Accepting a Threat: Passive and Active
This chapter assumes you know basic project management terms, including scope, schedule, budget, stakeholders, probability, and impact. You also know that a risk is an uncertain event that could affect a project objective.
What threat acceptance means
A threat is a risk with a possible negative effect. Accepting a threat means the team does not take preventive action to reduce its probability or impact. This can be a deliberate, reasonable choice. It does not mean ignoring the risk.
Acceptance fits when the risk is below the project's response threshold, when other responses cost more than the expected loss, or when no practical response exists. The project manager should compare the decision with the project's risk appetite, which is the amount and type of risk the organization is willing to tolerate.
There are two forms:
- Passive acceptance: The team records and monitors the risk but does not prepare a specific action.
- Active acceptance: The team prepares a contingency plan, trigger, owner, time, and resources for the event.
| Form | Before the event | When the event occurs |
|---|---|---|
| Passive acceptance | Monitor the risk | Decide what to do at that time |
| Active acceptance | Prepare a predefined response | Execute the contingency plan |
Passive acceptance
Use passive acceptance when the risk is low enough that routine monitoring is sufficient. For example, a team might accept a small chance that a workshop moves by one day because the schedule has enough flexibility.
The risk register should still state:
- The risk and its possible effect
- Probability, impact, and score
- The acceptance rationale
- The risk owner
- The next review date
The owner watches for changes. A rising probability, greater impact, or reduced schedule float may require a new response decision.
Active acceptance
Active acceptance is useful when the team accepts the current exposure but wants to limit disruption if the threat occurs. The contingency plan describes the action taken after a defined trigger.
For example, a project may accept the risk that a payment-terminal shipment arrives late. The team can set this trigger: “The supplier misses the first confirmed shipping date.” The contingency could be switching to a qualified second supplier. The response owner needs authority, timing, and funding to act.
A fallback plan is a second option if the contingency fails. In this example, the fallback might be renting terminals for the launch period.
Record and review the decision
Acceptance can leave residual risk, which is the risk remaining after a response. Active acceptance can also create secondary risks. Switching suppliers, for example, may create a quality risk. Record both risks and assign owners.
Use contingency reserves for known accepted threats with uncertain costs. Management reserves cover unforeseen work and normally require higher approval. Do not hide either reserve in an unexplained budget line.
Exercise
A low-score threat has no cost-effective preventive action, but a delay would require an immediate decision. Which acceptance form fits best, and what must the team define?
Show answer
Active acceptance fits best. The team should define an owner, trigger, contingency action, fallback if needed, and available reserve.