Sub topic 14
Control accounts and responsibility assignment
This chapter assumes you can already decompose scope into work packages, number WBS elements, and roll up estimates from work packages to parents. It covers how to group work packages into units that can be managed and tracked, and how to record who answers for each one.
Why a WBS needs a management layer
A WBS with 80 work packages is complete, but nobody can track 80 separate cost lines in a status meeting. Work packages are sized for estimating and day-to-day assignment. Reporting needs a coarser unit. That unit is the control account.
A control account is a management point on the WBS where scope, budget, actual cost and schedule are brought together and compared. It sits at a chosen level of the WBS and contains one or more work packages. Each control account has one named person accountable for it, usually called the control account manager.
Two rules keep control accounts consistent with the rest of the WBS:
- Every work package belongs to exactly one control account. This extends the mutual exclusivity rule: if a package were in two accounts, its cost would be counted twice.
- A control account never cuts across the hierarchy. It is a whole subtree, such as everything under 1.1, not a hand-picked mix of packages from different branches.
A control account is not a new level of decomposition. It is a label placed on an existing element, so you can add or move it without changing the scope the WBS describes.
Choosing the level for control accounts
Control accounts usually sit one or two levels above the work packages. You are balancing two things:
- Too low (one account per work package) gives you the same volume of reporting you were trying to avoid.
- Too high (one account for the whole project) hides problems until they are large.
Use these criteria to pick the level:
- One person can realistically oversee all the work in the account.
- The work in the account is done mostly by one team or one discipline.
- The account is big enough to report on meaningfully, but small enough that a variance points to a specific cause.
- The account matches how the budget is held, for example one department's cost center.
In the website relaunch example, the elements 1.1 Design, 1.2 Content, 1.3 Platform and 1.4 Project management are natural control accounts. Each has a single lead and a coherent body of work.
Checking control accounts in code
The rollup function from the earlier chapter sums estimates up the tree. A control account adds one more check: each work package must map to exactly one account, and the account's total is the sum of its packages. The script below enforces both rules and prices each account.
accounts = {
"CA-1.1": {"wbs": "1.1", "manager": "Design lead", "day_rate": 600},
"CA-1.2": {"wbs": "1.2", "manager": "Content lead", "day_rate": 450},
}
work_packages = [
("1.1.1", "Page templates", 8),
("1.1.2", "Style guide", 3),
("1.2.1", "Migrated pages", 10),
("1.2.2", "New landing pages", 5),
]
def account_for(code):
matches = [
name
for name, account in accounts.items()
if code.startswith(account["wbs"] + ".")
]
if len(matches) != 1:
raise ValueError(f"{code} belongs to {len(matches)} control accounts")
return matches[0]
days_by_account = {}
for code, name, days in work_packages:
account = account_for(code)
days_by_account[account] = days_by_account.get(account, 0) + days
for account, days in days_by_account.items():
info = accounts[account]
budget = days * info["day_rate"]
print(f"{account} {info['manager']}: {days} days, budget {budget:,}")Running it prints:
CA-1.1 Design lead: 11 days, budget 6,600
CA-1.2 Content lead: 15 days, budget 6,750If you add a package such as ("1.3.1", "Hosting environment", 4) without defining a CA-1.3 account, account_for raises an error. That is the intended behavior. An orphaned package is budget that nobody is watching.
Assigning responsibility
A control account names a single accountable person. Most work packages also involve other people, and a responsibility assignment matrix (RAM) records who does what for each element. The matrix has WBS elements as rows and people or roles as columns. Each cell holds a code for that person's involvement.
The most common coding is RACI:
| Code | Meaning | What it implies |
|---|---|---|
| R | Responsible | Does the work |
| A | Accountable | Owns the result and signs it off. Exactly one per row |
| C | Consulted | Gives input before the work is done |
| I | Informed | Is told the outcome |
Here is a RAM for part of the relaunch WBS:
| WBS element | Design lead | Content lead | Platform engineer | Product owner |
|---|---|---|---|---|
| 1.1.1 Page templates | A/R | C | C | I |
| 1.1.2 Style guide | A/R | I | I | C |
| 1.2.1 Migrated pages | C | A/R | C | I |
| 1.2.2 New landing pages | C | A/R | I | C |
| 1.3.1 Hosting environment | I | I | A/R | I |
Note how this maps to the WBS dictionary. The responsible field in a dictionary entry names the A in the matrix. The matrix adds the other roles around that name.
Rules for a usable matrix
- One A per row. Two accountable people means nobody is accountable. If you cannot choose, the work package is probably too broad and should be split.
- At least one R per row. An element with only A and no R has no one doing the work.
- Keep R and A together on small packages. A/R is fine when one person owns and performs the work.
- Limit C and I. If every cell in a row is filled, the matrix no longer says who matters.
- Assign roles first, then names. A role such as "Design lead" survives staff changes, and the person filling it can be recorded elsewhere.
Common errors
- Accounts that cross branches. An account made of 1.1.2 and 1.2.1 is a cost grouping, not a WBS subtree. Report it as a view if you need it, but do not use it as the account.
- Account manager equals project manager for everything. This turns the project manager into the only owner and removes the point of delegating. Reserve this for 1.4 Project management.
- Matrix drift. People change roles and packages are split, but the matrix is not updated. Review it whenever the WBS changes through change control.
- Responsibility assigned to a team name. A team cannot be held accountable. Name a role or person in the A column and list the team as R.
Exercises
Exercise
A project has control accounts at level 2. The Content lead wants to move work package 1.2.2 into the Design account because the designers will write the landing page copy. What must you check before agreeing, and what changes?
Show answer
Check whether the work is a different scope or just a different performer. If the work is still the "new landing pages" deliverable, it stays under 1.2 in the WBS, and only the RAM changes: the Design lead becomes R and the Content lead stays A, or accountability is formally reassigned. If the deliverable itself moves, that is a WBS change that goes through change control, and the code becomes 1.1.x so each work package still belongs to exactly one control account. Budgets of both accounts must be adjusted, and the rolled-up total must stay the same.
Exercise
A RAM row for work package 1.3.1 shows A for the Platform engineer and A for the Product owner. What is wrong, and what are two ways to fix it?
Show answer
Two accountable people mean accountability is unclear. Fix it by choosing one A (usually the Platform engineer, with the Product owner changed to C or I for sign-off input), or by splitting 1.3.1 into two work packages if it really contains two deliverables with different owners, each with its own single A.