Contingency Plans, Fallback Plans, and Triggers
Prerequisites assumed
You should know basic project management terms, including scope, schedule, budget, stakeholders, and risk owner. You should also understand that a risk is an uncertain event that may affect a project objective and that probability and impact are used to assess it.
Plan responses before the risk occurs
A contingency plan is a predefined action taken if a known risk occurs. It is part of the planned response, not an improvised reaction. For example, a team may accept the possibility that a supplier will deliver late but prepare an alternate delivery schedule.
A trigger is an observable condition that shows the risk is becoming real or that action is now needed. A trigger must be specific enough for people to recognize consistently.
A fallback plan is the action used when the first response does not work or is no longer available. It protects the project from the failure of the primary response.
| Item | Purpose | Example |
|---|---|---|
| Trigger | Shows when to act | Supplier misses the confirmed shipping date |
| Contingency plan | First planned action after the trigger | Switch the delivery sequence |
| Fallback plan | Backup if the first action fails | Use a qualified second supplier |
Consider a payment-terminal project. The team might choose to mitigate the threat of late delivery by ordering a first batch early. Its contingency plan is to switch the remaining order to a second supplier when the first supplier misses the confirmed shipping date. Its fallback plan is to reduce the initial rollout and use temporary terminals if the second supplier cannot meet the revised date.
Connect triggers to authority and reserves
The risk owner monitors the trigger and coordinates the response. The owner may need approval before spending a contingency reserve, changing the schedule, or notifying customers. Record these authority limits in the risk register.
A contingency reserve is time or money set aside for identified risks. A management reserve is held for unforeseen work and usually requires higher approval. Neither reserve is permission to spend without a trigger and an approved response.
After a response begins, reassess the risk. The response may leave a residual risk, which is the risk that remains. It may also create a secondary risk, which is a new risk caused by the response. For example, switching suppliers may reduce delay risk but create an untested quality risk.
Exercise
A supplier misses its shipping date. What should a useful response record contain?
Show answer
It should name the trigger, risk owner, contingency plan, fallback plan, authority or reserve needed, and any residual or secondary risks.