Sub topic 12
Validating the WBS with the team
This chapter assumes you have a draft WBS with hierarchical codes and work packages. It also assumes you know the 100% rule and mutual exclusivity. A draft is only a proposal. Validation checks whether the structure is complete, unambiguous and usable by the people who will do the work.
Why validate
The person who drafts a WBS usually knows the project's goals better than its details. Gaps and overlaps survive a solo review because the author reads what they meant to write. Other people read what is on the page.
Validation answers four questions:
- Completeness: Does the lowest level add up to all the scope, and nothing more?
- Clarity: Can each owner say what their element includes and excludes?
- Estimability: Can each work package be estimated, assigned and tracked?
- Agreement: Do the people who will do the work accept the structure?
A good approach combines mechanical checks, which a script can do, with judgment checks, which need people.
Step 1: Run structural checks
Some defects are mechanical, so find them before anyone's time is spent on a meeting. Typical checks:
- Every code is unique.
- Every code sits directly under its parent's code.
- Only leaf elements carry estimates.
- Every leaf has an estimate.
- Every element has a dictionary entry.
- A parent with exactly one child is flagged, because a single child usually means the parent and child are the same thing, or a sibling is missing.
The script below extends the roll-up code from the earlier chapters. It collects every problem instead of stopping at the first.
def validate(node, parent=None, seen=None, problems=None):
seen = set() if seen is None else seen
problems = [] if problems is None else problems
code = node["code"]
if code in seen:
problems.append(f"{code}: duplicate code")
seen.add(code)
if parent is not None and code.rsplit(".", 1)[0] != parent:
problems.append(
f"{code}: parent code is {code.rsplit('.', 1)[0]}, expected {parent}"
)
children = node.get("children", [])
if children:
if "estimate_days" in node:
problems.append(f"{code}: parent carries its own estimate")
if len(children) == 1:
problems.append(f"{code}: only one child, so the split adds nothing")
for child in children:
validate(child, code, seen, problems)
elif "estimate_days" not in node:
problems.append(f"{code}: work package has no estimate")
return problems
wbs = {
"code": "1", "name": "Website Relaunch",
"children": [
{"code": "1.1", "name": "Design", "children": [
{"code": "1.1.1", "name": "Page templates", "estimate_days": 8},
{"code": "1.1.2", "name": "Style guide"},
]},
{"code": "1.2", "name": "Content", "estimate_days": 5, "children": [
{"code": "1.2.1", "name": "Migrated pages", "estimate_days": 10},
]},
{"code": "1.3.1", "name": "Hosting environment", "estimate_days": 4},
],
}
for problem in validate(wbs):
print(problem)Running it prints:
1.1.2: work package has no estimate
1.2: parent carries its own estimate
1.2: only one child, so the split adds nothing
1.3.1: parent code is 1.3, expected 1The last message points to a missing element. Code 1.3 ("Platform") was never created, so its child was attached to the root.
Step 2: Trace to the scope statement
Completeness is checked in two directions.
- Downward (scope to WBS): Take each deliverable, requirement and acceptance condition in the scope statement and find the WBS element that produces it. An item with no element is a gap.
- Upward (WBS to scope): Take each work package and name the scope item that justifies it. A package with no justification is gold plating, or scope that was never agreed.
A simple traceability table works well:
| Scope statement item | WBS element | Result |
|---|---|---|
| Responsive templates for three page types | 1.1.1 Page templates | Covered |
| Migrate existing articles | 1.2.1 Migrated pages | Covered |
| Redirect old URLs | none | Gap |
| Social media integration | 1.2.3 Social feeds | Not in scope statement |
Both kinds of mismatch need a decision. Either change the WBS, or change the scope through the project's agreed process. Do not quietly fix the mismatch on the WBS side alone.
Also check the project management work. Planning, reporting, testing, training and handover are deliverable-producing work, and drafts often leave them out.
Step 3: Review with the people who own the work
Hold the review with the people who will estimate or perform the work, not only the sponsor. Walk through the WBS one branch at a time, with that branch's owner present. Ask each owner:
- What does this element produce? Is the name enough to tell?
- What would you add, remove or split?
- Is there work you would do that has no element? Where would you charge your time?
- Is the package small enough to estimate? Could you tell when it is done?
- Does any other element sound like it includes the same work?
The last two questions are the most useful. Overlap shows up when two owners each assume the other covers an item, or when both think they own it. Missing boundaries show up as long silences when you ask "Where does this work go?"
Concrete tests for a work package:
- The owner can name the finished output.
- The owner can give an estimate in days or cost without needing to know a lot more first.
- One person or team is accountable for it.
- Progress can be reported as done or not done, or with a simple measure.
Step 4: Read the dictionary for overlap
Read the dictionary entries side by side, not only the names. Two elements can have different names and describe the same work. Look for:
- Descriptions that share verbs and nouns, such as "configure the CMS" under two parents.
- Empty
excludedfields where a neighbour clearly exists. - Assumptions that depend on another element, such as 1.1.1 assuming the style guide in 1.1.2 is approved. These are dependencies the schedule must pick up.
- Acceptance criteria no one could test.
If an entry cannot be written without referring to a neighbour, the boundary between them is probably unclear.
Common validation failures
- Review by email only. People skim, and silence is read as agreement. Walk through the structure with the owners in a live session.
- Reviewing only the top levels. Overlaps usually hide at levels 3 and 4.
- Validating once. Revisions made after the review can break the checks. Re-run the script after every edit.
- No record of the decisions. Write down what changed and who accepted the revised structure. The record is the basis for the baseline.
- Mistaking agreement for correctness. If every owner approves but the traceability table shows gaps, the WBS is still incomplete.
Approving the baseline
When the checks pass and owners accept their branches, the sponsor or the project's approval authority signs off the WBS and dictionary together. They become the scope baseline. From that point, changes go through change control, covered in a later chapter.
Exercise
A WBS passes the script above with no problems. The traceability check finds a scope statement item, "train the support staff", that appears in no element. What does this tell you, and what should you do next?
Show answer
The script only checks structure, so it cannot detect missing scope. The training deliverable is a gap in the WBS, a breach of the 100% rule. Add an element for it, for example under project management or a new training branch. Then give it a dictionary entry, estimate it, assign an owner, re-run the structural checks and have the owners re-review the changed branch. If the stakeholders decide training is out of scope, record that decision in the scope statement instead.
Exercise
During review, two owners both describe their work as "configuring the content management system", one under 1.2 Content and one under 1.3 Platform. Which validation step catches this, and how do you resolve it?
Show answer
Reading the dictionary entries side by side (Step 4), or asking the owners what they would do and where it goes (Step 3), catches the overlap. Resolve it by splitting the work along a clear boundary, for example platform setup and user roles under 1.3, and content types and templates under 1.2. Then write that boundary in the excluded field of each entry, so that every piece of work belongs to exactly one element.