Sub topic 2
Think in Deliverables, Not Activities
This chapter assumes you know basic project terms such as project, stakeholder, deliverable, and milestone. It also assumes you have a written scope statement and can read a simple outline or tree structure.
The central idea
A work breakdown structure (WBS) organizes the total project scope around what the project must produce. Its elements should describe deliverables, components of deliverables, or other verifiable results.
An activity describes work someone performs. Examples include “write copy,” “configure hosting,” and “test pages.” These activities belong in a schedule or task list. They should not normally be the main organizing principle of the WBS.
Compare these two structures for a website relaunch:
| Activity-oriented structure | Deliverable-oriented structure |
|---|---|
| Design the pages | Page templates |
| Write the content | Migrated pages |
| Configure the server | Hosting environment |
| Test the website | Approved website |
The activity-oriented version describes how people will work. The deliverable-oriented version describes what the project will provide. The second version makes it easier to check whether the scope is complete.
Why deliverables are a better starting point
A deliverable is a product, service, result, or capability that the project must create. A deliverable can be physical, digital, or documentary.
Starting with deliverables helps the team:
- Compare the WBS directly with the scope statement.
- Identify missing parts of the expected result.
- Avoid mixing project work with operational work.
- Assign acceptance criteria to something observable.
- Estimate the work needed for each result.
- Prevent the same scope from appearing in multiple places.
For example, “hold a design workshop” is an activity. The workshop may produce a “approved style guide.” The style guide is the better WBS element because stakeholders can review and accept it.
Activities still matter. They are derived after the team understands the deliverables. A schedule might contain activities such as “draft style guide,” “review style guide,” and “apply revisions.” Those activities support the deliverable but do not define the project scope by themselves.
Use nouns for WBS elements
A useful test is to read each element as an answer to the question, “What will this project deliver?”
Noun phrases usually work well:
- Page templates
- Migrated pages
- Hosting environment
- Content management configuration
- Project plan and status reports
Verb phrases usually signal activities:
- Design pages
- Migrate content
- Configure hosting
- Manage the project
This is a rule of thumb, not a grammar requirement. “Launch website” may be an important result even though it contains a verb. The key question is whether the element identifies a result that can be reviewed, accepted, and traced to the scope.
Worked example: website relaunch
Suppose the scope statement requires a responsive website with approved designs, updated content, a configured platform, and project documentation. A deliverable-oriented outline could look like this:
1 Website Relaunch
1.1 Design
1.1.1 Page templates
1.1.2 Style guide
1.2 Content
1.2.1 Migrated pages
1.2.2 New landing pages
1.3 Platform
1.3.1 Hosting environment
1.3.2 Content management configuration
1.4 Project management
1.4.1 Project plan and status reportsEach lower-level item names a result. The project team can later identify the activities needed to create and approve each result.
> callout note > If an element cannot be reviewed, accepted, or traced to a required result, it may be an activity, a management action, or scope that does not belong in the WBS.
A practical review question
For every proposed element, ask:
- What result does this element represent?
- Who will accept it?
- What part of the scope requires it?
- Could the same result appear under another element?
If the answer describes only effort, such as “coordinate stakeholders,” rewrite it around the result, such as “stakeholder approval record,” when that record is genuinely part of the scope.
Exercise
You are building a WBS for a training course. Which is the better element: “Record instructional videos” or “Published instructional videos”? Why?
Show answer
“Published instructional videos” is better because it names the result that stakeholders can review and accept. Recording is an activity needed to create that result.