Sub topic 15
Rolling Wave Planning for Uncertain Work
This chapter assumes you can already decompose scope into deliverables and work packages, number the elements, and read a WBS dictionary entry. It builds on the decomposition and stopping rules from earlier chapters.
The problem: you cannot decompose what you do not know yet
Normal decomposition goes until every leaf is a work package you can estimate, assign and track. That works when the work is understood. Some work is not understood yet. Examples:
- A migration of 400 legacy pages, where nobody has audited how many are reusable.
- A vendor integration whose API is still being negotiated.
- A late-phase deliverable that depends on a decision made in month three.
If you force a detailed breakdown now, you invent work packages and estimates that are guesses. Those guesses end up in the baseline and later look like variances. If you leave the area undefined, you break the 100% rule, because part of the scope has no element.
Rolling wave planning solves this by planning in waves. Work in the near future is decomposed in detail. Work further out stays at a higher level, but it stays in the WBS. As the project advances, you decompose the next wave.
Planning packages
A planning package is a WBS element whose work content is known, but whose detailed work packages are not yet defined. It sits where a work package would normally sit, below a control account (the level where scope, cost and schedule are tracked together). Later it is replaced by child work packages.
| Property | Work package | Planning package |
|---|---|---|
| Scope and deliverable | Defined | Defined at a coarse level |
| Estimate | Single, bottom-up | Range or top-down figure |
| Activities | Listed in the schedule | Not yet listed |
| Owner | Assigned person or team | Assigned manager, often a lead |
| Counted in the baseline | Yes, as committed work | Yes, as provisional budget |
| Next step | Execute | Decompose into work packages |
The key point is that a planning package is still a complete, mutually exclusive slice of scope. It is not a placeholder for "TBD". Its deliverable and boundaries are written down, and only the internal detail is deferred.
How the waves work
The planning horizon is how far ahead you plan in detail. A common choice is one iteration, one phase or one to three months. The right length depends on how fast your information improves. The horizon should be short when uncertainty is high and longer when work is stable.
Each wave has the same routine:
- Pick the planning package whose work will start within the next horizon.
- Gather the information that was missing, such as the page audit or the signed vendor contract.
- Decompose the package into work packages, number them under its code, and write dictionary entries.
- Replace the planning package's range estimate with bottom-up estimates.
- Check that the children still add up to the parent's scope, and record the change.
A worked example
Take the website relaunch from earlier chapters. Design is well understood, so its work packages are fully defined. The content migration is not, because the page audit has not happened. Element 1.2.1 stays a planning package with a range estimate.
wbs = {
"code": "1", "name": "Website Relaunch",
"children": [
{"code": "1.1", "name": "Design", "children": [
{"code": "1.1.1", "name": "Page templates",
"kind": "work_package", "estimate_days": 8},
{"code": "1.1.2", "name": "Style guide",
"kind": "work_package", "estimate_days": 3},
]},
{"code": "1.2", "name": "Content", "children": [
{"code": "1.2.1", "name": "Migrated pages",
"kind": "planning_package", "low_days": 8, "high_days": 20},
]},
],
}
def rollup(node):
"""Return (committed, low, high) days for a node and everything below it."""
children = node.get("children")
if not children:
if node["kind"] == "work_package":
days = node["estimate_days"]
return days, days, days
return 0, node["low_days"], node["high_days"]
totals = [0, 0, 0]
for child in children:
if not child["code"].startswith(node["code"] + "."):
raise ValueError(f"{child['code']} is not under {node['code']}")
for i, value in enumerate(rollup(child)):
totals[i] += value
return tuple(totals)
committed, low, high = rollup(wbs)
print(f"committed={committed}, total range={low}-{high}")
# committed=11, total range=19-31The function reports committed effort and the range of the whole project separately. A sponsor reading "19 to 31 days" gets an honest picture. A single "21 days" would hide the fact that 1.2.1 is a guess.
Once the audit shows 120 reusable pages, you decompose 1.2.1 and replace the planning package:
code: "1.2.1"
name: Migrated pages
kind: planning_package
description: Reusable existing pages converted to the new templates and loaded into the new site.
deliverable: Migrated pages live in the staging environment
acceptance_criteria:
- All pages on the approved audit list are present and render correctly
responsible: Content lead
estimate_range_days: [8, 20]
decompose_by: 2026-12-15
decomposition_trigger: Page audit complete and signed off
excluded: New landing pages (see 1.2.2)The decompose_by date and the decomposition_trigger matter. Without them a planning package can sit untouched until the work is due.
Edge cases and failure modes
- Planning packages that never turn into work packages. Give each one an owner, a trigger and a date. Review the list at every status meeting.
- Hiding risk in the range. A range of 8 to 20 days is honest. A range of 5 to 80 days says you have not analyzed the work, and the package needs more discovery first.
- Planning everything as a planning package. Rolling wave is for work that is genuinely uncertain. Using it on well-understood work avoids the effort of planning and removes the baseline's ability to detect variance.
- Dropping scope while deferring detail. Every planning package must still be part of the parent's 100%. If a planning package has no written deliverable, it is a hole in the WBS.
- Silent changes. Replacing a planning package with work packages can change the total. If the new total falls outside the old range, or the scope boundary moves, treat it as a change request, not a quiet edit. Within the range, record it as normal planning.
- Contract and funding limits. Fixed-price contracts and fixed budgets may require firm figures. In that case, hold contingency for the planning packages and say so in the plan.
Checking your result
After each wave, run these checks:
- Every leaf of the WBS is either a work package or a planning package.
- Every planning package has a deliverable, an owner, a range estimate, a trigger and a date.
- Children of a decomposed package add up to the old package's scope, and their codes extend its code.
- The rolled-up committed total has risen, and the provisional range has narrowed.
Exercise
A WBS contains element 3.2.4 "Partner payment integration". The partner's API specification will not be released for two months. The team wants to delete 3.2.4 from the WBS until then, to keep the baseline clean. What should they do instead, and what must the element contain?
Show answer
Keep 3.2.4 in the WBS as a planning package, because deleting it would violate the 100% rule and leave part of the scope outside the baseline. It needs a written deliverable and exclusions so that it does not overlap other elements, an owner, a range estimate for the provisional budget, a decomposition trigger such as the API specification being released, and a date by which it will be decomposed into work packages numbered 3.2.4.1, 3.2.4.2 and so on. When the trigger occurs, replace the range with bottom-up estimates and record any change outside the original range through change control.