Sub topic 15
Contingency and Management Reserves
This chapter assumes you know basic project terms such as scope, schedule, budget, and stakeholders. It also assumes you can rate a risk using probability and impact.
A reserve is time or money held back to handle uncertainty. Reserves protect the project plan, but they are not permission to spend without control. Project teams usually distinguish between contingency reserves and management reserves.
Contingency reserves for identified risks
A contingency reserve covers a risk that the team has identified and analyzed. The event may not happen, but the project has a reasonable basis for estimating its possible cost or delay.
For example, a project might identify a risk that a supplier delivers equipment late. The team may add a two-week schedule reserve or a cost reserve for expedited shipping. The reserve belongs to the relevant project activity or work package when the plan supports that level of detail.
Contingency reserves are often called provisions for known unknowns. The uncertainty is known, even though the exact event or effect is not certain.
Use a contingency reserve when:
- The recorded risk occurs.
- The approved response needs more time or money than its original estimate.
- The project manager and governance process allow the use.
- The spending is recorded against the related risk.
Do not use it to hide poor estimating, fund unrelated scope, or avoid reporting a problem.
Management reserves for unforeseen work
A management reserve covers uncertain work that was not identified in the risk register when the baseline was created. It is therefore associated with unknown unknowns. Examples include an unexpected regulatory requirement or a major technical discovery.
Management reserve is normally part of the project's total approved budget but outside the cost baseline. The cost baseline is the time-phased budget used to measure performance. Moving management reserve into the baseline usually requires formal change control and approval from the sponsor or another authorized body.
| Reserve | Typical uncertainty | Where it sits | Common approval |
|---|---|---|---|
| Contingency reserve | Identified risk | Within the affected baseline or work package | Project manager or delegated authority |
| Management reserve | Unidentified or unforeseen work | Outside the cost baseline, within total budget | Sponsor or change control authority |
How the reserves relate
A response can also create a new risk. If expedited shipping uses a new supplier, the supplier's quality may become a secondary risk. Record and assess that risk rather than assuming the reserve solved every problem.
> callout note > A reserve is controlled capacity, not free money. Every use should identify the event, amount, authority, and effect on remaining exposure.
A practical control cycle
- Link each contingency reserve to an identified risk or response.
- Define who may authorize its use.
- Set a trigger and record the amount used.
- Recalculate the remaining reserve and expected project cost.
- Escalate when the reserve is insufficient.
- Release unused reserve only through the project's governance process.
Exercise
A documented supplier risk occurs, and the approved response needs additional shipping money. Which reserve should the team consider first, and what should it record?
Show answer
It should consider the contingency reserve first. It should record the risk, trigger, amount used, approver, updated forecast, and remaining exposure.