Sub topic 5
Decomposing Scope Level by Level
Assume you already know basic project terms, can read a scope statement, and understand that a work breakdown structure (WBS) is a hierarchy of project scope. This chapter focuses on turning broad deliverables into smaller, clearer elements.
Decomposition is the process of dividing project scope into progressively smaller parts. You start with the total project outcome and add detail one level at a time. Each lower level explains the content of its parent.
Start with the project outcome
Read the scope statement and identify what the project must deliver. Do not begin by listing activities such as “hold meetings” or “write code.” Begin with results that a stakeholder can review or accept.
For a website relaunch, the top level might be:
- Website relaunch
The next level could divide that result into major deliverables:
- Design
- Content
- Platform
- Project management
These elements describe the complete project scope. They do not describe a schedule or a task list.
Decompose one branch at a time
Select one major deliverable and ask:
> What smaller deliverables together make up this deliverable?
For example, the Design branch might contain:
- Page templates
- Style guide
Then ask the same question about Page templates:
- Home page template
- Article page template
- Contact page template
Continue until the elements are specific enough to estimate, assign, and track. The lowest planned elements are called work packages. A work package is a manageable unit of scope with a clear result.
The following diagram shows the direction of decomposition:
Check each level as you work
At every parent, check that its children cover the parent completely. This is the 100% rule: the child elements must represent all of the parent’s scope, including project management work when that work is part of the project.
Also check that children do not overlap. If both Content and Design include “page copy,” ownership is unclear and the same scope may be counted twice. Move the scope to one appropriate branch or clarify the boundary.
Use these questions during decomposition:
- What result does this parent promise?
- Which smaller results make up that promise?
- Is every part of the parent represented?
- Does any child belong under another parent?
- Can the team estimate and assign the lowest-level elements?
Know when to stop
Stop decomposing when another split would add detail without improving control. A work package should have:
- A clear scope boundary
- A measurable acceptance result
- One responsible owner or team
- A practical estimate
- A way to track progress
The correct size depends on the project. A small work package might take several days; a complex project may need smaller units. Do not force every branch to have the same number of levels. Decompose uncertain areas further when needed, while leaving well-understood areas at a higher level.
Exercise
A project has a “Customer training” deliverable. Which decomposition is more suitable: “schedule training, prepare slides, deliver sessions” or “training materials, approved training environment, completed training sessions”? Why?
Show answer
“Training materials, approved training environment, completed training sessions” is more suitable because each child is a deliverable that can be reviewed and accepted. The other list contains activities.