Sub topic 4
The 100% Rule and Mutually Exclusive Elements
Assume you have a written project scope statement and understand WBS parent-child relationships. The 100% rule and mutual exclusivity help you check whether your decomposition represents the complete project scope without counting any scope twice.
The 100% rule
The 100% rule says that the child elements of a WBS parent must represent 100% of the scope of that parent. They must include all required work and deliverables, but no work outside the parent’s scope.
The rule applies at every level:
- The project’s top-level elements cover the entire project.
- The children of each deliverable cover the entire deliverable.
- Work packages cover the complete scope of their parent element.
- A parent does not contain extra scope that is missing from its children.
For example, a website relaunch might have these top-level elements:
| WBS element | Scope covered |
|---|---|
| Design | Page templates and visual style |
| Content | Migrated pages and new landing pages |
| Platform | Hosting and content management configuration |
| Project management | Planning, reporting and project control |
If user training is required by the scope statement but appears nowhere in the WBS, the WBS violates the 100% rule. If project management is included in the project scope, it must also appear somewhere in the structure.
The rule does not mean that every activity needs to appear. A WBS describes scope through deliverables and work packages. Scheduling activities, such as “review” or “test,” may be planned later against those elements.
Mutual exclusivity
Mutually exclusive WBS elements have clear boundaries. Scope belongs to one element rather than several elements. This prevents double counting, unclear ownership and disputes about where work belongs.
Consider these two elements:
1.2.1 Migrated pages1.2.2 Website pages
The second element overlaps the first because migrated pages are also website pages. An estimate for migration could be counted under both elements.
A clearer decomposition might be:
1.2.1 Migrated pages1.2.2 New landing pages1.2.3 Approved page content
You still need to define the boundaries. For example, “approved page content” might mean editorial approval only, while migration means entering that content into the CMS.
Testing a decomposition
Review each parent with the project team:
- List the scope required by the parent.
- Ask whether every part appears in a child.
- Ask whether any child contains scope from another child.
- Check whether the child descriptions use observable boundaries.
- Confirm that the children do not add unauthorized scope.
A useful test is to assign each requirement to exactly one lowest-level WBS element. Unassigned requirements reveal gaps. Requirements assigned to multiple elements reveal overlap. Some shared work, such as a security review, may support several deliverables. Assign its scope to one appropriate work package and link the related tasks in the schedule rather than duplicating the WBS scope.
Exercise
A project has two child elements under “Training”: “User guides” and “Training materials.” What should you check first?
Show answer
Check whether the terms overlap. Define separate boundaries, such as written user guides versus presentation slides and lab exercises, or replace them with mutually exclusive deliverables.