Think in deliverables, not activities
This chapter assumes you know the basic project vocabulary: project, deliverable, stakeholder and milestone. It also assumes you have a written scope statement, or something equivalent, that says what the project must produce. The previous chapter covered where that scope comes from. This chapter covers the habit that makes a work breakdown structure (WBS) work: naming the things the project produces instead of the things people do.
Why the WBS is about outputs
A WBS divides the total scope of a project into smaller pieces of scope. Scope means what the project delivers, so each element of the WBS should name a part of the product, service or result. It should not name a piece of effort.
An activity is something people do over time, such as "write the style guide". A deliverable is something that exists when the work is done, such as "Style guide". The difference matters for three reasons:
- A deliverable can be inspected. You can hand it to the product owner and ask whether it is acceptable. An activity can only be reported as started, in progress or finished.
- A deliverable is complete or incomplete. An activity such as "testing" can go on indefinitely without anyone agreeing it is done.
- Deliverables hide no method. "Page templates" does not say whether they are built in-house, bought or generated. That leaves the team free to choose the method later, while the scope stays fixed.
Activities do belong in the project plan. They come later, when the schedule is built from the work packages. The WBS answers "what must exist?" and the schedule answers "what do we do, and in what order, to make it exist?"
Naming rules
Most WBS reviews end up checking the same few rules.
- Use a noun phrase. "Page templates", "Migrated pages" and "Hosting environment" are good. "Build templates" is not.
- Use a past participle when it helps. "Migrated pages" and "Approved templates" describe a state, which makes the finished condition clear.
- Make the name specific enough to be accepted or rejected. "Content" is a fine parent. As a leaf it is too vague, because nobody can say when it is done.
- Keep names unique and short. Two elements both called "Testing" under different parents cause confusion in reports.
The name is not the whole definition. A later chapter covers the WBS dictionary, which holds the description and acceptance criteria that make a short name unambiguous.
Rewriting activities as deliverables
Rewriting is mechanical in most cases. Ask "what exists when this is finished?" and name that.
| Activity wording | Deliverable wording | What exists at the end |
|---|---|---|
| Design the page layouts | Page templates | Approved template files |
| Write the style guide | Style guide | A published document |
| Move the old articles | Migrated pages | Pages live on the new platform |
| Set up the server | Hosting environment | A running, accessible environment |
| Do project management | Project plan and status reports | A plan and a series of reports |
The last row shows an unusual case. Management work does not produce a product, but a WBS still includes it. The way to include it is to name its outputs, here "Project plan and status reports", as in the sample outline in this tutorial's Website Relaunch example. Leaving management out would break the rule that the WBS covers all the work, which a later chapter treats in detail.
A worked derivation
Suppose a scope statement for the website relaunch says: "Replace the current site with a redesigned site on a new hosting platform. Existing articles are moved across, three new landing pages are added, and the site is managed by the marketing team through a content management system."
Read it once and underline every thing that must exist at the end:
- A redesigned look: page templates and a style guide.
- Existing articles on the new site: migrated pages.
- Three new landing pages.
- A hosting platform.
- A content management system the marketing team can use: its configuration.
Group these under parents that are themselves deliverables or groups of deliverables, and add management. The result is the outline below.
1 Website Relaunch
1.1 Design
1.1.1 Page templates
1.1.2 Style guide
1.2 Content
1.2.1 Migrated pages
1.2.2 New landing pages
1.3 Platform
1.3.1 Hosting environment
1.3.2 Content management configuration
1.4 Project management
1.4.1 Project plan and status reportsEvery leaf is a noun phrase, and none of them says how the work is done. "Design" at level 2 is a grouping label that is also a noun, which is acceptable as long as everything beneath it is a concrete output.
placeholderPlaceholder removed below.
The question to ask at each step
The diagram shows the check you apply to every candidate element as you write it.
Checking names automatically
A script cannot judge a WBS, but it can catch the most common slip, a leading verb. The function below flags names whose first word is a typical activity verb.
ACTIVITY_VERBS = {
"build", "create", "design", "develop", "write", "test",
"configure", "migrate", "install", "review", "plan", "manage",
}
def flag_activity_names(names):
"""Return the names whose first word looks like an activity verb."""
flagged = []
for name in names:
words = name.split()
if words and words[0].lower() in ACTIVITY_VERBS:
flagged.append(name)
return flagged
candidates = [
"Page templates",
"Design page templates",
"Write landing pages",
"Style guide",
"Test the site",
]
print(flag_activity_names(candidates))
# ['Design page templates', 'Write landing pages', 'Test the site']This is only a heuristic. It would also flag a legitimate deliverable such as "Test report" if you wrote it as "Test results" with a verb-like first word, and it misses verbs that are not in its list. Use it as a prompt for a human review, not as a gate.
Edge cases
Services and results. Not every project produces a physical thing. A training project's deliverables might be "Course materials" and "Trained staff", where the second names a result. Name the state that the customer will accept, not the delivery effort.
Ongoing work. Items such as "quality assurance" or "risk management" are efforts. Express them through what they produce, such as "Test report" or "Risk register", or group them under a management element with named outputs.
Phases. A phase like "Design" is a time-based grouping. Chapter 8 compares deliverable-based and phase-based organization. For now, note that even a phase-based WBS should still name deliverables beneath each phase.
Intermediate deliverables. Some outputs exist only to feed other work, such as an approved requirements list. They are still legitimate if they are accepted by someone and needed by the project.
Common mistakes in this step
- Mixing activities and deliverables at the same level. "Page templates" next to "Testing" gives a list with no consistent logic.
- Using vague grouping names as leaves. "Content" is a fine parent but cannot be a leaf, since nothing can be accepted against it.
- Hiding the method in the name. "Templates built in React" fixes a solution decision into the scope. Put it in the dictionary as an assumption or constraint if it is a real requirement.
- Naming by who does the work. "Design team work" describes a group, not an output. Organizational structure is covered later, under responsibility assignment.
Exercise
A draft WBS for a customer-support rollout has these level-2 elements: "Train agents", "Knowledge base articles", "Configure ticketing tool", "Go-live support". Rewrite each one as a deliverable, and say which element needs the most thought and why.
Show answer
"Train agents" becomes "Trained agents" (or "Training completion records"), "Knowledge base articles" is already a deliverable, "Configure ticketing tool" becomes "Configured ticketing tool", and "Go-live support" becomes an output such as "Go-live support report" or "Stabilized service at handover". "Go-live support" needs the most thought. It is open-ended effort, so you must decide what the customer will accept as finished, for example a defined period of operation with agreed performance targets, and name that result.
Exercise
Why is "Project management" allowed as a WBS element even though it sounds like an activity?
Show answer
It is allowed because it is a grouping whose leaves name outputs, such as "Project plan and status reports". The WBS must cover all the work in the scope, including management work, so the element stays. Its leaves must still be deliverables.