Sub topic 11
Accepting an Opportunity
When acceptance fits
Assume you know basic project management terms, understand that a risk is uncertain, and can use probability and impact ratings.
An opportunity is an uncertain event that could improve a project objective. Accepting an opportunity means the team chooses not to spend resources trying to make it happen. The team remains willing to benefit if the opportunity occurs.
Acceptance fits when:
- The opportunity has a modest benefit.
- An active response would cost more than the likely gain.
- The team cannot influence the cause.
- The opportunity is outside the project manager’s authority.
- The team has more important risks to manage.
Acceptance does not mean ignoring the opportunity. Record it, assign an owner, and decide how the team will notice it.
Passive and active acceptance
Passive acceptance requires no planned action. The team records the opportunity and reviews it during normal project monitoring. For example, a customer might approve an optional feature early, but the team does not change its plan to encourage that decision.
Active acceptance prepares the team to act if the opportunity occurs. Preparation might include reserving capacity, defining a decision rule, or identifying who can approve the action. These steps do not deliberately increase the opportunity’s probability. They make it easier to capture the benefit when it appears.
| Acceptance type | Team action | Example |
|---|---|---|
| Passive | Monitor through normal reviews | Record a possible referral without changing the sales plan |
| Active | Prepare a response after a trigger | Reserve production capacity if a bulk order arrives |
Record the trigger and decision
Suppose a larger customer might adopt a pilot and offer the project a bulk-purchase discount. If the discount is useful but unlikely, the team may accept the opportunity.
A useful acceptance plan includes:
- Trigger: the customer requests a pricing proposal.
- Owner: the sales manager watches for the trigger.
- Decision: the sponsor decides whether the discount justifies changing the delivery plan.
- Preparation: the team keeps the pricing model and capacity estimate current.
- Fallback: if the order would overload the team, use the normal delivery schedule or decline the extra volume.
The opportunity can still create a secondary risk. A large order may increase revenue but cause schedule pressure or quality problems. Record and assess that new uncertainty separately.
Document the choice
A risk register entry should make acceptance testable:
ID: R-11
Type: Opportunity
Description: A larger customer may adopt the pilot early, giving a bulk-purchase discount.
Probability: Low (2/5) Impact: High (4/5) Score: 8
Strategy: Accept
Owner: Sales manager
Trigger: Customer requests a pricing proposal
Action: Review the opportunity with the sponsor; do not change scope before approval.
Status: OpenReview the entry at risk meetings. Change the strategy if probability, benefit, capacity, or risk appetite changes.
Exercise
A possible partnership could save the project money, but pursuing it would require weeks of legal work and the project team has no influence over the partner. Which response is suitable?
Show answer
Accept the opportunity, record an owner and trigger, and monitor it without spending weeks pursuing it.