Sub topic 16
Keeping the WBS Current Under Change Control
Assume you have an approved WBS baseline, a scope statement, and a basic change-control process. Change control is the process for reviewing, approving, rejecting, and recording changes to project scope. The WBS must change when approved scope changes, but it should not change whenever someone suggests an idea.
Treat the WBS as a controlled baseline
A WBS baseline is the agreed version used to plan, estimate, assign, and measure the project. Record its version, approval date, and approvers. Keep older versions available so the team can see what changed and when.
A change request should explain the requested scope change and its effect on the project. Review at least these questions:
- What deliverable or work package changes?
- Is the requested work inside the existing scope?
- Does the change add, remove, split, or combine WBS elements?
- How will effort, cost, schedule, quality, risks, and responsibilities change?
- Which related plans, requirements, estimates, and schedules must change?
Do not edit the approved WBS first and seek approval later. Analyze the request against the current baseline. Update the WBS only after the appropriate person or change authority approves it.
Update the WBS and its supporting records
An approved change can affect more than one WBS line. For example, adding a customer portal may require new design, security, testing, training, and deployment work. Add the complete scope rather than inserting only the visible feature.
Maintain traceability by linking the change request to the affected WBS codes. Update the WBS dictionary, estimates, schedule activities, responsibility assignments, risks, and acceptance criteria as needed. If the change removes work, mark the affected element as removed or superseded instead of silently deleting its history.
| Change type | WBS action | Related records to review |
|---|---|---|
| New deliverable | Add and decompose a new branch | Estimates, schedule, owner, risks |
| Removed deliverable | Mark the branch removed in the new version | Budget, commitments, requirements |
| Clarified scope | Revise the dictionary or acceptance criteria | Requirements, tests, estimates |
Use stable codes where practical, but do not force an old code to represent a different deliverable. A removed element can remain in the historical baseline while a replacement receives a new code.
Manage uncertainty with rolling-wave planning
Some future work cannot be decomposed in detail because its requirements are unknown. In rolling-wave planning, near-term work is planned in detail while later work remains at a higher level. The high-level element is still part of the approved scope.
As information becomes available, decompose that element into work packages. Preserve the parent code and record when the detail was added. This is refinement, not an uncontrolled scope change, when the detailed work remains within the approved parent scope.
> callout note > A more detailed WBS is not automatically a scope change. Compare the new detail with the approved parent deliverable. If it adds work outside that parent, submit a change request.
Review and publish each version
After an approved update, check the 100% rule, mutual exclusivity, estimates, ownership, and acceptance criteria again. Ask affected team members to review the revised branch. Publish the new baseline with a short revision note, such as “Added 1.5 Customer portal and updated testing and deployment estimates.”
Keep the change log beside the WBS. It should identify the request, decision, date, affected codes, approver, and resulting baseline version. This record helps the team explain why the plan changed and prevents work from being added informally.
Exercise
A stakeholder asks the team to add multilingual support to an approved website WBS. What should happen before the WBS is edited?
Show answer
Record a change request, analyze its scope and impacts, obtain approval from the change authority, then add and decompose the affected deliverable and update related records.