Sub topic 5
Decomposing scope level by level
This chapter assumes you can read a scope statement and know that a WBS is a hierarchy of deliverables. You should also know the 100% rule, which says the children of an element must account for all of its scope and nothing outside it. Here you will turn a scope statement into a tree one level at a time, and learn what to check at each step.
Decomposition is a repeated procedure
Decomposition means splitting an element into smaller elements that together make up the whole. It is the same operation at every level:
- Take one element and restate its scope in a sentence.
- Ask what parts that deliverable consists of. Do not ask what steps it needs.
- Write the parts as noun phrases.
- Check that the parts add up to the parent and do not overlap.
- Repeat for each part until the stopping rules from the next chapter say to halt.
Work breadth-first. Finish level 2 for the whole project before you break anything into level 3. If you go deep on one branch first, you tend to give it more detail than the others and to leave gaps elsewhere. Those gaps are hard to see until late.
Deriving level 2 from the scope statement
Level 1 is the project itself. Level 2 is the most consequential split, because every later level inherits its logic. Derive it from the scope statement's deliverables list, not from a template.
Take this scope statement: "Relaunch the company website: new visual design, migration of existing pages, three new landing pages, a new hosting setup, and project reporting." Group the named deliverables by what they are:
| Scope statement phrase | Level 2 element |
|---|---|
| new visual design | 1.1 Design |
| migration of pages, three new landing pages | 1.2 Content |
| new hosting setup | 1.3 Platform |
| project reporting | 1.4 Project management |
Every phrase in the scope statement lands in exactly one element, and no element exists without a phrase behind it. That two-way trace is the practical form of the 100% rule at this level. If a phrase fits nowhere, you are missing an element. If an element has no phrase, either you invented scope or the scope statement is incomplete. Resolve that question with the sponsor and do not settle it silently.
Include project management as its own element. Planning, reporting and coordination are real, estimable scope, and leaving them out understates the total.
What to check at every level
Apply four checks to each set of siblings.
- Noun, not verb. Name elements by what exists when they are done: "Page templates", not "Designing pages". Verbs describe activities, which belong in the schedule later.
- Two or more children. A parent with exactly one child adds no information. Either the child is the same scope under a new name, or a sibling is missing.
- Similar grain. Siblings need not be equal in size, but a 2-day element beside a 60-day element often means the big one needs more splitting, or the small one is really a detail of something else.
- One logic per split. All the children of a parent should be divided by the same criterion, such as component, deliverable type or location. Mixing criteria is how overlaps start.
The last check is the most common source of trouble. Consider splitting "Content" into "Migrated pages", "New landing pages" and "Legal copy". The first two split by origin. The third splits by subject, and legal copy can appear on migrated pages and on new ones. Anyone estimating "Migrated pages" will not know whether the legal text is theirs. Fix it by keeping the origin criterion and recording legal review as an acceptance criterion on both elements.
Checking a decomposition with a script
Some of these checks are mechanical, so a short script can catch them. The script below flags single-child parents and names whose first word ends in "-ing", which suggests an activity. It is a heuristic, so it will produce false positives.
wbs = {
"code": "1", "name": "Website Relaunch",
"children": [
{"code": "1.1", "name": "Design", "children": [
{"code": "1.1.1", "name": "Page templates"},
{"code": "1.1.2", "name": "Style guide"},
]},
{"code": "1.2", "name": "Content", "children": [
{"code": "1.2.1", "name": "Migrated pages"},
]},
{"code": "1.3", "name": "Testing", "children": [
{"code": "1.3.1", "name": "Browser test report"},
{"code": "1.3.2", "name": "Accessibility audit report"},
]},
{"code": "1.4", "name": "Hosting environment"},
],
}
def check(node, problems=None):
if problems is None:
problems = []
children = node.get("children", [])
if len(children) == 1:
problems.append(
f"{node['code']}: single child '{children[0]['name']}'; "
"merge it up or add the missing sibling"
)
if node["name"].split()[0].lower().endswith("ing"):
problems.append(f"{node['code']}: '{node['name']}' reads like an activity")
for child in children:
check(child, problems)
return problems
for problem in check(wbs):
print(problem)Running it prints three lines:
1.2: single child 'Migrated pages'; merge it up or add the missing sibling
1.3: 'Testing' reads like an activity
1.4: 'Hosting environment' reads like an activityThe first two findings are real. "Content" is missing its landing-page sibling, and "Testing" should become something like "Test results". The third is a false positive, because "Hosting environment" is a thing, not an action. The script cannot judge that, so a person decides. Treat tools like this as prompts for review, never as approval.
Decomposing by a consistent rule
Choose the splitting criterion deliberately at each level. Common ones for deliverable-oriented work are:
- Component. A product divides into subsystems, such as the app, the API and the database.
- Deliverable type. A body of work divides into kinds of output, such as documents, software and training material.
- Audience or location. A rollout divides by site or user group when each needs its own deliverable.
Different branches may use different criteria. "Platform" might split by component and "Content" by origin. The rule is that siblings share one criterion, not that the whole tree does.
Edge cases
- Shared deliverables. A deliverable needed by two branches, such as a style guide used by design and content, must live in exactly one place. Record the dependency in the other element's assumptions and do not duplicate it.
- Work with no product. Training, meetings and handover do not yield a physical thing. Name them by their output: "Training sessions delivered" or "Handover pack".
- Unknown detail. If you cannot say what the parts of an element are yet, stop and mark it for later decomposition. Do not invent detail to fill the tree. Rolling wave planning covers this case in a later chapter.
- Depth varies. A WBS does not need uniform depth. One branch may stop at level 3 and another continue to level 5.
Exercise
A scope statement says: "Deliver a customer mobile app for iOS and Android, a back-end API, user documentation, and a launch event." A colleague proposes level 2 as: 1.1 Build the app, 1.2 Test, 1.3 Documentation, 1.4 Launch event. Name two problems and give a better level 2.
Show answer
Problems: "Build the app" and "Test" are activities, and "Test" is a phase that overlaps with building (the app and the API both need testing), so the split mixes criteria. The back-end API from the scope statement appears nowhere, which breaks the 100% rule. A better level 2 is 1.1 Mobile app (iOS and Android, with test results as children later), 1.2 Back-end API, 1.3 User documentation, 1.4 Launch event, plus 1.5 Project management. Each scope phrase maps to exactly one element.