Sharing an Opportunity
Assume you know basic project management vocabulary, including scope, schedule, budget, stakeholders, and risk registers. You should also understand that a risk is an uncertain event that can affect project objectives and that probability and impact can be assessed qualitatively.
An opportunity is a risk that could produce a beneficial outcome. The share strategy means partnering with another party so both parties can increase the chance of gaining that benefit or can contribute resources needed to capture it.
Sharing is useful when your project cannot exploit the opportunity alone. A partner may have specialist knowledge, distribution channels, technology, funding, or access to customers. The partner accepts part of the responsibility and receives an agreed part of the benefit.
When to share an opportunity
Compare sharing with other opportunity strategies:
| Strategy | Best fit |
|---|---|
| Exploit | The project can make the opportunity happen by itself |
| Enhance | The project can increase its probability or impact |
| Share | Another party has capabilities or authority the project needs |
| Accept | The team takes no special action but remains ready to benefit |
For example, a software project may discover that a large retailer could adopt its new feature. The project team could share the opportunity with an implementation partner. The partner provides integration specialists and customer access. In return, the partner receives an agreed percentage of the resulting revenue.
Sharing is more than asking another organization for help. It requires a deliberate agreement about responsibilities, decisions, costs, benefits, and ownership.
Plan the partnership
Start by describing the opportunity and the benefit it could create. Then identify the partner's contribution and define how the parties will work together.
A useful agreement answers these questions:
- What result will show that the opportunity was captured?
- Which party performs each activity?
- Who pays for additional work?
- How are revenue, savings, or recognition divided?
- What decisions require joint approval?
- What happens if the partner misses its commitment?
- When will the arrangement end?
The project manager should assign an owner for the opportunity response. The owner coordinates the partner and tracks whether the response is producing the expected benefit. A trigger might be “the customer requests a proposal.” The response could then activate a joint sales meeting and a draft delivery plan.
Record and review the response
Record the opportunity, strategy, partner, owner, trigger, expected benefit, and agreement in the risk register. Also record residual risks, which are risks that remain after sharing. For example, the partner may gain customer access, but delivery quality may remain uncertain.
A secondary risk is a new risk caused by the response. A partnership might create a secondary risk such as disagreement over customer data or benefit allocation. Assign an owner and response for that risk as well.
Review the arrangement at planned checkpoints. If the partner cannot meet its commitments, consider an alternative partner, a changed agreement, or accepting the remaining opportunity without the original arrangement.
Exercise
A project has a promising market opportunity, but an external firm owns the required sales channel. Which response is most suitable, and what should the project record?
Show answer
Share the opportunity. Record the partner, responsibilities, benefit allocation, trigger, owner, agreement, and any residual or secondary risks.