Sub topic 17
Common mistakes and how to avoid them
This chapter assumes you can already write a scope statement and decompose it into a WBS. You should know the 100% rule, work packages, hierarchical codes, the WBS dictionary and rolled-up estimates. Here you will learn to recognize the errors that most often damage a WBS and to catch them before they reach the schedule and budget.
Why WBS errors are expensive
Every later artifact is built on the WBS. The schedule, the cost baseline, responsibility assignments and status reports all hang from its elements. A missing element becomes unplanned work. An overlapping element becomes double-counted cost or a dispute about who owns the work. A vague element becomes a status line that stays "80% done" for weeks. Fixing these early costs minutes. Fixing them after the baseline is approved costs a change request.
Mistake 1: Naming activities instead of deliverables
A WBS element names a thing the project produces, not an action. "Design pages" and "Write content" describe effort. "Page templates" and "Migrated pages" describe outputs that can be inspected and accepted.
Activity names cause two problems. They invite you to list steps in time order, which turns the WBS into a half-built schedule. They also hide the completion test, because you cannot say when "testing" is finished, but you can say when "Approved test report" exists.
Fix: name each element with a noun phrase, and ask "what would I hand over or show to prove this is done?" Verbs belong in the activity list that you derive from each work package later.
Mistake 2: Gaps and overlaps
The 100% rule says the children of an element must cover all of its scope. Mutual exclusivity says no scope may appear under two elements.
- A gap usually appears when a team decomposes only the work it thinks about. Typical forgotten items are project management, training, data migration, documentation and handover.
- An overlap usually appears when two elements describe the same output from different angles, such as "Reports" under Software and "Reporting module" under Training.
Fix: compare the WBS against the scope statement line by line, once to find scope with no home and once to find scope with two homes. Use the "excluded" field in the dictionary to record where neighboring work lives, as in "Content writing (see 1.2)".
Mistake 3: Wrong depth
Depth errors go in both directions.
| Symptom | Cause | Fix |
|---|---|---|
| Work package takes months and cannot be tracked | Stopped decomposing too early | Split until one owner can estimate and report progress on it |
| Hundreds of one-hour items | Decomposed past useful control | Merge into packages you would actually track |
| Parent with exactly one child | Child restates the parent, or a sibling is missing | Merge the levels or add the missing sibling |
| Some branches at level 3, others at level 7 | Uneven detail | Acceptable if each leaf is a trackable package, but check that shallow branches are not hiding risk |
Branches do not need equal depth. A well-understood deliverable may need fewer levels than a risky one. What matters is that every leaf can be estimated, assigned and verified.
Mistake 4: Mixing organizing logic on one level
If level 2 mixes deliverables ("Design"), phases ("Testing phase") and departments ("Marketing team"), the same work can fit several elements and the 100% check becomes unreliable. Pick one organizing principle per level. A hybrid is fine, such as phases at level 2 and deliverables below, as long as each level follows a single rule.
Mistake 5: Inconsistent codes and thin dictionary entries
Codes should be hierarchical, so a child's code begins with its parent's code plus a dot. If "2.1" sits under "1.3", reports and rollups will misplace the element. Reusing a code after deleting an element is also risky, because old status reports and cost records then point at the wrong thing. Retire codes instead of recycling them.
A dictionary entry that says only "Build the site" gives no acceptance criteria, owner or exclusions. That makes the scope dispute inevitable. Every work package needs a deliverable, acceptance criteria, a responsible person, an estimate and exclusions.
Mistake 6: Estimates in the wrong place
Only leaf work packages should carry estimates. If a parent also has its own number, the rollup double-counts or hides a missing child. Contingency and management reserve should be shown separately, not buried in a leaf.
Mistake 7: Built alone, then left to rot
A WBS written by one person misses knowledge that the people who do the work have. Review it with the team, and have each work package owner confirm their entries. After approval, it becomes a baseline. Scope changes go through change control, and the WBS and dictionary are updated in the same step. A WBS that no longer matches the work is worse than none, because people still trust it.
Automating the mechanical checks
Some errors can be detected by a script. The checker below flags verb-led names, parents with their own estimates, single-child parents, leaves without estimates and codes that are not under their parent.
VERBS = {"design", "build", "write", "test", "create", "develop",
"implement", "migrate", "configure"}
def check(node, problems=None):
if problems is None:
problems = []
code, name = node["code"], node["name"]
children = node.get("children", [])
if name.split()[0].lower() in VERBS:
problems.append(f"{code}: '{name}' starts with a verb; name a deliverable")
if not children:
if "estimate_days" not in node:
problems.append(f"{code}: work package has no estimate")
return problems
if "estimate_days" in node:
problems.append(f"{code}: parent carries its own estimate")
if len(children) == 1:
problems.append(f"{code}: only one child; a single child adds no information")
for child in children:
if not child["code"].startswith(code + "."):
problems.append(f"{child['code']}: not under {code}")
check(child, problems)
return problems
wbs = {
"code": "1", "name": "Website Relaunch",
"children": [
{"code": "1.1", "name": "Design pages", "children": [
{"code": "1.1.1", "name": "Page templates", "estimate_days": 8},
]},
{"code": "1.2", "name": "Content", "estimate_days": 5, "children": [
{"code": "1.2.1", "name": "Migrated pages"},
]},
{"code": "1.3", "name": "Platform", "children": [
{"code": "1.3.1", "name": "Hosting environment", "estimate_days": 4},
{"code": "2.1", "name": "Content management configuration", "estimate_days": 3},
]},
],
}
for problem in check(wbs):
print(problem)Running it prints:
1.1: 'Design pages' starts with a verb; name a deliverable
1.1: only one child; a single child adds no information
1.2: parent carries its own estimate
1.2: only one child; a single child adds no information
1.2.1: work package has no estimate
2.1: not under 1.3A review sequence
Run the checks in an order that finds the costly errors first.
Summary of fixes
- Name outputs, not actions.
- Check coverage and overlap against the scope statement.
- Stop decomposing when a package can be estimated, assigned and verified.
- Use one organizing rule per level.
- Keep codes hierarchical and never reuse them.
- Put estimates on leaves only.
- Validate with the team and change the WBS only through change control.
Exercise
A WBS has element 3 "Training" with children 3.1 "Training materials" and 3.2 "Run workshops". Element 2 "Documentation" has a child 2.3 "User guide", and 3.1 also lists the user guide as part of the training materials. Name the two mistakes you can see and give one fix for each.
Show answer
"Run workshops" starts with a verb, so it names an activity. Rename it to a deliverable such as "Delivered workshop sessions" or "Attendance and feedback record". The user guide appears under both 2.3 and 3.1, which breaks mutual exclusivity and risks double-counted cost. Keep it under one element, for example 2.3, and put "Excluded: user guide (see 2.3)" in the dictionary entry for 3.1.
Exercise
The checker prints "1.2: parent carries its own estimate" for a parent with 5 days and a child estimated at 6 days. What should you do before changing any numbers?
Show answer
Find out whether the 5 days stands for work not covered by any child (a gap, which needs a new child element) or is an older, superseded estimate of the same scope (which should be removed). Only leaf work packages carry estimates, so the parent's total should come from the rollup of its children.