Sub topic 8
Choosing how to organize the first levels
This chapter assumes you know what a WBS is, can state the 100% rule, and have a scope statement to work from. The decision here is how to split level 2, the first split below the project name. Everything beneath it inherits that choice, so it is worth making on purpose.
Why level 2 matters
Level 1 is the whole project. Level 2 sets the main grouping that every later element sits under. It decides which questions the WBS answers easily. It also decides which questions need extra work, such as "what does this cost by phase?" or "what is left on the platform?".
You have three common options:
- Deliverable-based: level 2 elements are things the project produces.
- Phase-based: level 2 elements are stages of the project's life, such as discovery, build and cutover.
- Hybrid: you mix the two, usually phases at level 2 with deliverables below, or deliverables at level 2 with a separate project management element.
Other groupings exist, such as by geography, business unit, or subproject. They follow the same rules, so the three above are enough to reason with.
Deliverable-based organization
Each level 2 element is a deliverable or a group of related deliverables. This is the usual default, and it is the one used in this tutorial's running example:
1 Website Relaunch
1.1 Design
1.2 Content
1.3 Platform
1.4 Project managementIt works well because it ties directly to the scope statement. A deliverable either exists and is accepted, or it does not. That makes the WBS easy to check against the 100% rule: read the scope statement, and every promised deliverable should land under exactly one level 2 element. Deliverable-based structures also suit teams organized by skill, because "Design" and "Platform" map to people who do that work.
Its weakness is time. The structure says nothing about order, so you need the schedule to show that the style guide comes before the templates.
Phase-based organization
Each level 2 element is a stage of the project:
1 Website Relaunch
1.1 Discovery
1.2 Construction
1.3 CutoverPhases are familiar to stakeholders and match funding gates, such as "approve construction budget". They are also natural when the project runs as a series of distinct stages, each with its own sign-off.
The risk is that phases describe when, not what. Work packages under different phases can end up describing the same deliverable. "Draft templates" under Discovery and "Finish templates" under Construction both claim part of one deliverable, and the elements no longer exclude each other. Phase-based structures also drift toward activity names ("Testing", "Meetings"), which breaks the deliverable orientation from earlier chapters.
A phase-based level 2 is sound when each phase produces its own distinct deliverables. A construction project with separate design, procurement and installation stages is a good example.
Hybrid organization
A hybrid structure uses phases at level 2 and puts deliverables beneath them:
1 Website Relaunch
1.1 Discovery
1.1.1 Style guide
1.2 Construction
1.2.1 Page templates
1.2.2 Migrated pages
1.2.3 Hosting environment
1.3 Cutover
1.3.1 Redirect mapHybrids are common in long projects where management reviews by phase but teams work by deliverable. Use one rule for all siblings at any level. If level 2 is phases, every level 2 element must be a phase. Putting "Design" (a deliverable group) beside "Construction" (a phase) mixes categories, and the 100% rule becomes hard to check.
Project management usually sits as its own level 2 element, even in a deliverable-based WBS. It is a deliverable in its own right: the plan, status reports and closure documents.
The same work, grouped two ways
The work packages are the same under either structure. Only the grouping changes. This script shows it:
from collections import defaultdict
work_packages = [
{"name": "Page templates", "deliverable": "Design", "phase": "Construction"},
{"name": "Style guide", "deliverable": "Design", "phase": "Discovery"},
{"name": "Migrated pages", "deliverable": "Content", "phase": "Construction"},
{"name": "New landing pages", "deliverable": "Content", "phase": "Construction"},
{"name": "Hosting environment", "deliverable": "Platform", "phase": "Construction"},
{"name": "Redirect map", "deliverable": "Platform", "phase": "Cutover"},
]
def group_by(items, key):
groups = defaultdict(list)
for item in items:
groups[item[key]].append(item["name"])
return dict(groups)
print(group_by(work_packages, "deliverable"))
print(group_by(work_packages, "phase"))It prints:
{'Design': ['Page templates', 'Style guide'], 'Content': ['Migrated pages', 'New landing pages'], 'Platform': ['Hosting environment', 'Redirect map']}
{'Construction': ['Page templates', 'Migrated pages', 'New landing pages', 'Hosting environment'], 'Discovery': ['Style guide'], 'Cutover': ['Redirect map']}Each work package carries one value per grouping, so it appears exactly once in either view. That is what mutual exclusivity requires. Choosing level 2 means choosing which view is the structure. The other view can be recovered by tagging work packages, for example in a spreadsheet column or a project tool field.
Comparing the approaches
| Criterion | Deliverable-based | Phase-based | Hybrid |
|---|---|---|---|
| Link to scope statement | Direct | Indirect | Direct below level 2 |
| Shows sequence | No | Yes | Partly |
| Risk of overlapping elements | Low | High | Medium |
| Fits stage-gate funding | Needs extra tagging | Natural | Natural |
| Typical use | Product, software, content projects | Short, strongly staged projects | Large, long projects |
A decision procedure
Apply it in this order:
- List the main deliverables from the scope statement. If you can name them, start with a deliverable-based structure.
- Ask who reads the WBS. If sponsors approve money or scope at the end of each stage, phases at level 2 will fit their reviews.
- Check each phase for its own deliverables. If two phases would hold pieces of the same deliverable, keep deliverables at level 2.
- Add project management as its own element.
- Test the choice by assigning five or six real work packages. If you keep hesitating over which parent, the categories overlap.
Common mistakes at this stage
- Mixing categories at one level, such as "Design", "Construction" and "Testing" as siblings. The first is a deliverable group, and the other two are phases or activities.
- Using verbs at level 2 ("Build the site"). Level 2 names should be nouns, things that exist when the work is done.
- Dropping project management. The effort of planning and reporting is real scope, and leaving it out breaks the 100% rule.
- Repeating a deliverable under several phases. If a template appears under both Discovery and Construction, you have two elements for one deliverable.
- Choosing by habit instead of by the project. Reusing last project's phase structure on a product-based project hides the deliverables.
Exercise
Exercise
A project will deliver a mobile app, a back-end service and user training. The sponsor releases funds at three gates: Plan approved, Build approved, Launch approved. Teams are organized as a mobile team, a service team and a trainer. Which level 2 organization do you choose, and what do you check before committing?
Show answer
Use a hybrid or a deliverable-based structure with phase tags, and decide by checking overlap. The deliverables (Mobile app, Back-end service, User training) map to the teams and to the scope statement, so they make a good level 2. The sponsor's gates then become a tagging field on work packages, not a second hierarchy. If each gate would have distinct deliverables of its own, a phase level 2 with deliverables beneath it is also sound. Before committing, assign five real work packages, for example "API specification" and "Training handbook", to a parent. Confirm each fits exactly one parent, and add a Project management element so the 100% rule still holds.