How a WBS Is Structured: Levels and Parent-Child Relationships
Assume you know basic project management terms such as project, deliverable, stakeholder, and milestone. You should also have a project scope statement and be comfortable reading an outline or tree structure.
A work breakdown structure (WBS) is a hierarchy of the total project scope. It organizes what the project must deliver from broad outcomes to smaller, manageable pieces. Each item in the hierarchy is a WBS element. A higher-level element is a parent. The elements directly below it are its children.
Levels and parent-child relationships
The top level usually represents the whole project. The next level divides the project into major deliverables or scope areas. Lower levels divide those deliverables into smaller deliverables. The lowest planned level contains work packages, which are small enough to estimate, assign, and track.
For example:
1 Website Relaunch
1.1 Design
1.1.1 Page templates
1.1.2 Style guide
1.2 Content
1.2.1 Migrated pages
1.2.2 New landing pages
1.3 Platform
1.3.1 Hosting environment
1.3.2 Content management configuration
1.4 Project management
1.4.1 Project plan and status reportsIn this outline:
1 Website Relaunchis the project-level parent.1.1 Designis a child of the project and a parent of two design deliverables.1.1.1 Page templatesis a leaf element in this example.1.1.1belongs to1.1because its code extends the parent code.- The children of
1.1together describe the scope ofDesign.
A WBS does not require every branch to have the same number of levels. One deliverable may need three levels of decomposition while another can be managed as one work package. The correct structure depends on the complexity, risk, uncertainty, and management needs of each deliverable.
A parent is a summary of its children. If the children omit part of the parent's scope, the WBS is incomplete. If two children describe the same scope, estimates and ownership can overlap.
How to read the hierarchy
When reviewing a WBS, ask these questions at every branch:
- What complete scope does the parent represent?
- Do its children account for all of that scope?
- Does each child belong only to this parent?
- Are the children at a similar level of detail?
- Can the lowest elements be estimated and assigned?
The parent-child relationship should also support reporting. For example, a status report can show progress for 1.1 Design by summarizing the status of 1.1.1 Page templates and 1.1.2 Style guide.
| Element | Role | Relationship |
|---|---|---|
| 1 Website Relaunch | Project root | Parent of all major scope areas |
| 1.1 Design | Summary deliverable | Child of 1; parent of design work packages |
| 1.1.1 Page templates | Work package | Child of 1.1; leaf element |
Exercise
A parent element called “Mobile app” has children “iOS app” and “Android app.” Is this structure valid if the project also includes a shared backend?
Show answer
Not yet. The children omit the shared backend, so the parent’s scope is incomplete. Add a child such as “Backend services,” or decompose the scope using another mutually complete structure.