Sub topic 7
Defining Work Packages
Assume that you know basic project terms such as deliverable, stakeholder, and milestone. You also have a project scope statement and can read a hierarchical outline. This chapter focuses on the lowest useful level of a work breakdown structure (WBS): the work package.
What a work package is
A work package is the smallest WBS element that the project team can reasonably estimate, assign, schedule, and track. It describes a piece of project scope, not a single task or action.
For example, Page templates can be a work package in a website relaunch. “Write CSS for the home page” is an activity inside that work package. The work package includes all the work needed to produce its agreed deliverable.
A good work package has:
- A clear deliverable or result
- A defined boundary
- One responsible person or team
- An estimate of effort, duration, or cost
- Acceptance criteria
- Known assumptions and exclusions
- A way to measure progress
The work package should be small enough to control but large enough to represent a meaningful result. If it contains only one trivial action, it may be too detailed. If nobody can estimate its effort or decide whether it is complete, it is too broad.
Describe the boundary
A work package needs a clear start and finish. Describe what the team will produce and what it will not produce.
For Page templates, the description might include responsive HTML and CSS for the home, article, and contact pages. It might exclude content writing and production hosting. These exclusions prevent the package from overlapping with Content or Platform elements elsewhere in the WBS.
Use acceptance criteria that someone can check. “Design is good” is difficult to test. “The product owner approves the templates, and they render correctly on the agreed browsers and screen widths” gives the team a clearer completion rule.
| Work package field | Example for Page templates |
|---|---|
| Code | 1.1.1 |
| Deliverable | Approved responsive page templates |
| Responsible | Design lead |
| Estimate | 8 person-days |
| Acceptance criteria | Product owner approval and browser checks |
| Exclusions | Content writing and hosting configuration |
Separate scope from activities
Activities explain how the team will create the result. The work package explains the result itself.
Possible activities for Page templates include:
- Confirm layout requirements
- Create draft templates
- Review the drafts
- Apply approved changes
- Run browser checks
- Obtain approval
These activities belong in the schedule. The work package belongs in the WBS. Keeping them separate makes the WBS stable even when the team changes its method.
Check whether the package is ready
Before accepting a work package, ask:
- Can the team describe its output in one or two sentences?
- Can one person or team take responsibility for it?
- Can the team estimate its effort and cost?
- Can progress be measured without guessing?
- Are its boundaries clear relative to neighboring packages?
- Can the team determine objectively when it is complete?
If the answer to several questions is no, revise the package or decompose it further. If the package is already clear but contains many unrelated outputs, split it into separate packages.
Exercise
A work package is named “Improve the website.” What should you change first?
Show answer
Replace the vague result with a specific deliverable, such as “Approved responsive page templates for the home, article, and contact pages,” and then define its owner, estimate, acceptance criteria, and exclusions.