Sub topic 10
Showing the WBS as an Outline, Tree Chart or Table
Assume you know the basic project terms deliverable, work package, stakeholder, and milestone. This chapter focuses on how to represent the same work breakdown structure (WBS) in three useful formats. The format changes how people read the WBS, but it must not change the scope it describes.
One WBS, three views
A WBS is a hierarchy. Each child element belongs to one parent, and the children together describe the parent’s full scope. You can show that hierarchy as an outline, a tree chart, or a table.
Outline view
An outline uses indentation and hierarchical codes. It is compact and works well in documents, planning tools, and version control.
1 Website Relaunch
1.1 Design
1.1.1 Page templates
1.1.2 Style guide
1.2 Content
1.2.1 Migrated pages
1.2.2 New landing pages
1.3 Platform
1.3.1 Hosting environment
1.3.2 Content management configuration
1.4 Project management
1.4.1 Project plan and status reportsThe code shows position, not priority or sequence. Element 1.2.1 is part of Content because it begins with 1.2. It does not mean that this work starts after 1.2 or takes less effort than 1.2.2.
Tree chart
A tree chart makes parent-child relationships visible at a glance.
Tree charts are useful in workshops because the team can spot missing branches, overlapping elements, or an overly deep hierarchy quickly. They become harder to read when a project has many elements.
Table view
A table adds information that an outline or tree may not show. It is useful for assigning ownership, recording estimates, and linking each element to acceptance criteria.
| Code | WBS element | Type | Responsible role | Estimate |
|---|---|---|---|---|
| 1.1.1 | Page templates | Work package | Design lead | 8 days |
| 1.1.2 | Style guide | Work package | Design lead | 3 days |
| 1.2 | Content | Summary element | Content lead | 13 days |
A summary element groups child elements. A work package is a lowest-level WBS element that can be estimated, assigned, and tracked. Do not enter an independent estimate for a summary element if its value should be calculated from its children. Otherwise, the same effort may be counted twice.
Choosing a representation
Use an outline when the WBS is large or must be edited frequently. Use a tree chart when explaining scope to stakeholders or validating parent-child relationships. Use a table when the team needs estimates, owners, acceptance criteria, or status fields.
In practice, teams often use all three. They are views of one controlled WBS, not separate planning artifacts. If a new deliverable is added, update the source WBS and regenerate or revise the other views.
Exercise
A stakeholder says that the tree chart is easier to understand, but the project team needs estimates and owners. Which representation should you use?
Show answer
Use both views. Use the tree chart for discussion and the table for estimates and ownership, while keeping both synchronized with the same WBS codes and names.