Sub topic 1
Start from the Project Scope
Prerequisites
Assume you know basic project management terms such as project, deliverable, stakeholder, and milestone. You also need a written scope statement, or an equivalent description of what the project must deliver.
A work breakdown structure (WBS) is a hierarchy that organizes the total project scope into deliverables and smaller work packages. The WBS starts with the project outcome. It does not start with a task list, calendar, or team structure.
Read the scope statement for outcomes
Begin by identifying the project’s required outputs. Look for nouns that describe products, services, results, or capabilities. These become candidates for the first level below the project.
For example, suppose the scope statement says:
> The project will relaunch the company website with approved page designs, migrated content, a configured hosting platform, and project management reporting.
The main deliverables are:
- Approved page designs
- Migrated and new content
- Configured hosting platform
- Project management reporting
These deliverables are better starting points than activities such as “design pages,” “write content,” or “configure servers.” Activities describe how people work. A WBS describes what the project must produce.
Separate included and excluded scope
Scope statements usually contain both commitments and boundaries. Record both before building the WBS.
| Scope statement item | WBS treatment |
|---|---|
| Responsive page templates | Include under Design |
| Migrated website content | Include under Content |
| Search engine optimization after launch | Exclude unless explicitly approved |
| Hosting environment | Include under Platform |
An exclusion does not become a WBS element. It becomes a boundary that helps the team avoid adding unauthorized work.
Derive the first level
Use this sequence:
- State the project as the root element.
- List the major deliverables required for project acceptance.
- Check that each deliverable belongs inside the approved scope.
- Remove activities, departments, and vague categories.
- Confirm that the elements together represent the complete intended outcome.
A simple outline might look like this:
1 Website Relaunch
1.1 Design
1.2 Content
1.3 Platform
1.4 Project managementThe first level does not need to contain every detail. It establishes the structure that later levels will refine. For example, Design can later contain page templates and a style guide.
Trace scope into the WBS
Each WBS element should trace back to a sentence, requirement, or acceptance condition in the scope statement. This traceability makes omissions easier to find and prevents scope from expanding silently.
Use a traceability table when the scope is complex:
| Scope requirement | Candidate WBS element | Evidence of completion |
|---|---|---|
| Pages work on agreed screen sizes | Design | Approved responsive templates |
| Existing articles remain available | Content | Migrated pages reviewed |
| Editors can publish content | Platform | Configured system accepted |
The next step is to test whether each branch fully covers its parent without overlapping other branches. That check provides the foundation for decomposition.
Exercise
Why should “configure the hosting environment” normally appear below a deliverable such as “Platform” rather than as a top-level WBS element?
Show answer
It describes an activity or lower-level result. “Platform” identifies the major deliverable, while the hosting configuration can be decomposed beneath it.