Sub topic 13
Rolling Up Estimates from Work Packages
Assume you already know the WBS hierarchy, the 100% rule, and how to define work packages. This chapter focuses on turning work-package estimates into totals for higher WBS levels.
What a roll-up means
A roll-up is the process of calculating a parent element's estimate from the estimates of its children. Work packages at the lowest useful level usually hold the detailed estimates. Parent elements then show the combined effort or cost for their descendants.
For example, a website relaunch might contain these work packages:
| WBS code | Work package | Estimate |
|---|---|---|
| 1.1.1 | Page templates | 8 days |
| 1.1.2 | Style guide | 3 days |
| 1.2.1 | Migrated pages | 10 days |
The Design total is 11 person-days. The Content total is 10 person-days. The project total is 21 person-days, assuming these are the complete scope and no additional project-level work is included.
A roll-up must use one consistent measure. Effort is the amount of labor required, such as person-days. Cost is the money assigned to that work. Duration is the elapsed calendar time. These measures are related but are not interchangeable.
Calculate totals from the leaves
The safest approach is to estimate the work packages first and calculate each parent from its children. Do not independently estimate a parent and then add its children, because that can count the same work twice.
wbs = {
"code": "1",
"name": "Website Relaunch",
"children": [
{
"code": "1.1",
"name": "Design",
"children": [
{"code": "1.1.1", "name": "Page templates", "estimate_days": 8},
{"code": "1.1.2", "name": "Style guide", "estimate_days": 3},
],
},
{
"code": "1.2",
"name": "Content",
"children": [
{"code": "1.2.1", "name": "Migrated pages", "estimate_days": 10},
],
},
],
}
def rollup(node):
children = node.get("children", [])
if not children:
return node["estimate_days"]
return sum(rollup(child) for child in children)
print(rollup(wbs)) # 21The function treats a leaf as a work package and returns its estimate. For a parent, it recursively adds the totals of all child elements.
Avoid common roll-up errors
A parent total should include all work within its scope, including approved supporting work packages such as testing, training, or project management. Check that each work package appears under exactly one parent.
Do not add durations as if they were effort when tasks can run in parallel. Two work packages requiring five person-days each might need ten person-days of effort but only five calendar days if two people perform them simultaneously. Scheduling tools calculate elapsed duration from dependencies, calendars, and resource assignments.
Keep assumptions visible. If an estimate excludes external review or includes a contingency reserve, record that information in the WBS dictionary or estimate record. When a work package changes, recalculate every affected parent and compare the new total with the approved baseline.
>callout warning > A parent estimate is a derived value. If it does not equal the sum of its complete child scope, investigate the missing, duplicated, or incorrectly placed work before using the total for budgeting.
Exercise
Three work packages require 4, 6, and 8 person-days. They can run in parallel with suitable staff. What are the total effort and the minimum elapsed duration?
Show answer
The total effort is 18 person-days. The minimum elapsed duration is 8 calendar days, set by the longest work package, assuming no dependencies, resource limits, or nonworking days.