monitoring record includes a measurable indicator, a target, an owner, and a review date.
| Risk response | Indicator | Target or threshold | Review action |
|---|---|---|---|
| Order terminals early | Confirmed shipment date | No later than 15 June | Escalate or activate contingency |
Use triggers and leading indicators
A trigger is a warning sign that a risk is becoming more likely or more severe. A leading indicator is a measure that gives an early signal before the risk affects a project objective.
For the supplier risk, examples include:
- The supplier has not confirmed the production slot.
- The first shipping date is missed.
- Quality checks fail on the initial batch.
- The second supplier cannot meet the required volume.
The risk owner compares these signals with the response plan. If a trigger occurs, the owner follows the agreed contingency or reports that the response needs to change.
Review and update the risk register
At each review, record the current status rather than copying the original plan. Update:
- The response actions completed and remaining.
- The current probability, impact, and overall score.
- The response owner and next review date.
- Any residual risk left after the response.
- Any secondary risk caused by the response.
- Whether contingency reserves or management reserves may be needed.
A response can succeed partly. For example, a second supplier may reduce the chance of delay but increase the chance of defective terminals. That new exposure needs its own entry or a linked secondary-risk record.
Decide when to change course
Use evidence to choose among three actions:
- Continue the current response because indicators meet the target.
- Modify the response because it is producing insufficient results.
- Activate the contingency or escalate because a trigger has occurred.
The project manager should also check whether the response still fits the project's risk appetite and authority. A response that was acceptable early in the project may become unacceptable after costs, deadlines, or dependencies change.
Exercise
A mitigation action is complete, but the risk score has not fallen and a warning indicator has crossed its threshold. What should the risk owner do?
Show answer
Record the evidence, reassess the risk, and modify the response or activate the defined contingency. The owner should also record any residual or secondary risk.