Validating the WBS with the Team
Assume you know basic project management terms, have a written scope statement, and understand outline or tree structures. Validation checks whether the work breakdown structure (WBS) represents the complete project scope in a usable way. The project team, subject-matter experts, sponsors, and key stakeholders should take part because a WBS can look complete while hiding missing or duplicated work.
What to Validate
A useful validation review tests four properties:
- Completeness: The lowest-level work packages cover all project deliverables and project management work required by the scope.
- The 100% rule: The children of a WBS element represent all of that element's scope, with no missing portion.
- Mutual exclusivity: One piece of scope appears in only one WBS element. This prevents double counting.
- Usability: Each work package is clear enough to estimate, assign, schedule, monitor, and accept.
Review the WBS against the scope statement, contract, requirements, assumptions, exclusions, and acceptance criteria. Do not validate it only against the draft schedule. A schedule may omit work that has not yet been planned.
Run a Structured Team Review
Give participants the current WBS and its dictionary entries before the meeting. Ask them to review the structure independently, then discuss findings together. A facilitator can move through the WBS from the project root to each work package.
Use questions such as:
- What deliverable or result does this branch represent?
- Which scope statement or requirement supports it?
- What required result is missing?
- Does any element overlap another element?
- Is the boundary between parent and child elements clear?
- Can an owner define acceptance for this work package?
- Can the team estimate the work without inventing additional scope?
- Are assumptions and exclusions recorded?
- Is any work package too large to track or too small to manage?
Record each issue with the WBS code, description, decision, owner, and due date. Do not silently edit the WBS during the meeting. Capture disagreements first, then approve changes through the project's agreed change process.
Trace Findings Through the Hierarchy
A traceability check connects each required deliverable or requirement to a WBS element. The following review path helps the team find gaps:
If a requirement cannot be traced to a WBS element, the WBS may be incomplete. If an element cannot be traced to approved scope, it may be unnecessary scope or an unapproved addition.
Approve and Baseline the Result
After corrections, ask the responsible leads and sponsor to approve the WBS. Store the approved version with its dictionary and review record. This approved version becomes the scope baseline for planning and control.
Later changes should identify the affected WBS codes and explain their effect on estimates, schedule, ownership, and acceptance criteria. A new version should preserve the history of the decision.
Exercise
During review, two branches both include “user training materials.” What should the team do?
Show answer
Decide which branch owns the deliverable, remove the duplicate, and document the boundary or shared dependency in the WBS dictionary.