Choosing How to Organize the First Levels of a WBS
Assume you can read a project scope statement, identify deliverables, and use a basic outline or tree structure. This chapter focuses on how to arrange the first levels of a work breakdown structure (WBS). The arrangement affects how teams estimate, assign responsibility, report progress, and control changes.
Start with the project’s main organizing question
The first level below the project usually contains major scope categories. Choose categories that make the project easier to understand and control. The most common choices are deliverables, project phases, or a hybrid of both.
Deliverable-based organization
A deliverable-based WBS groups scope by the products, services, or results the project must produce. This approach keeps attention on what the project must provide.
For example, a website relaunch might begin with:
1 Website Relaunch
1.1 Design
1.2 Content
1.3 Platform
1.4 Project managementEach major element can then be decomposed into smaller deliverables. “Design” might include page templates and a style guide. “Platform” might include the hosting environment and content management configuration.
Use this structure when:
- The scope is defined mainly by customer-facing outputs.
- Acceptance criteria differ for each product or result.
- Different teams own different deliverables.
- You need clear traceability from scope to acceptance.
Phase-based organization
A phase-based WBS groups work by stages such as discovery, design, build, test, and deployment.
1 Website Relaunch
1.1 Discovery
1.2 Design
1.3 Build
1.4 Test
1.5 DeploymentThis can work well when the project follows a clear lifecycle and each phase produces a distinct result. It is less useful when phases contain the same types of work across many products. For example, testing may cover content, design, accessibility, and platform behavior. A phase-based structure can then hide which deliverable the testing supports.
Hybrid organization
A hybrid WBS uses one organizing approach at the top and another below it. For example, major deliverables might be the first level, with lifecycle phases beneath each deliverable:
1 Website Relaunch
1.1 Customer portal
1.1.1 Design
1.1.2 Build
1.1.3 Test
1.2 Marketing site
1.2.1 Design
1.2.2 Build
1.2.3 TestA hybrid is useful when both product ownership and lifecycle control matter. However, repeated phase names can create duplicate work or unclear responsibility. Define each element precisely and check that every item belongs to one parent only.
| Approach | Best fit | Main risk |
|---|---|---|
| Deliverable-based | Output-focused projects | Cross-cutting work may need careful placement |
| Phase-based | Clear sequential lifecycles | Deliverable ownership can become hidden |
| Hybrid | Complex projects with both views | Repetition and overlap |
Apply selection criteria
Choose the structure that makes these questions easiest to answer:
- What must the project deliver?
- Who accepts each result?
- Who is responsible for it?
- How will progress be measured?
- Where will a scope change be recorded?
Do not choose a phase-based structure only because the schedule uses phases. A schedule describes when work happens. A WBS describes the total scope. The two structures may align, but they do not have to be identical.
Exercise
A software project has three independently accepted products, but all products follow the same design, build, and test lifecycle. Which first-level organization is usually the clearest, and why?
Show answer
Use a deliverable-based first level, with lifecycle phases beneath each product if needed. This keeps product ownership and acceptance visible while preserving phase control.