Avoiding a Threat
Assume you know basic project terms, can describe a risk as an uncertain event, and have assessed probability and impact. This chapter focuses on one threat response: avoidance.
What avoidance means
A threat is a risk that could harm a project objective. Avoidance changes the project so the threat can no longer occur, or so its cause is removed. The team does not merely prepare for the event. It removes the exposure.
For example, suppose a project depends on a new payment integration that has not been tested with the required banking network. The team could avoid this threat by choosing an approved integration already used by the organization. The original integration threat no longer applies to the revised approach.
Avoidance can change:
- Scope, by removing a risky feature.
- Schedule, by moving work away from a known disruption.
- Technology, by replacing an unproven component.
- Delivery method, by using a supplier with established capability.
- Requirements, by selecting a standard rather than a custom solution.
When avoidance is suitable
Avoidance is strongest when the threat has high exposure and the project can change without violating its objectives. It is also useful when the threat's impact would be unacceptable, even if its probability is low.
| Situation | Possible avoidance decision |
|---|---|
| A specialized component has no qualified support team | Use a supported standard component |
| A release date overlaps a regulatory freeze | Move the release date |
| A feature requires unsafe production access | Remove or redesign the feature |
Avoidance has a cost. A simpler component may reduce functionality. A changed date may delay benefits. Removing a feature may reduce stakeholder value. Compare the cost of the change with the expected loss and with the project's risk appetite.
A practical avoidance workflow
- State the threat and its cause precisely. “The system may fail” is too broad. “The custom payment adapter may fail certification” identifies a decision point.
- Identify a change that removes the cause or exposure.
- Check the effect on scope, schedule, budget, quality, and stakeholders.
- Obtain approval if the change exceeds the project manager's authority.
- Update the risk register and project baselines.
- Check for new risks created by the change.
Document the decision
Record the selected strategy, the change that implements it, the owner, approval, and any remaining exposure. The avoided threat may close, but the replacement approach needs monitoring.
Exercise
A project may miss its launch because a required external service has no guaranteed capacity. What avoidance action could the team consider?
Show answer
Replace the service with an approved provider that has confirmed capacity, if the change fits the project's objectives and is authorized.