Sub topic 6
Knowing when to stop decomposing
This chapter assumes you can already split a scope statement into deliverables, check a decomposition against the 100% rule, and read a hierarchical outline with codes such as 1.2.1. Here you learn where each branch of the WBS should end.
Why the stopping point matters
Decomposition is the repeated splitting of a WBS element into smaller child elements. Each split adds detail, and each split also adds cost. Every extra element has to be named, numbered, described, estimated, assigned and tracked.
You can stop at the wrong level in two directions:
- Too coarse. A leaf such as "Build the platform" cannot be estimated with confidence. It has no single owner, and nobody can say whether it is 30% or 60% done. Hidden work sits inside it, which is how the 100% rule gets broken in practice.
- Too fine. A leaf such as "Email the vendor about the hosting quote" turns the WBS into a task list. Maintaining it takes more effort than the work itself. Small leaves also pull the WBS toward activities, which are the verbs of the schedule and not deliverables.
The leaves of a WBS are called work packages. The goal is to stop at the level where a work package is small enough to manage and large enough to be worth managing.
The tests for a good leaf
No single rule works for every project. Experienced planners combine several tests and treat any failure as a signal to look again.
- Estimable. The team can give a duration and cost with reasonable confidence. If the estimate is a wide guess, the element still hides unknowns.
- Assignable. One person or one team can be held responsible. If two groups each own half, split the element along that line.
- Trackable. You can tell when it is finished, using acceptance criteria that belong to the element and not to its parent.
- Bounded in time. Many organizations use the 8/80 rule: a work package should take no fewer than 8 and no more than 80 hours of effort. Others use the reporting period rule: no package should be longer than one status-reporting cycle, so progress is never a vague "in progress" for weeks.
- Worth its overhead. The effort to plan and track the element should be small compared with the effort to do it.
The numbers are heuristics, not standards. A construction project may accept packages of several weeks. A two-week software sprint project may use packages of a day or two. Choose thresholds once, write them down in the project's planning documents, and apply them consistently.
| Symptom | Likely cause | Action |
|---|---|---|
| Estimate range is very wide | Unknowns inside the element | Decompose, or run a small discovery task first |
| Two owners claim parts of it | More than one deliverable | Split by owner |
| Status stays "in progress" for many reporting periods | Package too large | Decompose or add interim deliverables |
| Leaf names start with verbs like "call" or "email" | Drifted into activities | Merge up to the deliverable |
| Leaves take under an hour each | Over-decomposed | Merge siblings into one package |
| Planned effort is mostly tracking overhead | Over-decomposed | Raise the minimum package size |
Decision flow
The flow below summarizes how to test one element. Apply it to every leaf, starting at the bottom of each branch.
Automating the size check
On a large WBS, checking every leaf by hand is slow. The script below walks a WBS held as nested dictionaries, like the one in the earlier roll-up example, and reports leaves that are outside the size limits or have no estimate. The thresholds are in days and are set to match a 10-working-day reporting window.
MAX_DAYS = 10
MIN_DAYS = 1
wbs = {
"code": "1", "name": "Website Relaunch",
"children": [
{"code": "1.1", "name": "Design", "children": [
{"code": "1.1.1", "name": "Page templates", "estimate_days": 8},
{"code": "1.1.2", "name": "Style guide", "estimate_days": 3},
]},
{"code": "1.3", "name": "Platform", "children": [
{"code": "1.3.1", "name": "Hosting environment", "estimate_days": 6},
{"code": "1.3.2", "name": "Content management configuration",
"estimate_days": 25},
]},
{"code": "1.4", "name": "Project management", "children": [
{"code": "1.4.1", "name": "Project plan and status reports",
"estimate_days": 0.5},
{"code": "1.4.2", "name": "Launch communications"},
]},
],
}
def leaves(node):
children = node.get("children")
if not children:
yield node
else:
for child in children:
yield from leaves(child)
def check_leaf(leaf):
days = leaf.get("estimate_days")
label = f"{leaf['code']} {leaf['name']}"
if days is None:
return f"{label}: no estimate; decompose or plan it as a later wave"
if days > MAX_DAYS:
return f"{label}: {days} days is above {MAX_DAYS}; consider decomposing"
if days < MIN_DAYS:
return f"{label}: {days} days is below {MIN_DAYS}; consider merging"
return None
for leaf in leaves(wbs):
message = check_leaf(leaf)
if message:
print(message)Running it prints three findings:
1.3.2 Content management configuration: 25 days is above 10; consider decomposing
1.4.1 Project plan and status reports: 0.5 days is below 1; consider merging
1.4.2 Launch communications: no estimate; decompose or plan it as a later waveThe script cannot judge whether an element is a real deliverable or has one owner. It only catches size problems, so a person still has to review the result.
Worked example: splitting an oversized leaf
Element 1.3.2 "Content management configuration" is 25 days, well over the limit. Asking "what are the separable deliverables inside it?" gives:
1.3.2 Content management configuration
1.3.2.1 Content types and fields
1.3.2.2 User roles and permissions
1.3.2.3 Editorial workflowEach child must pass the same tests. If "Content types and fields" is 9 days with one owner and clear acceptance criteria, it stops there. If "Editorial workflow" is still 12 days and depends on a decision the business has not made, it needs another look. Either split it further, or mark it for later detail (see the section on uncertain work below).
Note that the children are deliverables, not steps such as "interview editors" or "test workflow". Those are activities. They belong in the schedule under the work package, not in the WBS.
Different branches stop at different depths
A WBS does not have to be balanced. Well-understood branches can stop early, and risky or unfamiliar branches may need more levels. A "Hosting environment" package using a standard cloud template may be one leaf at level 3. An integration with a legacy system may need four levels before every leaf is estimable. Do not decompose a stable branch just to make the tree look even.
Uncertain work and rolling wave
Sometimes you cannot reach a good leaf because the information does not yet exist. The standard response is rolling wave planning, covered in a later chapter. You decompose the near-term work fully and leave far-term elements at a higher level, as planning packages. These are placeholders with a budget but no detailed breakdown. Record the planned date by which you will break each one down, so it is not left at a high level indefinitely.
Common errors
- Using one hour threshold for every project type and never revisiting it.
- Stopping when the diagram "looks complete" instead of testing each leaf.
- Splitting by time ("first half", "second half") instead of by deliverable.
- Creating leaves that share an owner and a deliverable, which breaks mutual exclusivity.
- Decomposing to task level in the WBS and then duplicating the same tasks in the schedule.
Exercise
A WBS leaf named "Set up payment system" has an estimate of 45 days, and both the finance team and the web team say they own part of it. Using the stopping tests, state what is wrong and how you would fix it.
Show answer
The leaf fails the size test (45 days is far above a typical limit such as 10 days or 80 hours) and the assignable test (two owners). Decompose it along the ownership line into separate deliverables, for example "Payment gateway integration" (web team) and "Merchant account and reconciliation process" (finance team). Then check each child against the estimable, assignable, trackable and size tests, and decompose again only if one still fails.
Exercise
A WBS has 60 leaves, many of them under four hours, with names such as "Send kickoff email" and "Book meeting room". What is the problem, and what would you do?
Show answer
The WBS has been decomposed to the activity level. The leaves are tasks, not deliverables, and the tracking overhead outweighs the work. Merge these leaves into a parent deliverable such as "Kickoff meeting held" with a package size above the project's minimum, and move the individual tasks into the schedule under that work package.