Residual and Secondary Risks
Prerequisites
This chapter assumes you know basic project management terms, what a risk is, and how probability and impact form a qualitative risk score. You should also understand the main response strategies: avoid, transfer, mitigate, accept, exploit, share, enhance, and escalate.
A risk response changes the original risk, but it may not remove uncertainty completely. The risk left after the response is the residual risk. A secondary risk is a new risk created by carrying out the response.
For example, a team may mitigate the threat that a supplier will deliver payment terminals late by ordering a first batch early and qualifying a second supplier. Some delivery risk remains. That is residual risk. The second supplier may have unproven quality, creating a new secondary risk.
How the two risks differ
| Risk type | Meaning | Example |
|---|---|---|
| Residual risk | The original risk that remains after a response | The primary supplier may still miss the revised date |
| Secondary risk | A new risk caused by the response | The backup supplier may provide faulty terminals |
Do not assume that a completed response means the risk is closed. Reassess probability and impact after the response. The residual score may be lower, unchanged, or occasionally higher.
Analyze residual risk
After selecting a response, ask:
- What probability and impact remain?
- Is the residual exposure within the project's risk appetite?
- Does the residual risk need its own owner, trigger, response, or reserve?
- Has the response introduced a new risk?
- Should the project sponsor approve the remaining exposure?
Risk appetite is the amount and type of uncertainty an organization is willing to accept. A low residual score may be acceptable for a routine schedule variance, but not for a safety or regulatory failure.
Acceptance can be passive or active. With passive acceptance, the team records and watches the risk. With active acceptance, the team prepares a contingency plan, defines a trigger, and sets aside resources.
Record both risks
Keep the original risk linked to any secondary risk. This prevents the team from losing the reason the new risk exists.
ID: R-07
Type: Threat
Description: Key supplier may deliver payment terminals late.
Strategy: Mitigate
Response: Order early and qualify a second supplier.
Residual risk: Delivery may still be late after the first batch.
Secondary risk: Backup supplier quality is unproven (R-15).
Owner: Procurement lead
Trigger: First confirmed shipping date is missed
Contingency: Switch remaining orders to the qualified backup supplier
Status: OpenThe owner monitors the trigger and checks whether the response works. If testing shows poor quality from the backup supplier, the team should assess R-15 separately and update its probability, impact, response, and reserve.
Exercise
A team transfers a cyber-risk to a vendor through an insurance policy. The vendor's claim process may delay recovery after an incident. What should the team record?
Show answer
The remaining cyber exposure is residual risk, and the possible recovery delay caused by relying on the vendor is secondary risk. Record owners, triggers, and contingency actions for both.